To determine: The range of values for ‘w’ such that Company C is a recommended outsourcing provider using factor rating method.
Introduction:
Factor-rating method:
The factor-rating method is a quantitative approach to make a decision from various alternatives such that the decision is beneficial to the firm involved. This method is utilized to decide on new layout, new locations, best supplier, outsourcing providers etc.

Answer to Problem 12P
Company C is recommended for all values of w such that 1 ≤ w ≤ 25.
Explanation of Solution
Given information:
Ratings of Outsource providers | |||||
Factor | Weight | A | B | C | D |
Labor | W | 5 | 4 | 3 | 5 |
Quality Procedures | 30 | 2 | 3 | 5 | 1 |
Logistics System | 5 | 3 | 4 | 3 | 5 |
Price | 25 | 5 | 3 | 4 | 4 |
Trustworthiness | 5 | 3 | 2 | 3 | 5 |
Technology in place | 15 | 2 | 5 | 4 | 4 |
Management team | 15 | 5 | 4 | 2 | 1 |
Weights or an scale = 1 - 30
Formula to calculate weighted rating:
Formula to calculate Total weighted rating:
Calculation for A:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the importance weighted with individual rating.
Labor:
The weighted rating for Labor is 5w.
Quality procedures:
The weighted rating for Quality procedures is 60.
Logistics System:
The weighted rating for Logistics System is 15.
Price:
The weighted rating for Price is 125.
Trustworthiness:
The weighted rating for Trustworthiness is 15.
Technology in place:
The weighted rating for Technology in place is 30.
Management Team:
The weighted rating for Management Team is 75.
Calculation of total weighted rating:
The total weighted rating is calculated by the summation of the individual weighted ratings.
The total weighted rating for A is 5w + 320.
Calculation for B:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the importance weighted with individual rating.
Labor:
The weighted rating for Labor is 4w.
Quality procedures:
The weighted rating for Quality procedures is 90.
Logistics System:
The weighted rating for Logistics System is 20.
Price:
The weighted rating for Price is 75.
Trustworthiness:
The weighted rating for Trustworthiness is 10.
Technology in place:
The weighted rating for Technology in place is 75.
Management Team:
The weighted rating for Management Team is 60.
Calculation of total weighted rating:
The total weighted rating is calculated by the summation of the individual weighted ratings.
The total weighted rating for B is 4w + 330.
Calculation for C:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the importance weighted with individual rating.
Labor:
The weighted rating for Labor is 3w.
Quality procedures:
The weighted rating for Quality procedures is 150.
Logistics System:
The weighted rating for Logistics System is 15.
Price:
The weighted rating for Price is 100.
Trustworthiness:
The weighted rating for Trustworthiness is 15.
Technology in place:
The weighted rating for Technology in place is 60.
Management Team:
The weighted rating for Management Team is 30.
Calculation of total weighted rating:
The total weighted rating is calculated by the summation of the individual weighted ratings.
The total weighted rating for C is 3w + 370.
Calculation for D:
Calculation of weighted rating:
The weighted rating is calculated by multiplying the importance weighted with individual rating.
Labor:
The weighted rating for Labor is 5w.
Quality procedures:
The weighted rating for Quality procedures is 30.
Logistics System:
The weighted rating for Logistics System is 25.
Price:
The weighted rating for Price is 100.
Trustworthiness:
The weighted rating for Trustworthiness is 25.
Technology in place:
The weighted rating for Technology in place is 60.
Management Team:
The weighted rating for Management Team is 15.
Calculation of total weighted rating:
The total weighted rating is calculated by the summation of the individual weighted ratings.
The total weighted rating for D is 5w + 255.
Calculation of range of values for w:
The range of values is calculated by equating the total weighted rating of C with all the other outsourcing providers.
Equating C with A:
Equating C with B:
Equating C with D:
The weights are scaled from 1 – 30 as given in the question. The value of w can only be in the range of 1 to 30. From (1), (2), and (3) the range of ‘w’ so that C is the best outsourcing provider is w ≤ 25. It means that ‘w’ can be assigned a value starting from 1 to 25.
Company C is recommended for all values of ‘w’ such that 1 ≤ w ≤ 25.
Want to see more full solutions like this?
Chapter 2 Solutions
Principles Of Operations Management
- Apple is a global technology company renowned for its innovation and design. To create its products, Apple has established a world class global supply chain to bring their products to market. What strategies is Apple using to source and manufacture its products? How does Apple view its responsibility to its suppliers and those who build its products?arrow_forwardCritical Path Method (CPM) is an important Project Management Tool that has wide industry application in modern day Project Management. By using an example of the project of your choice, critically examine the practical application of CPM as a Project Management Tool.arrow_forwardwhat is an other difination for principle?arrow_forward
- Need help or ideas to design out two slides as my script and writing quite long to squeese into two slides. But can just point form in slides with correct title and a good script for me to present two slides in only 2.5 mins. Following is my draft, pls guide me step by step on powerpoint creation and good script to present findings. My draft: Slide 1: Foreign Labor Exploitation in Dyson's Supply Chain Introduction Dyson's former Malaysian supplier, ATA IMS Bhd, became embroiled in serious labor exploitation allegations in 2021. These concerns surfaced when whistleblowers exposed unethical labor practices affecting migrant workers, primarily from Nepal and Bangladesh. Key Forms of Exploitation Debt Bondage Due to Recruitment Fees Workers were forced to pay exorbitant recruitment fees before securing employment, often taking loans at high interest rates. This financial burden trapped them in debt bondage, leaving them with little choice but to accept exploitative working…arrow_forwardNot use ai pleasearrow_forwardThe Business Development Bank of Canada. (2023). Canadian economic outlook for 2024: Shifting into neutral. https://www.bdc.ca/en/articles-tools/blog/canadian-economic-outlook-for-2024-shifting-into-neutral “Despite persistently high inflation and rising interest rates, the news was generally better than expected for the Canadian economy in 2023” (BDC Blog 2024). Discussion Question: In your view, what are the most pressing problems for Canadian companies or consumers in 2024? Explain your answer using current examples of companies or consumer concerns.arrow_forward
- how have idividual objectives led to the current situation at TeraCog? what should Emaa do?arrow_forwardCan you write me an email about addressing an issue to mentor my supervisor the right way of deligating operations dutiesarrow_forwardCan you right me an email about addressing an issue to mentor the right why of deligating operations dutiesarrow_forward
- Define delegation. Discuss in detail the four reasons why managers do delegation? Also statethe four main types of delegation.arrow_forwardB) Going forward, is Lean/JIT worth the risks? Should it be embraced (why?), abandoned (if so, why & what are the costs), or modified (how?) Do you think Lean works or not? Please write a complete response (about 1-2 paragraphs each part). Each team member should discuss and contribute so that the group agrees on their joint response. Please help each other and build upon and/or challenge others' points (in a respectful way!)arrow_forwardDiscuss the principle reasons that employee benefits have risen over the past 20 years, along with how best an organization can provide employees with a fair wage yet also provide some level of employee benefit coverage.arrow_forward
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing