Question
Book Icon
Chapter 2, Problem 12P
Summary Introduction

To determine: The range of values for ‘w’ such that Company C is a recommended outsourcing provider using factor rating method.

Introduction:

Factor-rating method:

The factor-rating method is a quantitative approach to make a decision from various alternatives such that the decision is beneficial to the firm involved. This method is utilized to decide on new layout, new locations, best supplier, outsourcing providers etc.

Expert Solution & Answer
Check Mark

Answer to Problem 12P

Company C is recommended for all values of w such that 1 ≤ w ≤ 25.

Explanation of Solution

Given information:

Ratings of Outsource providers
Factor Weight A B C D
Labor W 5 4 3 5
Quality Procedures 30 2 3 5 1
Logistics System 5 3 4 3 5
Price 25 5 3 4 4
Trustworthiness 5 3 2 3 5
Technology in place 15 2 5 4 4
Management team 15 5 4 2 1

Weights or an scale = 1 - 30

Formula to calculate weighted rating:

Weighted Rating = Importance Weight × rating

Formula to calculate Total weighted rating:

Total weighted rating = Individualweighted rating

Calculation for A:

Calculation of weighted rating:

The weighted rating is calculated by multiplying the importance weighted with individual rating.

Labor:

Labor = w × 5= 5w

The weighted rating for Labor is 5w.

Quality procedures:

Quality procedures = 30 × 2= 60

The weighted rating for Quality procedures is 60.

Logistics System:

Logistiscs System = 5 × 3= 15

The weighted rating for Logistics System is 15.

Price:

Price = 25 × 5= 125

The weighted rating for Price is 125.

Trustworthiness:

Trustworthiness = 5 × 3= 15

The weighted rating for Trustworthiness is 15.

Technology in place:

Technology in place = 15 × 2= 30

The weighted rating for Technology in place is 30.

Management Team:

Management team = 15 × 5= 75

The weighted rating for Management Team is 75.

Calculation of total weighted rating:

The total weighted rating is calculated by the summation of the individual weighted ratings.

Total weighted rating = 5w + 60 + 15 + 125 + 15 + 30 + 75= 5w + 320

The total weighted rating for A is 5w + 320.

Calculation for B:

Calculation of weighted rating:

The weighted rating is calculated by multiplying the importance weighted with individual rating.

Labor:

Labor = w × 4= 4w

The weighted rating for Labor is 4w.

Quality procedures:

Quality procedures = 30 × 3= 90

The weighted rating for Quality procedures is 90.

Logistics System:

Logistiscs System = 5 × 4= 20

The weighted rating for Logistics System is 20.

Price:

Price = 25 × 3= 75

The weighted rating for Price is 75.

Trustworthiness:

Trustworthiness = 5 × 2= 10

The weighted rating for Trustworthiness is 10.

Technology in place:

Technology in place = 15 × 5= 75

The weighted rating for Technology in place is 75.

Management Team:

Management team = 15 × 4= 60

The weighted rating for Management Team is 60.

Calculation of total weighted rating:

The total weighted rating is calculated by the summation of the individual weighted ratings.

Total weighted rating = 4w + 90 + 20 + 75 + 10 + 75 + 60= 4w + 330

The total weighted rating for B is 4w + 330.

Calculation for C:

Calculation of weighted rating:

The weighted rating is calculated by multiplying the importance weighted with individual rating.

Labor:

Labor = w × 3= 3w

The weighted rating for Labor is 3w.

Quality procedures:

Quality procedures = 30 × 5= 150

The weighted rating for Quality procedures is 150.

Logistics System:

Logistiscs System = 5 × 3= 15

The weighted rating for Logistics System is 15.

Price:

Price = 25 × 4= 100

The weighted rating for Price is 100.

Trustworthiness:

Trustworthiness = 5 × 3= 15

The weighted rating for Trustworthiness is 15.

Technology in place:

Technology in place = 15 × 4= 60

The weighted rating for Technology in place is 60.

Management Team:

Management team = 15 × 2= 30

The weighted rating for Management Team is 30.

Calculation of total weighted rating:

The total weighted rating is calculated by the summation of the individual weighted ratings.

Total weighted rating = 3w + 150 + 15 + 100 + 15 + 60 + 30= 3w + 370

The total weighted rating for C is 3w + 370.

Calculation for D:

Calculation of weighted rating:

The weighted rating is calculated by multiplying the importance weighted with individual rating.

Labor:

Labor = w × 5= 5w

The weighted rating for Labor is 5w.

Quality procedures:

Quality procedures = 30 × 1= 30

The weighted rating for Quality procedures is 30.

Logistics System:

Logistiscs System = 5 × 5= 25

The weighted rating for Logistics System is 25.

Price:

Price = 25 × 4= 100

The weighted rating for Price is 100.

Trustworthiness:

Trustworthiness = 5 × 5= 25

The weighted rating for Trustworthiness is 25.

Technology in place:

Technology in place = 15 × 4= 60

The weighted rating for Technology in place is 60.

Management Team:

Management team = 15 × 1= 15

The weighted rating for Management Team is 15.

Calculation of total weighted rating:

The total weighted rating is calculated by the summation of the individual weighted ratings.

Total weighted rating = 5w + 30 + 25 + 100 + 25 + 60 + 15= 5w + 255

The total weighted rating for D is 5w + 255.

Calculation of range of values for w:

The range of values is calculated by equating the total weighted rating of C with all the other outsourcing providers.

Equating C with A:

3w + 370  5w + 320370 - 320  5w - 3w50  2w25  w (1)

Equating C with B:

3w + 370  4w + 330370 - 330  4w - 3w40  w (2)

Equating C with D:

3w + 370  5w + 255370 - 255  5w - 3w115  2w57.5  w (3)

The weights are scaled from 1 – 30 as given in the question. The value of w can only be in the range of 1 to 30. From (1), (2), and (3) the range of ‘w’ so that C is the best outsourcing provider is w ≤ 25. It means that ‘w’ can be assigned a value starting from 1 to 25.

Company C is recommended for all values of ‘w’ such that 1 ≤ w ≤ 25.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
3. [25 pts.] Four projects are available for investment. The projects require the cash flows and yield the net present values (NPV) (in millions) shown in the following table. Project id. 1 2 Cash outflow at time 0 (million Lira) 8 8 NPV (million Lira) 12 11 3 4 6 5 8 6 If 20 million Lira is available for investment at time 0, find the investment plan that maximizes NPV. All investments are required to be 0 or 1 (fractional investment values are not permitted). a. Formulate the mathematical model. (Write the decision variables, objective function and the constraints.) [10 pts.] b. Find the optimal solution by using Branch and Bound method (Draw the branch and bound tree clearly, write also lower bounds(LB)) (Left branches x=0, right branches x =1) [15 pts.].
examine the production concept and operations management, what are the key steps required to achieve success?  Be specific in your response.
Produce a 3000 report with references on one international organization of your choice and Address the following: Provide a brief introduction of the organisation and sector it operates in, including its mission and vision statements, its core values, a summary of its financial performance and a general overview of the business’s operational activities. From the relevant literature explain the Total Quality Management (TQM) processes the chosen organization follows and identify one quality challenge/issue that the organization faced or is currently facing. Explain how the organization managed/or still managing the particular quality challenge/issue. Critically analyze whether the organization failed or succeeded in achieving and maintaining quality performance. Provide a few critical recommendations for business managers in order to highlight the importance of Total Quality Management (TQM) within an organization.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
    Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
  • Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
    Text book image
    Principles of Management
    Management
    ISBN:9780998625768
    Author:OpenStax
    Publisher:OpenStax College
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College