Textbook Question
Chapter 5, Problem 12P
A manager must decide how many machines of a cdertain type to purchase. Each machine can process 100 customers per day. One machine will result in a fixed cost of $2,000 per day, while two machines will result in a fixed cost of $3,800 per day. Variable costs will be $20 per customer, and revenue will be $45 per customer.
a. Determine the break-even point for each range.
b. If estimated demand is 90 to 120 customers per day, how many machines should be purchased?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A manager must decide how many machines of a certain type to purchase. Each machine can process 100 customers per day. One
machine will result in a fixed cost of $2,100 per day, while two machines will result in a fixed cost of $3,900 per day. Variable costs will
be $17 per customer, and revenue will be $45 per customer.
a. Determine the break-even point for each range. (Round your answers to the next whole number.)
One machine
Two machines
4,500
b. If estimated demand is 90 to 120 customers per day, how many machines should be purchased?
IIn a job shop, effective capacity is only 69 percent of design capacity, and actual output is 76 percent of effective output. What design capacity would be
needed to achieve an actual output of 13 jobs per week? What is its effective capacity?
a. The Design Capacity needed to achieve the required actual job outputs =Blank 1 (round to whole number)
b. The Effective Capacity needed to achieve the required actual job outputs = Blank 2 (round to whole number)
Blank 1
Blank 2
Add your answer
Add your answer
A machine was purchased one year ago. Presently, the market value is $16,000 and it declines by $3,000 every
year. For the next 3 years, the maintenance costs are as follows:
Year Maintenance costs
1
$890
$1,290
$1,690
2
3
What is the marginal cost of extending the service for the 3rd
year?
A. $2,690
В. $5,490
C. $4,690
D. $5,690
Chapter 5 Solutions
Operations Management
Ch. 5.8 - Explain the meaning of the phrase Hours versus...Ch. 5.8 - Prob. 1.2RQCh. 5.8 - Prob. 1.3RQCh. 5.8 - Prob. 1.4RQCh. 5.8 - Prob. 1.5RQCh. 5.S - Prob. 1DRQCh. 5.S - Prob. 2DRQCh. 5.S - Explain the term bounded rationality.Ch. 5.S - Prob. 4DRQCh. 5.S - Prob. 5DRQ
Ch. 5.S - What information is contained in a payoff table?Ch. 5.S - Prob. 7DRQCh. 5.S - Prob. 8DRQCh. 5.S - Under what circumstances is expected monetary...Ch. 5.S - Explain or define each of these terms: a. Laplace...Ch. 5.S - Prob. 11DRQCh. 5.S - Prob. 12DRQCh. 5.S - Prob. 13DRQCh. 5.S - Prob. 1PCh. 5.S - Refer to problem1. Suppose after a certain amount...Ch. 5.S - Refer to Problems 1 and 2 Construct a graph that...Ch. 5.S - Prob. 4PCh. 5.S - Prob. 5PCh. 5.S - The lease of Theme Park, Inc., is about to expire....Ch. 5.S - Prob. 7PCh. 5.S - Prob. 8PCh. 5.S - Prob. 9PCh. 5.S - A manager must decide how many machines of a...Ch. 5.S - Prob. 11PCh. 5.S - Prob. 12PCh. 5.S - Prob. 13PCh. 5.S - Prob. 14PCh. 5.S - Give this payoff table: a. Determine the range of...Ch. 5.S - Prob. 16PCh. 5.S - Repeat all parts of problem 16, assuming the value...Ch. 5.S - Prob. 18PCh. 5 - Prob. 1DRQCh. 5 - Prob. 2DRQCh. 5 - How do long-term and short-term capacity...Ch. 5 - Give an example of a good and a service that...Ch. 5 - Give some example of building flexibility into...Ch. 5 - Why is it important to adopt a big-picture...Ch. 5 - What is meant by capacity in chunks, and why is...Ch. 5 - Prob. 8DRQCh. 5 - How can a systems approach to capacity planning be...Ch. 5 - Prob. 10DRQCh. 5 - Why is it important to match process capabilities...Ch. 5 - Briefly discuss how uncertainty affects capacity...Ch. 5 - Prob. 13DRQCh. 5 - Prob. 14DRQCh. 5 - Prob. 15DRQCh. 5 - Prob. 16DRQCh. 5 - What is the benefit to a business organization of...Ch. 5 - Prob. 1TSCh. 5 - Prob. 2TSCh. 5 - Prob. 3TSCh. 5 - Prob. 1CTECh. 5 - Prob. 2CTECh. 5 - Identify four potential unethical actions or...Ch. 5 - Any increase in efficiency also increases...Ch. 5 - Prob. 1PCh. 5 - In a job shop, effective capacity is only 50...Ch. 5 - A producer of pottery is considering the addition...Ch. 5 - A small firm intends to increase the capacity of a...Ch. 5 - A producer of felt-tip pens has received a...Ch. 5 - A real estate agent is considering changing her...Ch. 5 - A firm plans to begin production of a new small...Ch. 5 - A manager is trying to decide whether to purchase...Ch. 5 - A company manufactures a product using two machine...Ch. 5 - A company must decide which type of machine to...Ch. 5 - Prob. 11PCh. 5 - A manager must decide how many machines of a...Ch. 5 - Prob. 13PCh. 5 - The following diagram shows a four-step process...Ch. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - A new machine will cost 18,000, butt result it...Ch. 5 - Remodelling an office will cost 25,000 and will...Ch. 5 - Prob. 1CQCh. 5 - Prob. 2CQCh. 5 - Prob. 3CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A manager must whether to buy machine A or B. Machine costs are as follows: A $52,000 each; B $100,000 each Product forecast and processing times on the machines are as follows Processing Time per unit (minutes) Product Annual Demand A B 1 8,000 2 18,000 3 10,000 Assume that only purchasing costs are being considered. Which machine would have the lowest purchase cost and how many of that machine would be need? Machines operate 8 hours a day 250 days per year. The machines differ in hourly operation costs. The A machines have an hourly operating cost of $12 each and B machines have an hourly operating cost of $30 each. What is the operating cost per year and which alternative should be selected to minimize total cost (for the first year) while satisfying the processing requirements? Edit Format Table 12pt v Paragraph v BIUA ev T?v||: MacBook Air esc 80 888 DII F1 F2 F3 F4 F5 F6 F7 FR @ # $ % 1 2 3 4 5 7 8. Q W E R T Y A S D F G < COarrow_forwardCompute the capacity (i.e. processing rate) for each of the following scenarios. Convertyour answers to parts per hour.a. A four-station line with single-machine stations, where the average processing timesare 15, 20, 10 and 12 minutes, respectively.b. A three-station line where the number of machines at stations 1, 2 and 3 is 2, 6, and3, respectively; and the average processing times are 10, 24 and 18 minutes,respectively.arrow_forwardA manager must decide which type of machine to buy, A, B, or C. Machines costs are as follows: Machine Cost A $40,000 B $30,000 C $80,000 Product forecast, processing times on the machines, and setup times are as follows: Processing Time Per Unit (minutes) Product Annual Demand A B C Setup Times (minutes) Production Lots (units) 1 16,000 3 4 2 20 200 2 12,000 4 5 3 35 100 3 6,000 5 6 3 60 50 4 30,000 2 4 1 15 500 Machines operate 10 hours a day, 250 days a year. The manager wants to have a capacity cushion of 10%. a. Assume that only purchasing costs are being considered. Which machines would have the lowest total cost, and how many of that machines would be needed? b. Consider this additional information: The machines differ in terms of hourly operating costs: The A machines have an hourly operating cost of $11 each, B machines have an hourly operating cost of $10 each, and C machines have an hourly operating cost of $12 each. Which alternative would…arrow_forward
- A computer repair service has a design capacity of 80 repairs per day. Its effective capacity, however, is 64 repairs per day, and its actual output is 62 repairs per day. The manager would like to increase the number of repairs per day. Which of the following factors should the manager investigate: quality problems, absenteeism, or scheduling and balancing? Explain .arrow_forwardAsaparrow_forwardDetermine the utilization and the efficiency for each of these situations:a. A loan processing operation that processes an average of 7 loans per day. The operation has a design capacity of 10 loans per day and an effective capacity of 8 loans per day.b. A furnace repair team that services an average of four furnaces a day if the design capacity is six furnaces a day and the effective capacity is five furnaces a day.c. Would you say that systems that have higher efficiency ratios than other systems will always have higher utilization ratios than those other systems? Explain.arrow_forward
- . A computer repair service has a design capacity of 80 repairs per day. Its effective capacity, however, is 64 repairs per day, and its actual output is 62 repairs per day. The manager would like to increase the number of repairs per day. Which of the following factors would you recommend that the manager investigate: quality problems, absenteeism, or scheduling and balancing? Explain your reasoning.arrow_forwardExplain capacity planning concepts with examples ?arrow_forwardIn a job shop, effective capacity is only 50 percent of design capacity, and actual output is80 percent of effective output. What design capacity would be needed to achieve an actual output c eight jobs per week?arrow_forward
- someone solve this question but do not use excel for this questionarrow_forwardWhat is CAPACITY REQUIREMENTS FORECASTING?arrow_forwardThe manager of a car wash must decide whether to have one or two wash lines. One line willmean a fixed cost of RM6000 a month, and two lines will mean a fixed cost of RM11000 amonth. Each line would be able to process 15 cars an hour. Variable costs will be RM3 per car,and revenue will be RM5.95 per car. The manager projects an average demand of between 14and 18 cars an hour. Would you recommend one or two lines? The car wash is open 300 hours amonth.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY