Chapter 3, Problem 19PE

Explanation of Solution

Network diagram:

The network diagram for the activities:

Explanation of Solution

Earliest expected completion time:

  • The earliest expected completion time is calculated by using time of each activity.
  • The box in a network diagram represents the activity. Each box consists of activity and time.
  • The start state is activity 1 and end state is 10. Each box consists of four values Early finish, Early start, Late start and Late finish.
  • The early start for first activity is 0 because it contains no predecessor.
  • Early finish is the sum of early start and time. Early start of the next activity is the early finish of its predecessor activity...

Explanation of Solution

Critical path:

  • For calculating critical path, select all activities that contain slack value 0...

Explanation of Solution

Activity 6 revised to take 6 weeks:

  • If the time of activity 6 is changed to 6 weeks instead of 2 weeks, then the critical will be changed...

Blurred answer
Students have asked these similar questions
What should the next three steps be in my machine based home security system after deployment and after the following current steps: Enhancing Security & Privacy Measures User Interface (UI) and Experience (UX) Improvement  Machine Learning Model Refinement & Continuous Improvement
I am creating a machine learning home based security system, have completed initial deployment and in the following phases of the project: Expanding device compatibility and integration, preparing for cloud integration, and implementing system reduncancy and disaster recovery. What should the next three phases be?
Hands-On Assignments Part II Assignment 1-5: Querying the DoGood Donor Database Review the DoGood Donor data by writing and running SQL statements to perform the following tasks: 1. List each donor who has made a pledge and indicated a single lump sum payment. Include first name, last name, pledge date, and pledge amount. 2. List each donor who has made a pledge and indicated monthly payments over one year. Include first name, last name, pledge date, and pledge amount. Also, display the monthly payment amount. (Equal monthly payments are made for all pledges paid in monthly payments.) 3. Display an unduplicated list of projects (ID and name) that have pledges committed. Don't display all projects defined; list only those that have pledges assigned. 4. Display the number of pledges made by each donor. Include the donor ID, first name, last name, and number of pledges. 5. Display all pledges made before March 8, 2012. Include all column data from the DD PLEDGE table.

Chapter 3 Solutions

Essentials of Systems Analysis and Design (6th Edition)

Ch. 3 - Prob. 11MCh. 3 - A graphical representation of a project that shows...Ch. 3 - Prob. 13MCh. 3 - Prob. 14MCh. 3 - A systems analyst with a diverse set of...Ch. 3 - The second phase of the project management...Ch. 3 - Prob. 17MCh. 3 - Prob. 18MCh. 3 - Prob. 19MCh. 3 - Prob. 20MCh. 3 - Prob. 1RQCh. 3 - Prob. 2RQCh. 3 - Prob. 3RQCh. 3 - Prob. 4RQCh. 3 - Prob. 5RQCh. 3 - Prob. 6RQCh. 3 - Prob. 7RQCh. 3 - Prob. 8RQCh. 3 - Prob. 9RQCh. 3 - Describe the steps involved in making a network...Ch. 3 - In which phase of the systems development life...Ch. 3 - What are some reasons why one activity may have to...Ch. 3 - Which of the four phases of the project management...Ch. 3 - What are some sources of risk in a systems...Ch. 3 - Search the Web for recent reviews of project...Ch. 3 - Prob. 16PECh. 3 - Prob. 17PECh. 3 - Prob. 18PECh. 3 - Prob. 19PECh. 3 - Construct a Gantt chart for the project defined in...Ch. 3 - Look again at the activities outlined in Problem...Ch. 3 - Prob. 25PECh. 3 - Prob. 26PECh. 3 - Prob. 27PECh. 3 - Prob. 29PECh. 3 - Prob. 30PECh. 3 - Prob. 31PECh. 3 - Prob. 32PECh. 3 - Prob. 33DQCh. 3 - Do you agree that breaking projects down into...Ch. 3 - Microsoft Project is powerful but expensive....Ch. 3 - When completing a project, some tasks are...Ch. 3 - a. While eating lunch one day, Juanita asked Chris...Ch. 3 - What qualities might Jim possess that would make...Ch. 3 - Prob. 41CQCh. 3 - Prob. 42CQCh. 3 - What should Jim do next to complete the project...Ch. 3 - Prob. 44CQ
Knowledge Booster
Background pattern image
Computer Science
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Enhanced Discovering Computers 2017 (Shelly Cashm...
Computer Science
ISBN:9781305657458
Author:Misty E. Vermaat, Susan L. Sebok, Steven M. Freund, Mark Frydenberg, Jennifer T. Campbell
Publisher:Cengage Learning
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Management Of Information Security
Computer Science
ISBN:9781337405713
Author:WHITMAN, Michael.
Publisher:Cengage Learning,
Text book image
Principles of Information Security (MindTap Cours...
Computer Science
ISBN:9781337102063
Author:Michael E. Whitman, Herbert J. Mattord
Publisher:Cengage Learning
Text book image
Fundamentals of Information Systems
Computer Science
ISBN:9781305082168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole