Concept explainers
Requirement – 1
International Financial Reporting Standards
They are commonly known as IFRS. These are set of accounting standards which are developed by independent (Non-profit) organization called as International Accounting Standards Board (IASB). These are universally accepted set of standards which state the rules and standards for accounting at global level.
Revenue recognized point of long term contract
A long-term contract qualifies for revenue recognition over time. The seller can recognize the revenue as per percentage of the completion of the project, which is recognized as revenue minus cost of completion until date.
If a contract does not meet the performance obligation norm, then the seller cannot recognize the revenue till the project is complete.
The revenue recognition principle
The revenue recognition principle refers to the revenue that should be recognized in the time period, when the performance obligation (sales or services) of the company is completed.
Rules of Debit and Credit:
Following rules are followed for debiting and crediting different accounts while they occur in business transactions:
- Debit, all increase in assets, expenses and dividends, all decrease in liabilities, revenues and stockholders’ equities.
- Credit, all increase in liabilities, revenues, and stockholders’ equities, all decrease in assets, expenses.
To determine: The amount of gross profit or loss to be recognized in 2018, 2019, and 2020.
Requirement – 1
Explanation of Solution
Here,
2018 gross profit recognized is $0
2019 gross profit recognized is $0
2020 gross profit recognized is $1,800,000
Now, calculate the total gross profit:
Hence, the calculated total gross profit is $1,800,000.
Requirement – 2
To prepare: The
Requirement – 2
Explanation of Solution
In the year 2018:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $2,400,000 | |||
Various accounts | $2,400,000 | |||
(To record construction cost) |
Table (1)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in liability value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
$2,000,000 | ||||
Billings on construction contract | $2,000,000 | |||
(To record progress billings) |
Table (2)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is an increase in revenue value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $1,800,000 | |||
Account receivable | $1,800,000 | |||
(To record cash collection) |
Table (3)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cost of construction | $2,400,000 | |||
Revenue from long-term contracts | $2,400,000 | |||
(To record gross profit) |
Table (4)
- Cost of construction is an expense. There is a decrease in stockholders’ equity value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in stockholders’ equity value. Therefore, it is credited.
In the year 2019:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $3,600,000 | |||
Various accounts | $3,600,000 | |||
(To record construction cost) |
Table (5)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in stockholders’ equity value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Account receivable | $4,000,000 | |||
Billings on construction contract | $4,000,000 | |||
(To record progress billings) |
Table (6)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is an increase in stockholders’ equity value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $3,600,000 | |||
Account receivable | $3,600,000 | |||
(To record cash collection) |
Table (7)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cost of construction | $3,600,000 | |||
Revenue from long-term contracts | $3,600,000 | |||
(To record gross profit) |
Table (8)
- Cost of construction is an expense. There is a decrease in liability value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in stockholders’ equity value. Therefore, it is credited.
In the year 2020:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $2,200,000 | |||
Various accounts | $2,200,000 | |||
(To record construction cost) |
Table (9)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in stockholders’ equity value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Account receivable | $4,000,000 | |||
Billings on construction contract | $4,000,000 | |||
(To record progress billings) |
Table (10)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is a decrease in
stockholders equity value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $4,600,000 | |||
Account receivable | $4,600,000 | |||
(To record cash collection) |
Table (11)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $1,800,000 | |||
Cost of construction | $2,400,000 | |||
Revenue from long-term contracts | $4,000,000 | |||
(To record gross profit) |
Table (12)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Cost of construction is an expense. There is a decrease in liability value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in stockholders’ equity value. Therefore, it is credited.
Requirement – 3
To prepare: The partial
Requirement – 3
Explanation of Solution
Partial balance sheet of W Construction Company is as follows:
In the year 2018:
Assets | 2018 | |
Account receivables | $400,000 | |
Construction in progress | $2,400,000 | |
Less: Billings | ($2,000,000) | |
Costs in excess of billings | $400,000 |
Table (13)
In the year 2019:
Assets | 2019 | |
Account receivables | $600,000 | |
Construction in progress | $6,000,000 | |
Less: Billings | ($6,000,000) | |
Costs in excess of billings | $0 |
Table (14)
Requirement – 4
The total amount of gross profit or loss to be recognized in 2018, 2019, and 2020.
Requirement – 4
Explanation of Solution
Here,
2018 gross profit recognized is $0
2019 gross profit recognized is $0
2020 gross profit recognized is $600,000
Now, calculate the total gross profit:
Hence, the calculated total gross profit is $600,000.
Note:
Details for cost incurred and estimated cost to complete.
Particulars | 2018 | 2019 | 2020 |
Costs incurred during the year | $2,400,000 | $3,800,000 | $3,200,000 |
Estimated costs to complete as of year-end | $5,600,000 | $3,100,000 |
Table (15)
Requirement – 5
The amount of revenue and gross profit or loss to be recognized in 2018, 2019, and 2020.
Requirement – 5
Explanation of Solution
Here,
2018 gross profit recognized is $0
2019 gross profit recognized is ($300,000)
2020 gross profit recognized is $200,000
Now, calculate the total gross profit:
Hence, the calculated total gross profit is ($100,000).
Note:
Details for cost incurred and estimated cost to complete.
Particulars | 2018 | 2019 | 2020 |
Costs incurred during the year | $2,400,000 | $3,800,000 | $3,900,000 |
Estimated costs to complete as of year-end | $5,600,000 | $4,100,000 |
Table (16)
Want to see more full solutions like this?
Chapter 5 Solutions
Intermediate Accounting
- Which statement is true when the outcome of construction contract cannot be estimated reliably? a. Contract costs shall be recognized as an expense in the period when incurred. b. Revenue shall be recognized only to the extent of contract costs incurred that is probable will be recoverable c. All of these statements are true. d. An expected loss on the construction contract shall be recognized as an expense immediately.arrow_forwardWhen the outcome of a construction contract cannot be estimated reliably, how shall contract revenue and contract costs associated with the construction contract be recognized? Group of answer choices They shall be recognized as revenue and expenses respectively by reference to the state of completion of the contract activity at the end of the reporting period also known as by percentage of completion method. They shall be recognized as revenue and expenses respectively by the date of earning of revenue or incurring of expenses also known as accrual method. They shall be recognized as revenue and expenses respectively by reference to the percentage of collection of receivables from customers also known as by installment method. Revenue shall be recognized only to the extent of contract cost incurred that is probable will be recoverable and the contract cost shall be recognized as an expense in the period in which there are incurred also known as cost recovery or zero-profit…arrow_forwardI need the answer quicklyarrow_forward
- Questionn. Answer the following questions with regard to the AIA A201TM - General Conditions of the Contract for Construction, a required reading item for Module 4: a). An abandoned well was found in the area of a proposed footing, and the well cap was clearly visible. The contractor claimed additional costs for structural fill. Should the architect approve his claim? b). Does the owner have the right to subcontract out portions of the work directly? c). The building official pointed out that the lack of fire alarms in the project violated local building codes. The owner went after the electrical contractor for negligence in reviewing the drawings. Should the electrical contractor be responsible for the delay and additional cost in fixing this problem? d). How can the contractor check on the owner's financial strength? e). In the contract, the stipulated allowance for the carpet is $10,000. The contractor spent $9,500 (delivery and tax included) on purchasing the carpet chosen by the…arrow_forwardAccess the FASB’s Codification Research System® at the FASB website (www.fasb.org) and select Basic View. Determine the specific seven-digit (XXX-XX-XX) or eight-digit Codification citation (XXX-XX-XX-X) for accounting for each of the following items: Definition of initial direct costs. When a modification to a contract is reported as a separate contract (that is, separate from the original contract). The disclosures required in the notes to the financial statements for a lessor. The classification criteria for when a lessee classifies a lease as a finance lease and a lessor classifies a lease as a sales-type lease.arrow_forwardDavid Mendez Under the percentage-of-completion method, how should the balances of progress billings and construction in process be disclosed in the financial statements prior to the completion of the contract? net, as income from construction if a credit balance, and loss from construction if a debit balance progress billings as deferred income, construction in progress as a deferred expense net, as a current asset if a debit balance, and a current liability if a credit balance progress billings as income, construction in process as inventoryarrow_forward
- Questionarrow_forwardUnder the completed-contract method, the Contract Asset/Liability account balance will consist of construction costs only. gross profit only. construction costs and gross profit. O construction costs and billings.arrow_forwardThis is under construction contracts in accounting for special transactions subjectarrow_forward
- 1. WHAT IS LONG-TERM CONSTRUCTION CONTRACTS? ELABORATE AND GIVE EXAMPLES OF LOCAL CONSTRUCTION CONTRACTS. DISCUSS THE ACCOUNTING STANDARDS GOVERNING IT. 2. WHAT ARE THE CONSIDERATIONS TO RECOGNIZE ONE AS ADDITIONAL CONTRACT REVENUE? GIVE SOME EXAMPLES OF ADDITIONAL CONTRACT REVENUES. 3. WHAT ARE THE VARIETY OF MEANS A STAGE OF COMPLETION CAN BE ESTIMATED? 4. HOW SHALL THE CONTRACTOR PRESENT IN ITS STATEMENT OF FINANCIAL STATEMENTS THE ACCOUNTS RELATED TO CONSTRUCTION CONTRACT? 5. WHEN THE COMPANY DECIDES TO CHANGE ITS ACCOUNTING FOR CONSTRUCTION CONTRACTS FROM PERCENTAGE OF COMPLETION TO COST RECOVERY METHOD. HOW SHALL THE ACCOUNTING CHANGE BE TREATED?arrow_forwardList and discuss Impairment measurements, Testing for Impairment, Asset Grouping, and Accounting for Impairments. Briefly describe any differences between GAAP and IFRS regulations.arrow_forwardThe primary issue in the accounting for construction contracts is the determination of the percentage of completion and revenue to be recognized during the period. the allocation of contract revenue and contract costs to the accounting periods in which construction work is performed. the determination of the rate at which physical performance has been made during the reporting period and the future performance on which future revenues will be allocated. the allocation of costs of a long-lived asset to permit the proper matching of costs with revenues.arrow_forward
- Auditing: A Risk Based-Approach (MindTap Course L...AccountingISBN:9781337619455Author:Karla M Johnstone, Audrey A. Gramling, Larry E. RittenbergPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning