Interpretation: As there was a concern pertaining to the number of faults in the billing process of Data Tech Credit Card Service Company, the manager of customer service has done a random inspection on 250 statements, for errors, that has happened to wrong entries that involved penalty charges, account numbers, charges levied on interests and customer account transactions. If there are one or more the errors, in the heads mentioned above, then that statement is considered as a defect. The Table 3.5 represents the data collected from the study for the last 30 days. A p-chart for the billing process needs to be constructed.
Sample | Number of errors in Sample of 250 | |||||||||
1 − 10 | 3 | 8 | 5 | 11 | 7 | 1 | 12 | 9 | 0 | 8 |
11 − 20 | 3 | 5 | 7 | 9 | 11 | 3 | 2 | 9 | 13 | 4 |
21 - 30 | 12 | 10 | 6 | 2 | 1 | 7 | 10 | 5 | 8 | 4 |
Table 3.5
Concept Introduction: A process is analyzed between the limits of control and evaluated whether the same is under control or not, identifying the count of defects present. A p-chart reflects the proportion of defects that a process has.
(b)
Interpretation: As there was a concern pertaining to the number of faults in the billing process of Data Tech Credit Card Service Company, the manager of customer service has done a random inspection on 250 statements, for errors, that has happened to wrong entries that involved penalty charges, account numbers, charges levied on interests and customer account transactions. If there are one or more the errors, in the heads mentioned above, then that statement is considered as a defect. The Table 3.5 represents the data collected from the study for the last 30 days. Any non-random behavior in the billing process that would require management attention needs to be found out.
Sample | Number of errors in Sample of 250 | |||||||||
1 − 10 | 3 | 8 | 5 | 11 | 7 | 1 | 12 | 9 | 0 | 8 |
11 − 20 | 3 | 5 | 7 | 9 | 11 | 3 | 2 | 9 | 13 | 4 |
21 - 30 | 12 | 10 | 6 | 2 | 1 | 7 | 10 | 5 | 8 | 4 |
Table 3.5
Concept Introduction: A process is analyzed between the limits of control and evaluated whether the same is under control or not, identifying the count of defects present. A p-chart reflects the proportion of defects that a process has.
Want to see the full answer?
Check out a sample textbook solutionChapter 3 Solutions
OPERATIONS MANAGEMENT CUSTOM ACCESS
- The project management team of Solar Systems has developed a network consisting of the following list of activities in installing its solar panels. Times are given in weeks. Activity Most Preceding Optimistic( a) likely(m) Pessimistic(b) A 5 11 14 B 3 3 9 C - 6 10 14 D A, B 3 5 7 E B 4 6 11 F C 6 8 13 G D, E 2 4 6 H F 3. 3 9 Required: A. Draw the activity network for this problem (either AON or AOA). B. Determine the Expected Time and Variance for each activity. C. D. Show the activity schedule (ES, EF, LS, and LF) as well as slack (in table) Determine and state the critical path for this project. This must be based on your work in and not by inspection. (ii). What are the expected time and the variance of the project? What is the probability the project will be finished within 25 weeks?arrow_forward2x+y-3z=9 x-3y+6z=5 3x+2y+z=20 Solve the following system of simultaneous equation using the Cramer's rulearrow_forwardThe frequency of breakdown of a machine that issues lottery tickets is given in the following table. Repairs cost an average of $240. A service firm is willing to provide preventive maintenance under either of two options: #1 is $500 and covers all necessary repairs, and #2 is $350 and covers any repairs after the first one. Which option would have the lowest expected cost: pay for all repairs, service option #1, or service option #2? Number of Breakdowns/Month 0 1 2 3 4 Frequency of Occurrence .10 .30 .30 .20 .10arrow_forward
- 1. William Beville's computer training school, in Richmond, stocks workbooks with the following characteristics: Demand D = 19,500 units / year Ordering cost S = $25 / order Holding Cost H = $4 / unit / year a) Calculate the EOQ for the workbooks b) What are the annual holding costs for the workbooks? c) What are the annual ordering costs? 2. What is the purpose of the ABC classification system? 3. What is "safety stock"? What does safety stock provide safety against? Explain your answer Replyarrow_forwardSammy's Soldier, manufactures paints. Its costing system utilizes two cost categories, direct materials and conversion costs. Each product must pass through Department A and Department B. Direct materials are added at the beginning of production. Conversion costs are allocated evenly throughout production. Data for Department A for February 2017 are: Work in process, beginning inventory, 30% converted.............. 200 units Units started during February............................................................... 800 units Work in process, ending inventory..................................................... 240 units Costs for Department A for February 2017 are: Work in process, beginning inventory: Direct materials.................................................. $150,000 Conversion costs............................................................................................................................. $210,000 Direct materials costs added during…arrow_forwardConsider the following data collected for Albo's Rentals: Direct Materials Direct Manufacturing Labor Cost incurred Actual inputs x Actual prices $210,000 $95,000 Actual inputs x standard prices 214,000 88,000 Standard inputs allowed for actual output x standard prices 220,000 85,000 Required: Compute the price and efficiency variances for direct materials: Question 17Answer a. Price $4000 F; Efficiency $10000 U b. Price $5000 F; Efficiency $5000 F c. Price $4000 F; Efficiency $6000 F d. Price $10000 U; Efficiency $4000 Farrow_forward
- Already got wrong Chatgpt answer Plz don't use chat gptarrow_forwardMany artists and art lovers embrace the idea of the “starving artist,” such as the early career artist who hasn’t yet sold much of her art or whose art hasn’t yet been “discovered,” the artist who sacrifices lifestyle, living in a cheap apartment in a poor neighborhood, scraping by with barely enough to eat, pouring every dollar at their disposal into his art, or the artist who makes do by working other jobs, such as a waiter or waitress, to pay the rent so he can work on his art in his free time. As an artist and businessperson, however, you’d rather not be a “starving artist.” Of course, it takes time to master your art, display your work, and build a following, but is it necessary if you’re successful as an artist to also be a bad businessperson. The challenge with your art, bronze sculptures, however, is what comes first, the chicken or the egg, in other words, success as an artist or financial success. With the cost of materials, foundry time to pour and shape your creations,…arrow_forwardCan you guys help me with this? Thank you! Here is the article's title by Murray Stassen about the current event: Clemens Trautmann promoted to President of Deutsche Grammophon and New Business Strategy This assignment requires the use of the concepts and theories learned to analyze a current event in the business world. It needs to be relevant to strategic management and has the quality of analysis of the situation from the article. From this situation, which of these concepts and theories could be applied to? * Five Generic Competitive Strategies: + Broad Low-Cost Strategy + Broad Differentiation Strategy + Focused Low-Cost Strategy + Focused Differentiation Strategy + Best-Cost Strategy * Ethical Universalism * Ethical Relativism * Corporate Social Responsibilityarrow_forward
- Identify the causes of the problem. -Start by Reviewing the Inputs box in the Organizing Framework to help you identify the causes of the problem in this case. First identify the person factors and then situation factors as inputs. -Then move to the Processes box in the Organizing Framework and review the potential causes among individual level, team level and organizational level factors. -For each cause explain why this is a cause of the problem. For each cause ask yourself “why” is this a cause to the problem we identified. Remember that asking why multiple times will help you find the root cause of the problem.arrow_forward6. Develop a POQ solution and calculate total relevant costs for the data in the following table. Period 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 30 40 30 70 20 10 80 50 Holding cost =$2.50/unit/week Holding cost =$2.50/unit/week; setup cost =$150setup cost =$15 0; lead time =1 week lead time =1 week; beginning inventory =40beginning inventory =40.arrow_forward5. Develop a lot-for-lot solution and calculate total relevant costs for the data in the following table. Period 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 30 40 30 70 20 10 80 50 Holding cost =$2.50/unit/week Holding cost =$2.50/unit/week; setup cost =$150setup cost =$15 0; lead time =1 week lead time =1 week; beginning inventory =40beginning inventory =40.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.