Evan Schwartz has six jobs wailing to be processed through his machine. Processing time (in days) and due date information for each job are as follows:
Sequence the jobs by FCFS, SPT, SLACK, and DDATE. Calculate (he mean flow time and mean tardiness of the six jobs under each sequencing rule. Which rule would you recommend?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Eight jobs have arrived in the following order:
Job Processing Time Due Date
1
25
11
12
9
2
3
4
5
6
7
8
9
5
11
st
4
10
7
16
6
18
16
Find and compare the performance measures for the following sequencing rules using the Excel Sequencing template.
Round your answers to two decimal places.
A. Process in the order they have arrived
24
42
Average
Flow Time Lateness Tardiness
Average
B. Shortest processing time
The SPT sequence is 4, 2, 8, 6, 1, 5, 3, 7
Flow Time Lateness Tardiness
Average
Earliest due date
The EDD sequence is 4, 2, 3, 8, 5, 6, 1, 7
Flow Time Lateness Tardiness
Evan Schwartz has six jobs waiting to be processedthrough his machine. Processing time (in days) and duedate information for each job are as follows:Sequence the jobs by FCFS, SPT, SLACK, and DDATE.Calculate the mean flow time and mean tardiness of the sixjobs under each sequencing rule. Which rule would yourecommend?
Eight jobs have arrived in the following order:
Job
Processing Time
Due Date
1
7
23
2
3
9
3
5
8
4
2
11
5
6
16
6
9
18
7
14
40
8
4
31
Find and compare the performance measures for the following sequencing rules using the Excel Sequencing template. Round your answers to two decimal places.
Process in the order they have arrived
Flow Time
Lateness
Tardiness
Average
Chapter 17 Solutions
Operations and Supply Chain Management 9th edition
Ch. 17 - Scheduling Major League Baseball Umpires It used...Ch. 17 - Scheduling Major League Baseball Umpires It used...Ch. 17 - Solving Tough Scheduling Problems in Healthcare...Ch. 17 - Solving Tough Scheduling Problems in Healthcare...Ch. 17 - Analytics at Airbnb Airbnb is a global community...Ch. 17 - Analytics at Airbnb Airbnb is a global community...Ch. 17 - Analytics at Airbnb Airbnb is a global community...Ch. 17 - Analytics at Airbnb Airbnb is a global community...Ch. 17 - How do scheduling activities differ for projects,...Ch. 17 - Why is scheduling a job shop so difficult?
Ch. 17 - What three functions are typically performed by a...Ch. 17 - Prob. 4QCh. 17 - How can the success of a scheduling system be...Ch. 17 - Describe the process of loading and load leveling....Ch. 17 - What is the purpose of dispatch lists? How are...Ch. 17 - When should the following sequencing rules be...Ch. 17 - Give examples of sequencing rules you use to...Ch. 17 - What information is provided by the critical ratio...Ch. 17 - How are work packages, hot lists, and exception...Ch. 17 - What are Gantt charts, and why are they used so...Ch. 17 - Explain the concept behind input/output control....Ch. 17 - Explain the difference between infinite and finite...Ch. 17 - How does theory of constraints differ from...Ch. 17 - Explain the drum-buffer-rope concept.Ch. 17 - Discuss the similarities and differences between...Ch. 17 - What are some typical issues involved in employee...Ch. 17 - What quantitative techniques are available to help...Ch. 17 - At Valley Hospital, nurses beginning a new shift...Ch. 17 - Valley Hospital (from Problem 17.1) wants to focus...Ch. 17 - Prob. 3PCh. 17 - Sunshine House received a contract this year as a...Ch. 17 - Karina Nieto works for New Products Inc., and one...Ch. 17 - Decenture has four new IT hires available for...Ch. 17 - Blue Jeans Modeling Agency specializes in...Ch. 17 - Evan Schwartz has six jobs wailing to be processed...Ch. 17 - College students always have a lot of work to do,...Ch. 17 - Today is day 4 of the planning cycle. Sequence the...Ch. 17 - Alices Alterations has eight jobs to be completed...Ch. 17 - Jobs A. B, C, and D must be processed through the...Ch. 17 - Sequence the following jobs by (a) SPT, (b) DDATE,...Ch. 17 - Prob. 14PCh. 17 - Claims received by Healthwise Insurance Company...Ch. 17 - Jobs processed through Percys machine shop pass...Ch. 17 - Prob. 17PCh. 17 - Sassy U makes fashion jeans out of a variety of...Ch. 17 - Restore is a small repair shop that makes...Ch. 17 - Precision Painters, Inc., has five house painting...Ch. 17 - Tracy has six chapters on her desk that must be...Ch. 17 - Updike Upholstery cuts and sews fabric for custom...Ch. 17 - The following data have been compiled for an...Ch. 17 - The input/output report for Work Center 6 is as...Ch. 17 - Kim Johnson, R.N., the charge nurse of the...Ch. 17 - Rosemary Hanes needs help in scheduling volunteers...Ch. 17 - Schedule the wail staff at Vincents Restaurant...Ch. 17 - Mr. Baskins, manager of Tom and Jerrys Ice Cream...
Additional Business Textbook Solutions
Find more solutions based on key concepts
•• B.4. Consider the following linear programming problem:
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Create an Excel spreadsheet on your own that can make combination forecasts for Problem 18. Create a combinatio...
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
The best fits using exponential smoothing, trend analysis, and linear regression for the given data. Introducti...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
The schedule Dr. Barr set up worked well at the clinic where she was a resident. What are some of the reasons w...
Operations Management, Binder Ready Version: An Integrated Approach
What is precedent, and how does it affect common law?
Business in Action
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- There are six jobs as below. The processing time (in days) and due date for each job are below. Job lamolam A B C D E F (a) the average flow time Processing Time (days) (b) average tardiness 1 16 4 10 5 8 Due Date (days from present time) Please use SPT (shortest processing time) priority rule to calculate: 7 16 4 15 10 18 (c) average number of jobs at the work center, for each of these rules:arrow_forwardFive jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 6 10 B 5 17 C 2 13 D 3 9 E 4 15 Using the earliest due date (EDD) rule, the average tardiness of the five jobs is:arrow_forwardEva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived: Job VWX Y Z Processing Time (hrs) 7 1 9 3 5 Due (hrs from now) 5 1 4 2 3 If Eva uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average completion time?arrow_forward
- Three jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 2 8 B 6 6 C 5 13 Using the earliest due date (EDD) rule, the average tardiness of the five jobs is:arrow_forwardIn a few words, explain how to prevent a process getting starved in priority scheduling.arrow_forwardThe following table contains information regarding jobs that are to be scheduled through one machine: Job Processing Time (Days) Due date A 4 20 B 12 30 C 2 15 D 11 16 E 10 18 F 3 5 G 6 9 Qus 1: Find the FCFS Schedule? Qus 2: Find the SOT Schedule? Qus 3:Find the DDate Schedule? Qus 4: What are the mean flow time and average lateness for each of the schedule above? Qus 5: Which priority rule is appropriate for job scheduling? Justify your answer.arrow_forward
- Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. According to EDD, what is the optimal sequence? Job Processing Time (days) Due Date A 8 12 B 4 9 IC 3 6 7 E 5 20 a) E-A-B-D-C b) C-B-E-D-A c) A-B-C-D-E d) C-D-B-A-Earrow_forwardThe following table contains information concerning four jobs that are awaiting processing at awork center.JobJob Time(days)Due Date(days)A 14 20B 10 16C 7 15D 6 17a. Sequence the jobs using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. Assume the list is by orderof arrival.b. For each of the methods in part a, determine (1) the average job flow time, (2) the average tardiness, and (3) the average number of jobs at the work center.c. Is one method superior to the others? Explain.arrow_forwardAt the campus copy shop, six jobs have a rrived in the order shown (A, B, C, D, E, and F) at the beginning of the day (today, which is a workday). All of the jobs are due at varioustimes today. Your task is to evaluate four common sequencing rules. a) Sequence the jobs according to the following decision rules:FCFS, EDD, SPT, and LPT.b) For the FCFS sequence, compute the average completion (flow) time, average lateness, and average number of jobs in the system.c) For the EDD sequence, compute the average completion (flow) time, average lateness, and average number of jobs in the system.d) For the SPT sequence, compute the average completion (flow) time, average lateness, and average number of jobs in the system. e) For the LPT sequence, compute the average completion (flow)time, average lateness, and average number of jobs…arrow_forward
- Compare the differences between flow classification and flow scheduling?arrow_forward1.Explain the concepts of scheduling and sequencing 2.Describe staff scheduling and appointment system decisions 3.Describe how to solve two-resource sequencing problems.arrow_forwardThe owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Job processing time hrs due from now W 4 4 X 3 5 Y 2 2 Z 1 1 If he uses the earliest due date first priority rule to schedule these jobs, what will be the average job tardiness?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY