Long-term contract; revenue recognition upon project completion; loss projected on entire project
• LO5–8, LO5–9
[This is a variation of E 5–19 focusing on the revenue recognition upon project completion.]
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000.
In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of $3,800,000 were incurred. The company’s fiscal year-end is December 31. This project does not qualify for revenue recognition over time.
Required:
1. Calculate the amount of gross profit or loss to be recognized in each of the three years.
2. Prepare
3. Prepare a partial
Want to see the full answer?
Check out a sample textbook solutionChapter 5 Solutions
Intermediate Accounting
- Problem 6-12 (Algo) Long-term contract; revenue recognized over time vs. upon project completion; loss projected on entire project [LO6-9] Curtiss Construction Company, Incorporated, entered into a fixed-price contract with Axelrod Associates on July 1, 2024, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,120,000. The building was completed on December 31, 2026. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date Required: At 12-31-2024 At 12-31-2025 At 12-31-2026 10% 60% 100% $ 361,000 3,249,000 722,000 $ 2,604,000 1,736,000 2,210,000 $ 4,392,000 0 4,120,000 1. Compute gross profit or…arrow_forwardExercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2021, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of $3,820,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion. Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2021, 2022, and 2023 using the percentage of completion method.2a. Prepare journal entries for 2021 to record the transactions…arrow_forwardPlease don't give image formatarrow_forward
- Please do not give solution in image format thankuarrow_forwardJay Don't upload any imagearrow_forwardP 6-10 Long-term ontract; venue cognition ver time .LO6-8, 06-9 In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The TODO was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Required: 2024 $2,400,000 5,600,000 2,000,000 1,800,000 Cost incurred during the year Estimated costs to complete as of year-end 1. Calculate the amount of revenue and gross profit to be recognized in each of the three years. 2. Prepare all necessary journal entries for each of the years (credit "Cash, Materials, etc. for construction costs incurred). 3. Prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Indicate whether any of the amounts shown are contract assets or…arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education