Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion
• LO5–9
Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars.
Required:
Copy and complete the following table:
The revenue recognition principle
The revenue recognition principle refers to the revenue that should be recognized in the time period, when the performance obligation (sales or services) of the company is completed.
Revenue recognized point of long term contract
A long-term contract qualifies for revenue recognition over time. The seller can recognize the revenue as per percentage of the completion of the project, which is recognized as revenue minus cost of completion until date.
If a contract does not meet the performance obligation norm, then the seller cannot recognize the revenue till the project is complete.
To determine: The amount of gross profit or loss to be recognized under various situations.
Answer to Problem 5.21E
The amount of gross profit or loss to be recognized under various situations is as follows:
(Figure 1)
Explanation of Solution
Working note:
Situation – 1
1. Compute the value of gross profit or loss recognized over time
Here,
Particulars | 2018 | 2019 | 2020 |
Contract price (A) | $5,000,000 | $5,000,000 | $5,000,000 |
Actual costs to date | 1,500,000 | 3,600,000 | 4,500,000 |
Estimated costs to complete | 3,000,000 | 900,000 | 0 |
Total estimated costs (B) | 4,500,000 | 4,500,000 | 4,500,000 |
Estimated gross profit(actual in 2020)
|
$500,000 | $500,000 | $500,000 |
Table (1)
In the year 2018:
In the year 2019:
In the year 2020:
2. Compute the value of gross profit or loss recognized upon completion
Year | Gross profit recognized |
2018 | 0 |
2019 | 0 |
2020 | $500,000 |
Total gross profit | $500,000 |
Table (2)
(4)
Situation – 2
1. Compute the value of gross profit or loss recognized over time
Here,
Particulars | 2018 | 2019 | 2020 |
Contract price (A) | $5,000,000 | $5,000,000 | $5,000,000 |
Actual costs to date | 1,500,000 | 2,400,000 | 4,800,000 |
Estimated costs to complete | 3,000,000 | 2,400,000 | 0 |
Total estimated costs (B) | 4,500,000 | 4,800,000 | 4,800,000 |
Estimated gross profit(actual in 2020)
|
$500,000 | $200,000 | $200,000 |
Table (3)
In the year 2018:
In the year 2019:
In the year 2020:
2. Compute the value of gross profit or loss recognized upon completion
Year | Gross profit recognized |
2018 | 0 |
2019 | 0 |
2020 | $200,000 |
Total gross profit | $200,000 |
Table (4)
(8)
Situation – 3
1. Compute the value of gross profit or loss recognized over time
Here,
Particulars | 2018 | 2019 | 2020 |
Contract price (A) | $5,000,000 | $5,000,000 | $5,000,000 |
Actual costs to date | 1,500,000 | 3,600,000 | 5,200,000 |
Estimated costs to complete | 3,000,000 | 1,500,000 | 0 |
Total estimated costs (B) | 4,500,000 | 5,100,000 | 5,200,000 |
Estimated gross profit(actual in 2020)
|
$500,000 | $(100,000) | $(200,000) |
Table (5)
In the year 2018:
In the year 2019:
In the year 2020:
2. Compute the value of gross profit or loss recognized upon completion
Year | Gross profit recognized |
2018 | 0 |
2019 | $(100,000) |
2020 | $(100,000) |
Total gross profit | $(200,000) |
Table (6)
(12)
Situation – 4
1. Compute the value of gross profit or loss recognized over time
Here,
Particulars | 2018 | 2019 | 2020 |
Contract price (A) | $5,000,000 | $5,000,000 | $5,000,000 |
Actual costs to date | 500,000 | 3,500,000 | 4,500,000 |
Estimated costs to complete | 3,500,000 | 875,000 | 0 |
Total estimated costs (B) | 4,000,000 | 4,375,000 | 4,500,000 |
Estimated gross profit(actual in 2020)
|
$1,000,000 | $625,000 | $500,000 |
Table (7)
In the year 2018:
In the year 2019:
In the year 2020:
2. Compute the value of gross profit or loss recognized upon completion
Year | Gross profit recognized |
2018 | 0 |
2019 | 0 |
2020 | $500,000 |
Total gross profit | $500,000 |
Table (8)
(16)
Situation – 5
1. Compute the value of gross profit or loss recognized over time
Here,
Particulars | 2018 | 2019 | 2020 |
Contract price (A) | $5,000,000 | $5,000,000 | $5,000,000 |
Actual costs to date | 500,000 | 3,500,000 | 4,800,000 |
Estimated costs to complete | 3,500,000 | 1,500,000 | 0 |
Total estimated costs (B) | 4,000,000 | 5,000,000 | 4,800,000 |
Estimated gross profit(actual in 2020)
|
$1,000,000 | $0 | $200,000 |
Table (9)
In the year 2018:
In the year 2019:
In the year 2020:
2. Compute the value of gross profit or loss recognized upon completion
Year | Gross profit recognized |
2018 | 0 |
2019 | 0 |
2020 | $200,000 |
Total gross profit | $200,000 |
Table (10)
(20)
Situation – 6
1. Compute the value of gross profit or loss recognized over time
Here,
Particulars | 2018 | 2019 | 2020 |
Contract price (A) | $5,000,000 | $5,000,000 | $5,000,000 |
Actual costs to date | 500,000 | 3,500,000 | 5,300,000 |
Estimated costs to complete | 4,600,000 | 1,700,000 | 0 |
Total estimated costs (B) | 5,100,000 | 5,200,000 | 5,300,000 |
Estimated gross profit(actual in 2020)
|
$(100,000) | $(200,000) | $(300,000) |
Table (11)
In the year 2018:
In the year 2019:
In the year 2020:
2. Compute the value of gross profit or loss recognized upon completion
Year | Gross profit recognized |
2018 | $(100,000) |
2019 | (100,000) |
2020 | (100,000) |
Total gross profit | $(300,000) |
Table (12)
(24)
Want to see more full solutions like this?
Chapter 5 Solutions
Intermediate Accounting
- Please answer No. 22 and 23 The First Part of Question No. 23 is on the other Picture Provide a complete solution. Thank Youarrow_forwardnku.4 give in table format or i will give you down votearrow_forwardRequired information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Problem 6-10 (Algo) Part 3 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Current liabilities: 2024 $ 2,156,000 5,544,000 2,130,000 1,865,000 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Note: Do not round intermediate calculations. 2024 2025 2026 $ 3,388,000 $ 2,371,600 2,156,000 0 3,414,000 3,300,000 2025 4,456,000…arrow_forward
- please help me in getting correct answer and dont give images in answer thankuarrow_forwardRequired information Skip to question [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 2025 2026 Cost incurred during the year $ 2,016,000 $2,808,000 $2,613,600 Estimated costs to complete as of year-end 5, 184,000 2,376, 000 0 Billings during the year 2, 180,000 2,644,000 5, 176,000 Cash collections during the year 1,890,000 2,500,000 5,610,000 Westgate recognizes revenue over time according to percentage of completion. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc." for construction costs incurred). 2-c. In the journal below, complete the…arrow_forwardRequired information Skip to question [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 2025 2026 Cost incurred during the year $ 2,059, 000 $ 2,627,000 $ 2,655,400 Estimated costs to complete as of year - end 5, 041, 000 2,414, 000 0 Billings during the year 2, 190, 000 2, 496,000 5, 314,000 Cash collections during the year 1,895,000 2,400,000 5, 705, 000 Westgate recognizes revenue over time according to percentage of completion. 2 - a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 2- b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc." for construction costs incurred). 2- c. In the journal…arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education