Operations Management
Operations Management
13th Edition
ISBN: 9781259667473
Author: William J Stevenson
Publisher: McGraw-Hill Education
bartleby

Concept explainers

Question
Book Icon
Chapter 5, Problem 11P

a)

Summary Introduction

To determine: The number of machines of each type required to handle the demand and its capacity and the machine that would have lower total cost.

Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.

a)

Expert Solution
Check Mark

Answer to Problem 11P

Two machines are need in type A and type B and one machine is needed in type C. Buying two B machines would have lower total cost.

Explanation of Solution

Given information:

A company should decide whether to buy machine of type A, type B, or type C. The cost of type A machine is $40,000, cost of type B machine is $30,000, and the cost of type C machine is $80,000.

Annual demand and processing unit is given as follows for each product:

ProductAnnual demandProcessing time per unit
A B C
1 16,000 3 4 2
2 12,000 4 4 3
3 6,000 5 6 4
4 30,000 2 2 1

Determine the number of machines of each type required and its capacity:

It is given that the machines will operate 60 minutes per hour, 10 hours per day and 250 days per year.

Determine the minutes available for all types of machine:

It is calculated by multiplying number of days per year, hours per day, and minutes per hour. Hence, the available minutes per year for machine type A, type B, and type C is 150,000 minutes per year.

Available minutes=Number of days per year×Hours per day×Minutes per hour=250×10×60=150,000 minutes per year

Determine the processing requirement of product 1 using machine type A:

It is calculated by multiplying annual demand of product 1 and the processing time per unit on type A. Hence, the processing requirements of product 1 using machine type A is 48,000 minutes.

Processing requirement of product 1=Annual demand×Processing time=16,000×3 minutes=48,000 minutes

Determine the processing requirement of product 2 using machine type A:

It is calculated by multiplying annual demand of product 2 and the processing time per unit on type A. Hence, the processing requirements of product 2 using machine type A is 48,000 minutes.

Processing requirement of product 2=Annual demand×Processing time=12,000×4 minutes=48,000 minutes

Determine the processing requirement of product 3 using machine type A:

It is calculated by multiplying annual demand of product 3 and the processing time per unit on type A. Hence, the processing requirements of product 3 using machine type A is 30,000 minutes.

Processing requirement of product 3=Annual demand×Processing time=6,000×5 minutes=30,000 minutes

Determine the processing requirement of product 4 using machine type A:

It is calculated by multiplying annual demand of product 4 and the processing time per unit on type A. Hence, the processing requirements of product 4 using machine type A is 60,000 minutes.

Processing requirement of product 4=Annual demand×Processing time=30,000×2 minutes=60,000 minutes

Determine the total processing requirement using machine type A:

It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type A is 186,000 minutes.

Total processing requirements=(Processing requirement of product 1+Processing requirement of product 2+Processing requirement of product 3+Processing requirement of product 4)=48,000+48,000+30,000+60,000=186,000 minutes3,100 hours

Determine the needed number of machine type A:

It is calculated by dividing the total processing requirement and available minutes for machine type A. Hence, the needed number of machine type A is 2 machines.

Number of machine type A needed=Processing time neededAvailable minutes for machine type A=186,000150,000=1.242 machines

Determine the processing requirement of product 1 using machine type B:

It is calculated by multiplying annual demand of product 1 and the processing time per unit on type B. Hence, the processing requirements of product 1 using machine type B is 64,000 minutes.

Processing requirement of product 1=Annual demand×Processing time=16,000×4 minutes=64,000 minutes

Determine the processing requirement of product 2 using machine type B:

It is calculated by multiplying annual demand of product 2 and the processing time per unit on type B. Hence, the processing requirements of product 2 using machine type B is 48,000 minutes.

Processing requirement of product 2=Annual demand×Processing time=12,000×4 minutes=48,000 minutes

Determine the processing requirement of product 3 using machine type B:

It is calculated by multiplying annual demand of product 3 and the processing time per unit on type B. Hence, the processing requirements of product 3 using machine type B is 36,000 minutes.

Processing requirement of product 3=Annual demand×Processing time=6,000×6 minutes=36,000 minutes

Determine the processing requirement of product 4 using machine type B:

It is calculated by multiplying annual demand of product 4 and the processing time per unit on type B. Hence, the processing requirements of product 4 using machine type B is 60,000 minutes.

Processing requirement of product 4=Annual demand×Processing time=30,000×2 minutes=60,000 minutes

Determine the total processing requirement using machine type B:

It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type B is 208,000 minutes.

Total processing requirements=(Processing requirement of product 1+Processing requirement of product 2+Processing requirement of product 3+Processing requirement of product 4)=64,000+48,000+36,000+60,000=208,000 minutes3,466.67 hours

Determine the needed number of machine type B:

It is calculated by dividing the total processing requirement and available minutes for machine type B. Hence, the needed number of machine type B is 2 machines.

Number of machine type B needed=Processing time neededAvailable minutes for machine type B=208,000150,000=1.382 machines

Determine the processing requirement of product 1 using machine type C:

It is calculated by multiplying annual demand of product 1 and the processing time per unit on type B. Hence, the processing requirements of product 1 using machine type B is 32,000 minutes.

Processing requirement of product 1=Annual demand×Processing time=16,000×2 minutes=32,000 minutes

Determine the processing requirement of product 2 using machine type C:

It is calculated by multiplying annual demand of product 2 and the processing time per unit on type B. Hence, the processing requirements of product 2 using machine type B is 36,000 minutes.

Processing requirement of product 2=Annual demand×Processing time=12,000×3 minutes=36,000 minutes

Determine the processing requirement of product 3 using machine type C:

It is calculated by multiplying annual demand of product 3 and the processing time per unit on type B. Hence, the processing requirements of product 3 using machine type B is 24,000 minutes.

Processing requirement of product 3=Annual demand×Processing time=6,000×4 minutes=24,000 minutes

Determine the processing requirement of product 4 using machine type C:

It is calculated by multiplying annual demand of product 4 and the processing time per unit on type B. Hence, the processing requirements of product 4 using machine type B is 30,000 minutes.

Processing requirement of product 4=Annual demand×Processing time=30,000×1 minutes=30,000 minutes

Determine the total processing requirement using machine type C:

It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type C is 122,000 minutes.

Total processing requirements=(Processing requirement of product 1+Processing requirement of product 2+Processing requirement of product 3+Processing requirement of product 4)=32,000+36,000+24,000+30,000=122,000 minutes2,033.33 hours

Determine the needed number of machine type C:

It is calculated by dividing the total processing requirement and available minutes for machine type C. Hence, the needed number of machine type C is 1 machine.

Number of machine type C needed=Processing time neededAvailable minutes for machine type C=122,000150,000=0.811 machines

Determine the total cost considering purchase cost of machine type A:

It is calculated by multiplying number of machines and the cost of the machine. Hence, the total cost is $80,000.

Total cost=Number of machines×Cost of the machine=2×40,000=80,000

Determine the total cost considering purchase cost of machine type B:

It is calculated by multiplying number of machines and the cost of the machine. Hence, the total cost is $60,000.

Total cost=Number of machines×Cost of the machine=2×30,000=60,000

Determine the total cost considering purchase cost of machine type C:

It is calculated by multiplying number of machines and the cost of the machine. Hence, the total cost is $80,000.

Total cost=Number of machines×Cost of the machine=1×80,000=80,000

Hence, Buying 2 of the B machines at a total cost of $60,000 have lower total cost.

b)

Summary Introduction

To determine: The machine that would have lower total cost considering operating cost.

Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.

b)

Expert Solution
Check Mark

Answer to Problem 11P

Buying two B machines would have lower total cost.

Explanation of Solution

Given information:

A company should decide whether to buy machine of type A, type B, or type C. The cost of type A machine is $40,000, cost of type B machine is $30,000, and the cost of type C machine is $80,000.

Annual demand and processing unit is given as follows for each product:

ProductAnnual demandProcessing time per unit
A B C
1 16,000 3 4 2
2 12,000 4 4 3
3 6,000 5 6 4
4 30,000 2 2 1

Operating cost for machine A is $10 per hour, operating cost for machine B is $11 per hour, and operating cost for machine C is $12 per hour.

Calculate the total cost considering both purchasing cost and operating cost for machine A:

It is calculated by adding the total cost considering purchasing cost and the operating cost which can be attained by multiplying operating cost per hour and the total processing hours.

Total cost=Total cost considering purchasing cost+(Total processing hours×Operating cost per hour)=$80,000+(3,100 hours×$10)=$80,000+$31,000=$111,000

Calculate the total cost considering both purchasing cost and operating cost for machine B:

It is calculated by adding the total cost considering purchasing cost and the operating cost which can be attained by multiplying operating cost per hour and the total processing hours.

Total cost=Total cost considering purchasing cost+(Total processing hours×Operating cost per hour)=$60,000+(3,466.67 hours×$11)=$60,000+$38,133=$98,133

Calculate the total cost considering both purchasing cost and operating cost for machine C:

It is calculated by adding the total cost considering purchasing cost and the operating cost which can be attained by multiplying operating cost per hour and the total processing hours.

Total cost=Total cost considering purchasing cost+(Total processing hours×Operating cost per hour)=$80,000+(2,033.22 hours×$12)=$80,000+$24,400=$104,400

Hence, buying two B machines would have lower total cost.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
provide scholarly reseach and references for the following 1. explain operational risks and examples of such risk faced by management at financial institutions 2. discuss the importance of establishing an effective risk management policy at financial institutions to manage operational risk, giving example of a risk management strategy used by financial institutions to mitigate such risk.   3. what is the rold of the core principles of effective bank supervision as it relates to operational risk, in the effective management of financial institutions.
Please show all units, work, and steps needed to solve this problem I need answer typing clear urjent no chatgpt used pls i will give 5 Upvotes.
IM.82 A distributor of industrial equipment purchases specialized compressors for use in air conditioners. The regular price is $50, however, the manufacturer of this compressor offers quantity discounts per the following discount schedule: Option Plan Quantity Discount A 1 - 299 0% B 300 - 1,199 0.50% C 1,200+ 1.50% The distributor pays $56 each time it places an order with the manufacturer. Holding costs are negligible (none) but they do earn 10% annual interest on all cash balances (meaning there will be a financial opportunity cost when they put cash into inventory). Annual demand is expected to be 10,750 units. When there is no quantity discount (Option Plan A, the first row of the schedule listed above), what is the adjusted order quantity? (Display your answer to the nearest whole number.) 491 Based on your answer to the previous question, and based on the annual demand as stated above, what will be the annual ordering costs? (Display your answer to the…

Chapter 5 Solutions

Operations Management

Ch. 5.S - What information is contained in a payoff table?Ch. 5.S - Prob. 7DRQCh. 5.S - Prob. 8DRQCh. 5.S - Under what circumstances is expected monetary...Ch. 5.S - Explain or define each of these terms: a. Laplace...Ch. 5.S - Prob. 11DRQCh. 5.S - Prob. 12DRQCh. 5.S - Prob. 13DRQCh. 5.S - Prob. 1PCh. 5.S - Refer to problem1. Suppose after a certain amount...Ch. 5.S - Refer to Problems 1 and 2 Construct a graph that...Ch. 5.S - Prob. 4PCh. 5.S - Prob. 5PCh. 5.S - The lease of Theme Park, Inc., is about to expire....Ch. 5.S - Prob. 7PCh. 5.S - Prob. 8PCh. 5.S - Prob. 9PCh. 5.S - A manager must decide how many machines of a...Ch. 5.S - Prob. 11PCh. 5.S - Prob. 12PCh. 5.S - Prob. 13PCh. 5.S - Prob. 14PCh. 5.S - Give this payoff table: a. Determine the range of...Ch. 5.S - Prob. 16PCh. 5.S - Repeat all parts of problem 16, assuming the value...Ch. 5.S - Prob. 18PCh. 5 - Prob. 1DRQCh. 5 - Prob. 2DRQCh. 5 - How do long-term and short-term capacity...Ch. 5 - Give an example of a good and a service that...Ch. 5 - Give some example of building flexibility into...Ch. 5 - Why is it important to adopt a big-picture...Ch. 5 - What is meant by capacity in chunks, and why is...Ch. 5 - Prob. 8DRQCh. 5 - How can a systems approach to capacity planning be...Ch. 5 - Prob. 10DRQCh. 5 - Why is it important to match process capabilities...Ch. 5 - Briefly discuss how uncertainty affects capacity...Ch. 5 - Prob. 13DRQCh. 5 - Prob. 14DRQCh. 5 - Prob. 15DRQCh. 5 - Prob. 16DRQCh. 5 - What is the benefit to a business organization of...Ch. 5 - Prob. 1TSCh. 5 - Prob. 2TSCh. 5 - Prob. 3TSCh. 5 - Prob. 1CTECh. 5 - Prob. 2CTECh. 5 - Identify four potential unethical actions or...Ch. 5 - Any increase in efficiency also increases...Ch. 5 - Prob. 1PCh. 5 - In a job shop, effective capacity is only 50...Ch. 5 - A producer of pottery is considering the addition...Ch. 5 - A small firm intends to increase the capacity of a...Ch. 5 - A producer of felt-tip pens has received a...Ch. 5 - A real estate agent is considering changing her...Ch. 5 - A firm plans to begin production of a new small...Ch. 5 - A manager is trying to decide whether to purchase...Ch. 5 - A company manufactures a product using two machine...Ch. 5 - A company must decide which type of machine to...Ch. 5 - Prob. 11PCh. 5 - A manager must decide how many machines of a...Ch. 5 - Prob. 13PCh. 5 - The following diagram shows a four-step process...Ch. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - A new machine will cost 18,000, butt result it...Ch. 5 - Remodelling an office will cost 25,000 and will...Ch. 5 - Prob. 1CQCh. 5 - Prob. 2CQCh. 5 - Prob. 3CQ
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College