Chapter 5, Problem 1CTE
Summary Introduction
To determine: The recommendation to increase the number of repairs per day based on the investigation of manager regarding quality problems, absenteeism, or
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted. Utilization refers to the effective use of the resource or the supply. It is the action of practically using the available materials.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A computer repair service has a design capacity of 80 repairs per day. Its effective capacity, however, is 64 repairs per day, and its actual output is 62 repairs per day. The manager would like to increase the number of repairs per day. Which of the following factors would you recommend that the manager investigate: quality problems, absenteeism, or scheduling and balancing? Explain your reasoning.
Pendryl Office Supplies is evaluating the profitability of leasing a photocopier for its customers to use on a self serve basis at 10 cents/copy. The copier may be leased for $300 per month plus 1.5 cents per copy on a full service contract. Pendryl can purchase paper at $5 per 500 sheet ream. Toner costs $100 per bottle, which in normal use will last for 5000 pages. Pendryl thinks that there are additional other costs of 0.5 cents per copy.
A. How many copies per month must be sold in order to break even? (6000 copies/month)
B. What will be the increase in monthly profit for each 1000 copies sold above the break-even point? ($50 per month)
The following data for 2021 are available for Canlubang AutomotiveCompany which manufactures and sells a single automotive product line.Unit selling price = 4Unit variable cost = 20Total fixed cost = 200,000a.) What is the break-even point in units for the current year?b.) Prepare a break-even chart for the operation in 2021 intervals of 5,000 units from 5,000to 30,000 units (show complete solution)
Chapter 5 Solutions
Operations Management
Ch. 5.8 - Explain the meaning of the phrase Hours versus...Ch. 5.8 - Prob. 1.2RQCh. 5.8 - Prob. 1.3RQCh. 5.8 - Prob. 1.4RQCh. 5.8 - Prob. 1.5RQCh. 5.S - Prob. 1DRQCh. 5.S - Prob. 2DRQCh. 5.S - Explain the term bounded rationality.Ch. 5.S - Prob. 4DRQCh. 5.S - Prob. 5DRQ
Ch. 5.S - What information is contained in a payoff table?Ch. 5.S - Prob. 7DRQCh. 5.S - Prob. 8DRQCh. 5.S - Under what circumstances is expected monetary...Ch. 5.S - Explain or define each of these terms: a. Laplace...Ch. 5.S - Prob. 11DRQCh. 5.S - Prob. 12DRQCh. 5.S - Prob. 13DRQCh. 5.S - Prob. 1PCh. 5.S - Refer to problem1. Suppose after a certain amount...Ch. 5.S - Refer to Problems 1 and 2 Construct a graph that...Ch. 5.S - Prob. 4PCh. 5.S - Prob. 5PCh. 5.S - The lease of Theme Park, Inc., is about to expire....Ch. 5.S - Prob. 7PCh. 5.S - Prob. 8PCh. 5.S - Prob. 9PCh. 5.S - A manager must decide how many machines of a...Ch. 5.S - Prob. 11PCh. 5.S - Prob. 12PCh. 5.S - Prob. 13PCh. 5.S - Prob. 14PCh. 5.S - Give this payoff table: a. Determine the range of...Ch. 5.S - Prob. 16PCh. 5.S - Repeat all parts of problem 16, assuming the value...Ch. 5.S - Prob. 18PCh. 5 - Prob. 1DRQCh. 5 - Prob. 2DRQCh. 5 - How do long-term and short-term capacity...Ch. 5 - Give an example of a good and a service that...Ch. 5 - Give some example of building flexibility into...Ch. 5 - Why is it important to adopt a big-picture...Ch. 5 - What is meant by capacity in chunks, and why is...Ch. 5 - Prob. 8DRQCh. 5 - How can a systems approach to capacity planning be...Ch. 5 - Prob. 10DRQCh. 5 - Why is it important to match process capabilities...Ch. 5 - Briefly discuss how uncertainty affects capacity...Ch. 5 - Prob. 13DRQCh. 5 - Prob. 14DRQCh. 5 - Prob. 15DRQCh. 5 - Prob. 16DRQCh. 5 - What is the benefit to a business organization of...Ch. 5 - Prob. 1TSCh. 5 - Prob. 2TSCh. 5 - Prob. 3TSCh. 5 - Prob. 1CTECh. 5 - Prob. 2CTECh. 5 - Identify four potential unethical actions or...Ch. 5 - Any increase in efficiency also increases...Ch. 5 - Prob. 1PCh. 5 - In a job shop, effective capacity is only 50...Ch. 5 - A producer of pottery is considering the addition...Ch. 5 - A small firm intends to increase the capacity of a...Ch. 5 - A producer of felt-tip pens has received a...Ch. 5 - A real estate agent is considering changing her...Ch. 5 - A firm plans to begin production of a new small...Ch. 5 - A manager is trying to decide whether to purchase...Ch. 5 - A company manufactures a product using two machine...Ch. 5 - A company must decide which type of machine to...Ch. 5 - Prob. 11PCh. 5 - A manager must decide how many machines of a...Ch. 5 - Prob. 13PCh. 5 - The following diagram shows a four-step process...Ch. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - A new machine will cost 18,000, butt result it...Ch. 5 - Remodelling an office will cost 25,000 and will...Ch. 5 - Prob. 1CQCh. 5 - Prob. 2CQCh. 5 - Prob. 3CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A small language school has a class offering capacity of 80 students per day. Its effective capacity, however, is 64 students per day, and its actual output is 62 students per day. The operational manager would like to increase the number of students per day. Which of the following factors would you recommend that the manager investigate: quality problems, absenteeism, or scheduling and balancing? Explain your reasoning.A small language school has a class offering capacity of 80 students per day. Its effective capacity, however, is 64 students per day, and its actual output is 62 students per day. The operational manager would like to increase the number of students per day. Which of the following factors would you recommend that the manager investigate: quality problems, absenteeism, or scheduling and balancing? Explain your reasoning.arrow_forwardMajestic Corporation provides call-center ordering services for Essential Oils magazine. Majestic receives an annual fee of $200,000 for providing such services and is also eligible to receive a performance bonus up to $65,000 if the average customer wait times are below certain thresholds at the end of the year. Using historical results as well as current expectations, Majestic estimates the chances of achieving the different performance bonuses as shown in the table here. Assume there are NO revenue constraints, and the entity uses the expected value approach to record variable consideration when recognizing revenue during the period. Which is the amount of the performance bonus management can recognize in the transaction price? Average wait times Performance Bonus % Chance of Achieving $65,000 15% < 1 minute < 2 minutes < 3 minutes < 4 minutes < 5 minutes $45,000 $25,000 $5,000 0 10% 50% 20% 5% a. Management would include the variable consideration in the transaction price in the…arrow_forwardKilmer Company's customer demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units: Actual run time this week Machine time available per week Actual run rate this week Ideal run rate Defect-free output this week Total output this week (including defects) 1-a. Utilization rate 1-b. Efficiency rate. 1-c. Quality rate 1-d. Overall equipment effectiveness 2-a. Utilization loss in units 2-b. Efficiency loss in units 2-c. Quality loss in units 23,310 minutes 25,900 minutes 0.90 8.00 units per minute 10 units per minute Required: 1. and 2. With respect to the company's overall equipment effectiveness, calculate the following: Note: Do not round intermediate calculations. Round final answers to 2 decimal places and "Units" answers to the nearest whole number. 149,184 units 186,480 unitsarrow_forward
- A seed company has a design capacity of 80 metric tonnes per day. It's effective capacity, However, is 64metric tonnes per day, and it's actual output is 62 metric tonnes per day. The operations manager would like to increase the number of Metric tonnes per day. Which of the following factors would you recommend that the operations manager investigate: quality problems, absenteeism, or scheduling?arrow_forwardWilliams Performance Co. manufactures sports cars. After making a sale, the salesperson sends thecar to be detailed before the customer takes it home. Detailing the car takes 30 minutes at a cost of$15 per hour for direct labor and $5 per car for materials. If the company is open 5 days per week andsells an average of five cars per day, what is the average cost per 5-day week for detailing cars?arrow_forwardA restaurant earns $3,950 in sales from 64 guests for Monday’s dinner. Four (4) back-of-the-house employees work the full three-hour dinner shift that night. What is the back-of-the-house team’s sales per person-hour rate? What is the back-of-the-house team’s covers per person-hour rate?arrow_forward
- Hospital output has frequently been measured by bed day, or by number of cases admitted to or discharged from hospitals. Overtime, however, the typical admitted patient receives a greater intensity of services primarily attributable to technology. If you want to compare year-over year outputs you must account for this changes. What is the term we use to account for these adjustments so that we can compare apples to apples? A. Measure of effectiveness B. Output adjustments C. Intensity adjustments D. Cross-sectional comparisonsarrow_forwardA company with 617 employees had the following expenses this year (2018): 14 hospitalizations, $5,600 Cost (each) What is the total cost of 14 hospitalizations?arrow_forwardexplain the FIVE (5)ways to produce an added value to customer service.arrow_forward
- A computer repair service has a design capacity of 80 repairs per day. Its effective capacity, however, is 64 repairs per day, and its actual output is 62 repairs per day. The manager would like to increase the number of repairs per day. Which of the following factors should the manager investigate: quality problems, absenteeism, or scheduling and balancing? Explain .arrow_forwardDetermine the utilization and the efficiency for each of these situations:a. A loan processing operation that processes an average of 7 loans per day. The operation has a design capacity of 10 loans per day and an effective capacity of 8 loans per day.b. A furnace repair team that services an average of four furnaces a day if the design capacity is six furnaces a day and the effective capacity is five furnaces a day.c. Would you say that systems that have higher efficiency ratios than other systems will always have higher utilization ratios than those other systems? Explain.arrow_forwardIf an air-conditioned space has a temperture decrease of 2 degrees Celcius, and the relative humidity remains the same, how much more cost effective would that be over a summer.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY