Intermediate Accounting
9th Edition
ISBN: 9781259722660
Author: J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Textbook Question
thumb_up100%
Chapter 5, Problem 5.31BE
Long-term contract; revenue recognition over time; profit recognition
• LO5–9
A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
5
Dineshbhai
Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion
[LO6-9]
On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington,
D.C., for $410 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and
estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):
Costs incurred during the year
Estimated costs to complete as of December
2024
$ 50
200
2025
$ 150
2026
$ 45
50
31
Required:
1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this
contract, assuming Sanderson recognizes revenue over time according to percentage of completion.
2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this
contract, assuming this project does not qualify…
Chapter 5 Solutions
Intermediate Accounting
Ch. 5 - What are the five key steps a company follows to...Ch. 5 - What indicators suggest that a performance...Ch. 5 - What criteria determine whether a company can...Ch. 5 - We recognize service revenue either at one point...Ch. 5 - What characteristics make a good or service a...Ch. 5 - Prob. 5.6QCh. 5 - What must a contract include for the contract to...Ch. 5 - How might the definition of probable affect...Ch. 5 - When a contract includes an option to buy...Ch. 5 - Prob. 5.10Q
Ch. 5 - Prob. 5.11QCh. 5 - Is a customers right to return merchandise a...Ch. 5 - Prob. 5.13QCh. 5 - Under what circumstances should sellers consider...Ch. 5 - When should a seller view a payment to its...Ch. 5 - What are three methods for estimating stand-alone...Ch. 5 - When is revenue recognized with respect to...Ch. 5 - In a franchise arrangement, what are a franchisors...Ch. 5 - When does a company typically recognize revenue...Ch. 5 - Prob. 5.20QCh. 5 - Prob. 5.21QCh. 5 - Prob. 5.22QCh. 5 - Must bad debt expense be reported on its own line...Ch. 5 - Explain the difference between contract assets,...Ch. 5 - Explain how to account for revenue on a long-term...Ch. 5 - Prob. 5.26QCh. 5 - Prob. 5.27QCh. 5 - What are the two general criteria that must be...Ch. 5 - Explain why, in most cases, a seller recognizes...Ch. 5 - Revenue recognition for most installment sales...Ch. 5 - Prob. 5.31QCh. 5 - How does a company report deferred gross profit...Ch. 5 - Prob. 5.33QCh. 5 - Briefly describe the guidelines for recognizing...Ch. 5 - Prob. 5.35QCh. 5 - Briefly describe the guidelines provided by GAAP...Ch. 5 - Revenue recognition at a point in time LO52 On...Ch. 5 - Timing of revenue recognition LO53 Estate...Ch. 5 - Prob. 5.3BECh. 5 - Allocating the transaction price LO54 Sarjit...Ch. 5 - Existence of a contract LO5-5 Tulane Tires wrote...Ch. 5 - Prob. 5.6BECh. 5 - Prob. 5.7BECh. 5 - Performance obligations; warranties LO55 Vroom...Ch. 5 - Prob. 5.9BECh. 5 - Prob. 5.10BECh. 5 - Performance obligations; construction LO55...Ch. 5 - Prob. 5.12BECh. 5 - Prob. 5.13BECh. 5 - Variable consideration LO56 Leo Consulting enters...Ch. 5 - Variable consideration LO56 In January 2018,...Ch. 5 - Prob. 5.16BECh. 5 - Prob. 5.17BECh. 5 - Payment s by the seller to the customer LO56...Ch. 5 - Estimating stand-alone selling prices: adjusted...Ch. 5 - Estimating stand-alone selling prices: expected...Ch. 5 - Estimating stand-alone selling prices; residual...Ch. 5 - Timing of revenue recognition; licenses LO57 Saar...Ch. 5 - Prob. 5.23BECh. 5 - Prob. 5.24BECh. 5 - Timing of revenue recognition; franchises LO57...Ch. 5 - Timing of revenue recognition; bill-and-hold LO57...Ch. 5 - Prob. 5.27BECh. 5 - Prob. 5.28BECh. 5 - Contract assets and contract liabilities LO58...Ch. 5 - Prob. 5.30BECh. 5 - Long-term contract; revenue recognition over time;...Ch. 5 - Prob. 5.32BECh. 5 - Long-term contract; revenue recognition upon...Ch. 5 - Long-term contract; revenue recognition; loss on...Ch. 5 - Installment sales method On July 1, 2018, Apache...Ch. 5 - Prob. 5.36BECh. 5 - Cost recovery method Refer to the situation...Ch. 5 - Prob. 5.38BECh. 5 - Prob. 5.39BECh. 5 - Revenue recognition; software contracts under IFRS...Ch. 5 - Prob. 5.41BECh. 5 - Prob. 5.1ECh. 5 - Prob. 5.2ECh. 5 - Allocating transaction price LO54 Video Planet...Ch. 5 - Prob. 5.4ECh. 5 - Prob. 5.5ECh. 5 - Prob. 5.6ECh. 5 - Prob. 5.7ECh. 5 - Prob. 5.8ECh. 5 - Prob. 5.9ECh. 5 - Variable considerationmost likely amount; change...Ch. 5 - Variable considerationexpected value; change in...Ch. 5 - Prob. 5.12ECh. 5 - Approaches for estimating stand-alone selling...Ch. 5 - FASB codification research LO56, LO57 Access the...Ch. 5 - Franchises; residual method LO56, LO57 Monitor...Ch. 5 - FASB codification research LO58 Access the FASB...Ch. 5 - Long-term contract; revenue recognition over time...Ch. 5 - Long-term contract; revenue recognition over time...Ch. 5 - Long-term contract; revenue recognition over time;...Ch. 5 - Long-term contract; revenue recognition upon...Ch. 5 - Income (loss) recognition; Long-term contract;...Ch. 5 - Long-term contract; revenue recognition over time;...Ch. 5 - Installment sales method Charter Corporation,...Ch. 5 - Installment sales method; journal entries [This is...Ch. 5 - Installment sales; alternative recognition methods...Ch. 5 - Journal entries; point of delivery, installment...Ch. 5 - Prob. 5.27ECh. 5 - Prob. 5.28ECh. 5 - Prob. 5.29ECh. 5 - Prob. 5.30ECh. 5 - Prob. 5.31ECh. 5 - Prob. 5.32ECh. 5 - Prob. 5.33ECh. 5 - Prob. 5.34ECh. 5 - Prob. 5.35ECh. 5 - Prob. 5.1PCh. 5 - Prob. 5.2PCh. 5 - Prob. 5.3PCh. 5 - Prob. 5.4PCh. 5 - Prob. 5.5PCh. 5 - Variable consideration; change of estimate LO53,...Ch. 5 - Prob. 5.7PCh. 5 - Prob. 5.8PCh. 5 - Prob. 5.9PCh. 5 - Long-term contract; revenue recognition over time ...Ch. 5 - Long-term contract; revenue recognition upon...Ch. 5 - Long-term contract; revenue recognized over time;...Ch. 5 - Long-term contract; revenue recognition over time...Ch. 5 - Income statement presentation; installment sales...Ch. 5 - Prob. 5.15PCh. 5 - Installment sales; alternative recognition methods...Ch. 5 - Installment sales and cost recovery methods...Ch. 5 - Prob. 5.18PCh. 5 - Franchise sales; installment sales method Olive...Ch. 5 - Prob. 5.1BYPCh. 5 - Judgment Case 52 Satisfaction of performance...Ch. 5 - Judgment Case 53 Satisfaction of performance...Ch. 5 - Prob. 5.4BYPCh. 5 - Prob. 5.5BYPCh. 5 - Prob. 5.6BYPCh. 5 - Prob. 5.8BYPCh. 5 - Prob. 5.9BYPCh. 5 - Prob. 5.10BYPCh. 5 - Prob. 5.11BYPCh. 5 - Prob. 5.12BYPCh. 5 - Prob. 5.13BYPCh. 5 - Prob. 5.14BYPCh. 5 - Prob. 5.15BYPCh. 5 - Prob. 5.16BYPCh. 5 - Prob. 5.19BYPCh. 5 - Prob. 1CCTC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 Required: Required 1 Required 2 Required 3 2024 2025 2026 Construction revenue Construction expense Gross profit (loss) 1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income…arrow_forwardExercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,200,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2021, is as follows: Balance Sheet Accounts receivable (from construction progress billings) Construction in progress. Less: Billings on construction contract Cost and profit of uncompleted contracts in excess of billings Income Statement Income (before tax) on the contract recognized in 2021 Required: 1. What was the cost of construction actually incurred in 2021? $ 160,000 (152,000) 1. Actual costs incurred in 2021 2. Cash collections in 2021 3. Estimated cost to complete 4. Estimated percentage $26,000 $36,000 8,000 2. How much cash was collected in 2021 on this contract? 3. What…arrow_forwardExercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $230 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 Required: Required 1 Required 2 Required 3 Year 1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming this project does not qualify…arrow_forward
- Dinesh Bhaiarrow_forwardProblem 6-11 (Algo) Long-term contract; revenue recognition upon completion [LO6-9] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year- end Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Cost incurred during the year Estimated costs to complete as of year- end Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 2-b. In the journal below, complete the…arrow_forwardProblem 6-11 (Algo) Long-term contract; revenue recognition upon completion [LO6-9] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc."…arrow_forward
- Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion [LO6-9] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. Cost incurred during the year Estimated costs to…arrow_forwardProblem 6-12 (Algo) Long-term contract; revenue recognized over time vs. upon project completion; loss projected on entire project [LO6-9] Curtiss Construction Company, Incorporated, entered into a fixed-price contract with Axelrod Associates on July 1, 2024, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,120,000. The building was completed on December 31, 2026. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date Required: At 12-31-2024 At 12-31-2025 At 12-31-2026 10% 60% 100% $ 361,000 3,249,000 722,000 $ 2,604,000 1,736,000 2,210,000 $ 4,392,000 0 4,120,000 1. Compute gross profit or…arrow_forwardsharadarrow_forward
- ter 6 Exercises 1 pok int i int 9 ences Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9] Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,600,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: Costs incurred during the year. Estimated costs to complete as of 12/31 Billings during the year. Cash collections during the year Complete this question by entering your answers in the tabs below. Required 1 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time according to percentage of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract…arrow_forwardHaresharrow_forwardA4arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning
Depreciation -MACRS; Author: Ronald Moy, Ph.D., CFA, CFP;https://www.youtube.com/watch?v=jsf7NCnkAmk;License: Standard Youtube License