Long-term contract; revenue recognition over time and at a point in time
• LO5–9
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below:
2018 | 2019 | |
Costs incurred during the year | $ 300,000 | $ 1,575,000 |
Estimated costs to complete as of 12/31 | 1,200,000 | –0– |
Billings during the year | 380,000 | 1,620,000 |
Cash collections during the year | 250,000 | 1,750,000 |
Required:
1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming Nortel recognizes revenue over time according to percentage of completion.
2. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming this project does not qualify for revenue recognition over time.
3. Prepare a partial
4. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2018 assuming this project does not qualify for revenue recognition over time.
Want to see the full answer?
Check out a sample textbook solutionChapter 5 Solutions
Intermediate Accounting
- Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below:2018 2019Costs incurred during the year $ 300,000 $ 1,575,000Estimated costs to complete as of 12/31 1,200,000 –0–Billings during the year 380,000 1,620,000Cash collections during the year 250,000 1,750,000Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming Nortelrecognizes revenue over time according to percentage of completionarrow_forwardAssume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 356,000 $ 2,135,000 Estimated costs to complete as of 12/31 1,424,000 0 Billings during the year 475,000 1,760,000 Cash collections during the year 415,000 1,820,000 Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time according to percentage of completion.2. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming this project does not qualify for revenue recognition over time.3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2021 assuming Nortel recognizes revenue over time according to…arrow_forwardAssume Avaya contracted to provide a customer with Internet infrastructure for $2,200,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: 2024 2025 Costs incurred during the year $ 316,000 $ 1,700,000 Estimated costs to complete as of 12/31 1,264,000 0 Billings during the year 400,000 1,660,000 Cash collections during the year 290,000 1,770,000 Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time according to percentage of completion. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming this project does not qualify for revenue recognition over time.arrow_forward
- Assume Avaya contracted to provide a customer with Internet infrastructure for $2,910,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: 2024 2025 Costs incurred during the year $ 376,000 $ 2,265,000 Estimated costs to complete as of 12/31 1,504,000 0 Billings during the year 535,000 1,810,000 Cash collections during the year 500,000 1,845,000 Question: Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming this project does not qualify for revenue recognition over time.arrow_forwardter 6 Exercises 1 pok int i int 9 ences Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9] Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,600,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: Costs incurred during the year. Estimated costs to complete as of 12/31 Billings during the year. Cash collections during the year Complete this question by entering your answers in the tabs below. Required 1 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time according to percentage of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract…arrow_forwardExercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,200,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2021, is as follows: Balance Sheet Accounts receivable (from construction progress billings) Construction in progress. Less: Billings on construction contract Cost and profit of uncompleted contracts in excess of billings Income Statement Income (before tax) on the contract recognized in 2021 Required: 1. What was the cost of construction actually incurred in 2021? $ 160,000 (152,000) 1. Actual costs incurred in 2021 2. Cash collections in 2021 3. Estimated cost to complete 4. Estimated percentage $26,000 $36,000 8,000 2. How much cash was collected in 2021 on this contract? 3. What…arrow_forward
- Entity 2 entered contracts with two separate customers on 1 January 2022. The following information relates to these two contracts for 2022. A B £’000 £’000 Total contract price 40,000 40,000 Costs incurred to date 12,000 12,000 Anticipated further costs to completion 18,000 18,000 Cumulative progress billings invoiced 10,000 10,000 Cumulative progress billings received 8,000 8,000 Only contract A’s performance obligation is satisfied over time. Entity 2 is using the input method to determine the percentage of completion. Show how these two contracts should be presented in Entity 2’s financial statements for 2022.arrow_forwardDineshbhaiarrow_forwardshj.7arrow_forward