Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the Caribbean: On Stranger Tides (starring Johnny Depp), identified 16 activities to be completed before the release of the film.
a) How many weeks in advance of the film release should Four Squares have started its marketing campaign? What is the critical path? The tasks (in time units of weeks) are as follows:
b) What is the probability of completing the marketing campaign in the time (in weeks) noted in pan a?
c) If activities I and J were not necessary, what impact would this have on the critical path and the number of weeks needed to complete the marketing campaign?
Want to see the full answer?
Check out a sample textbook solutionChapter 3 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
- A Social Project manager is faced with a project with the following activities: Activity-ID Description Duration 1-2 Social Work Team to live in Village 5 Weeks 1-3 Social Research Team to do survey 12 Weeks 3-4 Analyse results of survey 5 Weeks 2-4 Establish Mother & Child Health Program 14 Weeks 3-5 Establish Rural Credit Programme 15 Weeks 4-5 carry out Immunisation of under Fives 4 Weeks Draw the arrow diagram, using the helpful numbering of the activities, which suggests the…arrow_forwardA Social Project manager is faced with a project with the following activities: Activity-ID Description Duration 1-2 Social Work Team to live in Village 5 Weeks 1-3 Social Research Team to do survey 12 Weeks 3-4 Analyse results of survey 5 Weeks 2-4 Establish Mother & Child Health Program 14 Weeks 3-5 Establish Rural Credit Programme 15 Weeks 4-5 carry out Immunisation of under Fives 4 Weeks Draw the arrow diagram, using the helpful numbering of the activities, which suggests the…arrow_forwardFor Activity A, B, C, D, E, F, Garrow_forward
- A tank has been decommissioned for some years and there is a need to remove this tank as the land is required for other purposes. It is suspected of not being emptied properly and is now rusting and that waste of an indeterminate nature has been pumped into it in the past ie. Nobody knows with certainty what is in the tank. Provide an outline of how a HAZOP study needs to be set up for this project. Marking Guidance: a) Describing problem b) Preparation phase c) Examination phase d) Reporting and follow-up phasearrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) B A, D C E, F This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B - D - E - G. c) The project length for the leadership training program development project = 28 days. d) Slack time for each of the activities is: ABCDEFG Activity A Slack Time ∞ or w w w 10arrow_forwardA competitor of Kozar International Inc. has begun marketing a new, instant-developing film project. Kozar has had a similar product under study in its research and development (R&D) department but has not yet been able to begin production. Because of the competitor’s action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are as follows: Draw the Project Networkarrow_forward
- A competitor of Kozar International Inc. has begun marketing a new, instant-developing film project. Kozar has had a similar product under study in its research and development (R&D) department but has not yet been able to begin production. Because of the competitor’s action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are as follows: Develop an activity schedule for this project using early and late start and finish times, compute activity slack time and define the critical activities.arrow_forwardA competitor of Kozar International Inc. has begun marketing a new, instant-developing film project. Kozar has had a similar product under study in its research and development (R&D) department but has not yet been able to begin production. Because of the competitor’s action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are as follows: A: Draw the Project Network B: Develop an activity schedule for this project using early and late start and finish times, compute activity slack time, and define the critical activities.arrow_forwardMary is planning her wedding and develops the following preliminary information. Construct an early start date Gantt chart.arrow_forward
- Farihah is a project manager for a systems development project involving a new database application for her organization’s human resources department. Despite Farihah’s best efforts at estimating the time requirements for the project, the team has missed the deadline for completing the Analysis Phase and producing the System Proposal. Farihah had estimated during her 6-week Planning Phase that Analysis would require 2 months, but the team finished the System Proposal 2 weeks behind their planned target date. Based on her discussions with the team members, Farihah believes that the system is more complex than she originally thought. Should Farihah adjust her timeline, or can she try to make up for the lost two weeks? Farihah needs your advice.arrow_forwardPlease solve my Problem as Soon as possible. Thank You!arrow_forwardI'm unable to answer the following question? What is the total cost of crashing the project from its current duration down to 13 weeks?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.