Long-term contract; revenue recognition over time
• LO5–8, LO5–9
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: Westgate recognizes revenue over time according to percentage of completion.
Required:
1. Calculate the amount of revenue and gross profit to be recognized in each of the three years.
2. Prepare all necessary
3. Prepare a partial
4. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information:
5. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information:
Requirement – 1
Contract
Contract is a written document that creates legal enforcement for buying and selling the property. It is committed by the parties to perform their obligations and enforcing their rights.
Revenue recognized point of long term contract
A long-term contract qualifies for revenue recognition over time. The seller can recognize the revenue as per percentage of the completion of the project, which is recognized by revenue minus cost of completion until date.
If a contract does not meet the performance obligation norm, the seller cannot recognize the revenue till the project complete.
The revenue recognition principle
The revenue recognition principle refers to the revenue that should be recognized in the time period, when the performance obligation (sales or services) of the company is completed.
To determine: The amount of revenue and gross profit or loss to be recognized in 2018, 2019, and 2020.
Explanation of Solution
Recognized revenue
In the year 2018:
Given,
The contract price is $10,000,000
Actual cost to date is $2,400,000
Calculated total estimated cost is $8,000,000(1)
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is $3,000,000.
In the year 2019:
Given,
The contract price is $10,000,000
Actual cost to date is $6,000,000
Calculated total estimated cost is $8,000,000
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is $4,500,000.
In the year 2020:
Given,
Contract price is $10,000,000
Calculated revenue recognition in 2018 is $3,000,000
Calculated revenue recognition in 2019 is $4,500,000
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is$2,500,000.
Recognized gross profit
In the year 2018
Here,
Estimated gross profit in 2018 is $2,000,000 (1)
Total estimated cost is $8,000,000,
Actual cost to date is $2,400,000.
Now, calculate the gross profitrecognition:
Hence, the calculated gross profit recognition is $6,000,000.
In the year 2019
Here,
Estimated gross profit in 2019 is $2,000,000(1)
Total estimated cost is $8,000,000,
Gross profit recognition in 2018 is $6,000,000
Actual cost to date is $6,000,000.
Now, calculate the gross profitrecognition:
Hence, the calculated gross profit recognition is $9,000,000.
In the year 2020
Here,
Estimated gross profit in 2020 is $1,800,000(1)
Gross profit recognition in 2018 is $6,000,000,
Gross profit recognition in 2019 is $9,000,000.
Now, calculate the gross profitrecognition:
Hence, the calculated gross profit recognition is $3,000,000.
Working note:
Calculate the value of gross profit (in millions)
Particulars | 2018 | 2019 | 2020 | |||
Contract price | $1,000 | $1,000 | $1,000 | |||
Actual costs to date | $240 | $600 | $820 | |||
Estimated costs to complete | $560 | $200 | $0 | |||
Less: Total estimated cost | $800 | $800 | $820 | |||
Estimated gross profit | $200 | $200 | $180 |
Table (1)
(1)
Requirement – 2
To prepare: The journal entries for the year 2018, 2019 and 2020.
Explanation of Solution
In the year 2018:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $2,400,000 | |||
Various accounts | $2,400,000 | |||
(To record construction cost) |
Table (2)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in liability value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Account receivable | $2,000,000 | |||
Billings on construction contract | $2,000,000 | |||
(To record progress billings) |
Table (3)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is a decrease in liability value. Therefore, it is debited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $1,800,000 | |||
Account receivable | $1,800,000 | |||
(To record cash collection) |
Table (4)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cost of construction | $600,000 | |||
Construction in progress | $2,400,000 | |||
Revenue from long-term contracts | $3,000,000 | |||
(To record gross profit) |
Table (5)
- Cost of constructionis anexpense. There is a decrease in liability value. Therefore, it is debited.
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in liability value. Therefore, it is credited.
In the year 2019:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $3,600,000 | |||
Various accounts | $3,600,000 | |||
(To record construction cost) |
Table (6)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in liability value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Account receivable | $4,000,000 | |||
Billings on construction contract | $4,000,000 | |||
(To record progress billings) |
Table (7)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is a decrease in liability value. Therefore, it is debited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $3,600,000 | |||
Account receivable | $3,600,000 | |||
(To record cash collection) |
Table (8)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cost of construction | $900,000 | |||
Construction in progress | $3,600,000 | |||
Revenue from long-term contracts | $4,500,000 | |||
(To record gross profit) |
Table (9)
- Cost of constructionis anexpense. There is a decrease in liability value. Therefore, it is debited.
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in liability value. Therefore, it is credited.
In the year 2020:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $2,200,000 | |||
Various accounts | $2,200,000 | |||
(To record construction cost) |
Table (10)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in liability value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Account receivable | $4,000,000 | |||
Billings on construction contract | $4,000,000 | |||
(To record progress billings) |
Table (11)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is a decrease in liability value. Therefore, it is debited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $4,600,000 | |||
Account receivable | $4,600,000 | |||
(To record cash collection) |
Table (12)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $300,000 | |||
Cost of construction | $2,200,000 | |||
Revenue from long-term contracts | $2,500,000 | |||
(To record gross profit) |
Table (13)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Cost of constructionis anexpense. There is a decrease in liability value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in liability value. Therefore, it is credited.
Requirement – 3
To prepare: The partial balance sheet for 2018 and 2019.
Explanation of Solution
Partial balance sheet of W Construction Company is as follows:
In the year 2018:
Assets | 2018 | |
Account receivables | $200,000 | |
Construction in progress | $3,000,000 | |
Less: Billings | ($2,000,000) | |
Costs in excess of billings | $1,000,000 |
Table (14)
In the year 2019:
Assets | 2019 | |
Account receivables | $600,000 | |
Construction in progress | $7,500,000 | |
Less: Billings | ($6,000,000) | |
Costs in excess of billings | $1,500,000 |
Table (15)
Requirement – 4
Explanation of Solution
Recognized revenue
In the year 2018:
Given,
The contract price is $10,000,000
Actual cost to date is $2,400,000
Calculated total estimated cost is $8,000,000(1)
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is $3,000,000.
In the year 2019:
Given,
The contract price is $10,000,000
Actual cost to date is $6,200,000
Calculated total estimated cost is $9,300,000
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is $3,666,667.
In the year 2020:
Given,
Contract price is $10,000,000
Calculated revenue recognition in 2018 is $3,000,000
Calculated revenue recognition in 2019 is $3,666,667
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is$3,333,333.
Recognized gross profit
In the year 2018
Here,
Estimated gross profit in 2018 is $2,000,000, (2)
Total estimated cost is $8,000,000,
Actual cost to date is $2,400,000.
Now, calculate the gross profitrecognition:
Hence, the calculated gross profit recognition is $6,000,000.
In the year 2019
Here,
Estimated gross profit in 2019 is $700,000 (2)
Total estimated cost is $9,300,000,
Gross profit recognition in 2018 is $6,000,000
Actual cost to date is $6,200,000.
Now, calculate the gross profitrecognition:
Hence, the calculated gross loss recognition is $133,333.
In the year 2020
Here,
Estimated gross profit in 2020 is $600,000(2)
Gross profit recognition in 2018 is $600,000,
Gross profit recognition in 2019 is -$133,333.
Now, calculate the gross profitrecognition:
Hence, the calculated gross profit recognition is $133,333.
Working note
Particulars | 2018 | 2019 | 2020 |
Costs incurred during the year | $2,400,000 | $3,800,000 | $3,200,000 |
Estimated costs to complete as of year-end | $5,600,000 | $3,100,000 |
Calculate the estimated gross profit ($ in millions):
Particulars | 2018 | 2019 | 2020 | |||
Contract price | $1,000 | $1,000 | $1,000 | |||
Actual costs to date | $240 | $620 | $940 | |||
Estimated costs to complete | $560 | $310 | $0 | |||
Total estimated cost | $800 | $930 | $940 | |||
Estimated gross profit | $200 | $70 | $60 |
Table (15)
(2)
Requirement – 5
Explanation of Solution
Recognized revenue
In the year 2018:
Given,
The contract price is $10,000,000
Actual cost to date is $2,400,000
Calculated total estimated cost is $8,000,000(1)
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is $3,000,000.
In the year 2019:
Given,
The contract price is $10,000,000
Actual cost to date is $6,200,000
Calculated total estimated cost is $10,300,000
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is $3,019,417.
In the year 2020:
Given,
Contract price is $10,000,000
Calculated revenue recognition in 2018 is $3,000,000
Calculated revenue recognition in 2019 is $3,019,417
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is$3,980,583.
Recognized gross profit
In the year 2018
Here,
Estimated gross profit in 2018 is $2,000,000(3)
Total estimated cost is 8,000,000
Actual cost to date is $2,400,000
Now, calculate the gross profitrecognition:
Hence, the calculated gross profit recognition is $6,000,000.
In the year 2019
Here,
Estimated gross profit in 2019 is -$300,000(3)
Gross profit recognition in 2018 is $6,000,000.
Now, calculate the gross profitrecognition:
Hence, the calculated gross profit recognition is ($900,000).
In the year 2020
Here,
Estimated gross profit in 2020 is -$100,000 (3)
Gross profit recognition in 2018 is $600,000,
Gross profit recognition in 2019 is -$900,000.
Now, calculate the gross profitrecognition:
Hence, the calculated gross profit recognition is $200,000.
Working note
Particulars | 2018 | 2019 | 2020 |
Costs incurred during the year | $2,400,000 | $3,800,000 | $3,900,000 |
Estimated costs to complete as of year-end | $5,600,000 | $4,100,000 |
Calculate the value of estimated gross profit ($ in millions):
Particulars | 2018 | 2019 | 2020 | |||
Contract price | $1,000 | $1,000 | $1,000 | |||
Actual costs to date | $240 | $620 | $1,100 | |||
Estimated costs to complete | $560 | $410 | $0 | |||
Less: Total estimated cost | $800 | $1,030 | $1,010 | |||
Estimated gross profit | $200 | -$30 | -$10 |
(3)
Want to see more full solutions like this?
Chapter 5 Solutions
Intermediate Accounting
- Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion [LO6-9] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year- end Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Cost incurred during the year Estimated costs to complete as of year- end Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 2-b. In the journal below, complete the…arrow_forwardProblem 6-11 (Algo) Long-term contract; revenue recognition upon completion [LO6-9] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. Cost incurred during the year Estimated costs to…arrow_forwardRequired information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Problem 6-10 (Algo) Part 3 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Current liabilities: 2024 $ 2,156,000 5,544,000 2,130,000 1,865,000 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Note: Do not round intermediate calculations. 2024 2025 2026 $ 3,388,000 $ 2,371,600 2,156,000 0 3,414,000 3,300,000 2025 4,456,000…arrow_forward
- A4arrow_forwardearrow_forwardProblem 6-11 (Algo) Long-term contract; revenue recognition upon completion [LO6-9] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year. 2021 $1,584,000 5,616,000 1,200,000 1,000,000 Cost incurred during the year Estimated costs to complete as of year-end) 2022 $3,240,000 2,376,000 3,624,000 2,800,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). Cost incurred during the…arrow_forward
- Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion [LO6-9] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Cost incurred during the year Estimated costs to complete as of year-end 2021 $1,584,000 5,616,000 1,200,000 1,000,000 Cost incurred during the year Estimated costs to complete as of year-end Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).…arrow_forwardS Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Problem 6-10 (Algo) Part 3 Balance Sheet (Partial) Current assets: 2024 2025 $ 2,523,000 $ 3,177,000 6,177,000 1,800,000 2,070,000 3,630,000 1,835,000 3,400,000 Current liabilities: 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related t contract. Note: Do not round intermediate calculations. 2024 2026 $ 1,980,000 2025 0 4,300,000…arrow_forwardRequired Information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following Information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2025 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2024 2026 $ 2,490,000 5,810,000 2,030,000 $ 3,984,000 $ 2,008,600 1,826,000 в 4,444,000 3,900,000 3,526,000 4,285,000 1,815,000 Westgate recognizes revenue over time according to percentage of completion. Problem 6-10 (Algo) Part 4 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs Incurred and costs to complete Information. Note: Do not round Intermediate calculations and round your final…arrow_forward
- Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Current liabilities: Problem 6-10 (Algo) Part 3 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Note: Do not round Intermediate calculations. 2024 2024 $ 2,490,000 5,810,000 2,030,000 1,815,000 0 2025 $ 3,984,000 1,826,000 4,444,000 3,900,000 0 2025 0 2026 $ 2,008, 600 0 0…arrow_forwardRequired information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) $ $ Problem 6-10 (Algo) Part 5 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. Answer is complete but not entirely correct. 2024 2024 $ 2,016,000 5,184,000 2,180,000 1,890,000…arrow_forwardRequired information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) $ $ Problem 6-10 (Algo) Part 5 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar…arrow_forward
- Individual Income TaxesAccountingISBN:9780357109731Author:HoffmanPublisher:CENGAGE LEARNING - CONSIGNMENT