Question
Book Icon
Chapter 2, Problem 8P

a)

Summary Introduction

To determine: The suitable outsourcing provider using factor- rating method.

Introduction:

Factor-rating method:

The factor-rating method is a quantitative approach to make a decision from various alternatives such that the decision is beneficial to the firm involved. This method is utilized to decide on new layout, new locations, best supplier, outsourcing providers etc.

a)

Expert Solution
Check Mark

Answer to Problem 8P

The suitable outsourcing provider is Canada.

Explanation of Solution

Given information:

Selection criterion Weight England Canada
Price of service from outsourcer 0.1 2 3
Nearness of facilities to client 0.6 3 1
Level of technology 0.2 1 3
History of successful outsourcing 0.1 1 2

Low Risk = 1

High Risk = 3

Formula to calculate weighted risk:

Weighted Risk = Weight × Risk rating

Formula to calculate Total weighted risk:

Total weighted risk = Individualweightedrisk

Principles Of Operations Management, Chapter 2, Problem 8P , additional homework tip  1

Excel Formula:

Principles Of Operations Management, Chapter 2, Problem 8P , additional homework tip  2

Calculation of weighted risk for England:

The weighted risk is calculated my multiplying the weights with risk rating of each criteria.

The weighted risk is calculated as follows:

Service from outsourcer:

Price of service from outsourcer = 0.1 × 2=0.2

The weighted risk for price of service from outsourcer is 0.2.

Nearness of facilities to client:

Nearness of facilities to client = 0.6 × 3=1.8

The weighted risk for Nearness of facilities to client is 1.8.

Level of Technology:

Level of Technology = 0.2 × 1=0.2

The weighted risk for Level of Technology is 0.2.

History of successful outsourcing:

History of successful outsourcing = 0.1 × 1=0.1

The weighted risk for History of successful outsourcing is 0.1.

Calculation of Total weighted risk:

The total weighted risk is calculated be summing all the weighted risk values.

Total weighted risk = 0.2 + 1.8 + 0.2 + 0.1= 2.3

The total weighted risk for England is 2.3.

Calculation of weighted risk for Canada:

The weighted risk is calculated my multiplying the weights with risk rating of each criteria.

The weighted risk is calculated as follows:

Price of service from outsourcer:

Price of service from outsourcer = 0.1 × 3=0.3

The weighted risk for price of service from outsourcer is 0.3.

Nearness of facilities to client:

Nearness of facilities to client = 0.6 × 1=0.6

The weighted risk for nearness of facilities to client is 0.6.

Level of Technology:

Level of Technology = 0.2 × 3=0.6

The weighted risk for Level of Technology is 0.6.

History of successful outsourcing:

History of successful outsourcing = 0.1 × 2=0.2

The weighted risk for History of successful outsourcing is 0.2.

Calculation of Total weighted risk:

The total weighted risk is calculated be summing all the weighted risk values.

Total weighted risk = 0.3 + 0.6 + 0.6 + 0.2= 1.7

The total weighted risk for Canada is 1.7.

The weighted risk value for England is 2.3. The weighted risk value for Canada is 1.7. Since, the risk value for Canada is less for England (1.7 < 2.3), Canada is selected.

The suitable outsourcing provider is Canada.

b)

Summary Introduction

To determine: The impact of doubling the weights used in part (a).

Introduction:

Factor-rating method:

The factor-rating method is a quantitative approach to make a decision from various alternatives such that the decision is beneficial to the firm involved. This method is utilized to decide on new layout, new locations, best supplier, outsourcing providers etc.

b)

Expert Solution
Check Mark

Answer to Problem 8P

The Doubling of weights will have No Change.

Explanation of Solution

Given information:

Selection criterion Weight England Canada
Price of service from outsourcer 0.2 2 3
Nearness of facilities to client 1.2 3 1
Level of technology 0.4 1 3
History of successful outsourcing 0.2 1 2

Low Risk = 1

High Risk = 3

Formula to calculate weighted risk:

Weighted Risk = Weight × Risk rating

Formula to calculate Total weighted risk:

Total weighted risk = Individualweightedrisk

Principles Of Operations Management, Chapter 2, Problem 8P , additional homework tip  3

Excel Formula:

Principles Of Operations Management, Chapter 2, Problem 8P , additional homework tip  4

Calculation of weighted risk for England:

The weighted risk is calculated my multiplying the weights with risk rating of each criteria.

The weighted risk is calculated as follows:

Price of service from outsourcer:

Price of service from outsourcer = 0.2 × 2=0.4

The weighted risk for price of service from outsourcer is 0.4.

Nearness of facilities to client:

Nearness of facilities to client = 1.2 × 3=3.6

The weighted risk for nearness of facilities to client is 3.6.

Level of Technology:

Level of Technology = 0.4 × 1=0.4

The weighted risk for Level of Technology is 0.4.

History of successful outsourcing:

History of successful outsourcing = 0.2 × 1=0.2

The weighted risk for History of successful outsourcing is 0.2.

Calculation of Total weighted risk:

The total weighted risk is calculated be summing all the weighted risk values.

Total weighted risk = 0.4 + 3.6 + 0.4 + 0.2= 4.6

The total weighted risk for England is 4.6.

Calculation of weighted risk for Canada:

The weighted risk is calculated my multiplying the weights with risk rating of each criteria.

The weighted risk is calculated as follows:

Price of service from outsourcer:

Price of service from outsourcer = 0.2 × 3=0.6

The weighted risk for price of service from outsourcer is 0.6.

Nearness of facilities to client:

Nearness of facilities to client = 1.2 × 1= 1.2

The weighted risk for nearness of facilities to client is 1.2.

Level of Technology:

Level of Technology = 0.4 × 3=1.2

The weighted risk for Level of Technology is 1.2.

History of successful outsourcing:

History of successful outsourcing = 0.2 × 2=0.4

The weighted risk for History of successful outsourcing is 0.4.

Calculation of Total weighted risk:

The total weighted risk is calculated be summing all the weighted risk values.

Total weighted risk = 0.6 + 1.2 + 1.2 + 0.4= 3.4

The total weighted risk for Canada is 3.4.

The weighted risk value for England is 4.6. The weighted risk value for Canada is 3.4. Since, the risk value for Canada is less for England (3.4 < 4.6), Canada is selected.

The doubling of weights of the risk avoidance criteria does not alter the result arrived at in part (a). The weighted risk value is doubled for England and Canada. But, the risk value of Canada is still lower than England. The result will not change irrespective of doubling the weights because the risk avoidance criterion value is unaltered.

Hence, the Doubling of weights will have No Change.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Could you please help explain How was the poor strategic decisions lead to economic downturns of Circuit City Company? What are the sequences of key events and problems that contribute to its collapse. Could you please explain each one them and give the examples If Circuit City would apply Lean Six Sigma. would it helped prevent businesses from collapsed?? How Qualitative and quantitative Research Methodology in Case Study Research would affect Circuit City?
Apple is a global technology company renowned for its innovation and design. To create its products, Apple has established a world class global supply chain to bring their products to market. What strategies is Apple using to source and manufacture its products? How does Apple view its responsibility to its suppliers and those who build its products?
Critical Path Method (CPM) is an important Project Management Tool that has wide industry application in modern day Project Management. By using an example of the project of your choice, critically examine the practical application of CPM as a Project Management Tool.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Contemporary Marketing
    Marketing
    ISBN:9780357033777
    Author:Louis E. Boone, David L. Kurtz
    Publisher:Cengage Learning
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Contemporary Marketing
Marketing
ISBN:9780357033777
Author:Louis E. Boone, David L. Kurtz
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing