Question
Chapter 17, Problem 17P
Summary Introduction
To identify: The restaurant’s chef has to prepare 5 dishes with the first process of marinating and then cooking. Processing them is a two-step process. Preparing a sequencing order for the entire batch and identifying the total time to complete the whole process.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Abbott Manufacturing produces plastic cases for solar photovoltaic panels and has decided to combine orders from customers to increase work order size, and thereby, make one large production run per model type.
Plastic injection molding machines are used to make these parts, and it is time consuming to clean and re-setup the machines between production runs. Each molding machine and operator works one 10-hour shift with
a one-hour lunch break and one-half hour for operator breaks.
Consolidated
Work Orders
Model XVT-5 Case
Model UYT-3 Case
Model KLY-6 Case
Work Order
Quantity
9,600 panels
7,900
12,000
Setup
(Changeover)
Time per
Work Order
(minutes)
98
160
What is the total workload (demand) in hours for this work order mix? Round your answer to one decimal place.
The total workload is
hours.
How many machines will it take to do this work in one, two, or three days? Round your answers up to the nearest whole number.
To do this work in 1 day they need
machine(s).
machine(s).
To do this…
Abbott Manufacturing produces plastic cases for solar photovoltaic panels and has decided to combine orders from customers to increase work order
size, and thereby, make one large production run per model type. Plastic injection molding machines are used to make these parts, and it is time
consuming to clean and re-setup the machines between production runs. Each molding machine and operator works one 10-hour shift with a one-
hour lunch break and one-half hour for operator breaks.
Consolidated
Work Orders
Model XVT-5 Case
Model UYT-3 Case
Model KLY-6 Case
Work Order
Quantity
8,800 panels
8,700
12,400
Setup
(Changeover)
Time per
Work Order
(minutes)
86
63
135
Processing
Time per
Panel
(seconds)
2.50
2.22
4.11
What is the total workload (demand) in hours for this work order mix? Round your answer to one decimal place.
The total workload is
hours.
How many machines will it take to do this work in one, two, or three days? Round your answers up to the nearest whole number.
To do this work…
William Beebe owns a small shoe store. He has 10 pairs of shoes that requireresoling and polishing. He has a machine that can resole one pair of shoes at atime, and the time required for the operation varies with the type and condition of theshoe and the type of sole that is used. Shoes are polished on a machine dedi-cated tothis purpose as well, and polishing is always done after resoling. His assistant generally does the polishing while Mr. Beebe does the resoling. The resoling and polishingtimes (in minutes) are Shoes Resoling Time Polishing Time1 14 32 28 13 12 24 6 55 10 106 14 67 4 128 25 89 15 510 10 5In what order should the shoes be repaired in order to minimize the total makespanfor these 10 jobs?
Chapter 17 Solutions
Operations and Supply Chain Management 9th edition
Ch. 17 - Scheduling Major League Baseball Umpires It used...Ch. 17 - Scheduling Major League Baseball Umpires It used...Ch. 17 - Solving Tough Scheduling Problems in Healthcare...Ch. 17 - Solving Tough Scheduling Problems in Healthcare...Ch. 17 - Analytics at Airbnb Airbnb is a global community...Ch. 17 - Analytics at Airbnb Airbnb is a global community...Ch. 17 - Analytics at Airbnb Airbnb is a global community...Ch. 17 - Analytics at Airbnb Airbnb is a global community...Ch. 17 - How do scheduling activities differ for projects,...Ch. 17 - Why is scheduling a job shop so difficult?
Ch. 17 - What three functions are typically performed by a...Ch. 17 - Prob. 4QCh. 17 - How can the success of a scheduling system be...Ch. 17 - Describe the process of loading and load leveling....Ch. 17 - What is the purpose of dispatch lists? How are...Ch. 17 - When should the following sequencing rules be...Ch. 17 - Give examples of sequencing rules you use to...Ch. 17 - What information is provided by the critical ratio...Ch. 17 - How are work packages, hot lists, and exception...Ch. 17 - What are Gantt charts, and why are they used so...Ch. 17 - Explain the concept behind input/output control....Ch. 17 - Explain the difference between infinite and finite...Ch. 17 - How does theory of constraints differ from...Ch. 17 - Explain the drum-buffer-rope concept.Ch. 17 - Discuss the similarities and differences between...Ch. 17 - What are some typical issues involved in employee...Ch. 17 - What quantitative techniques are available to help...Ch. 17 - At Valley Hospital, nurses beginning a new shift...Ch. 17 - Valley Hospital (from Problem 17.1) wants to focus...Ch. 17 - Prob. 3PCh. 17 - Sunshine House received a contract this year as a...Ch. 17 - Karina Nieto works for New Products Inc., and one...Ch. 17 - Decenture has four new IT hires available for...Ch. 17 - Blue Jeans Modeling Agency specializes in...Ch. 17 - Evan Schwartz has six jobs wailing to be processed...Ch. 17 - College students always have a lot of work to do,...Ch. 17 - Today is day 4 of the planning cycle. Sequence the...Ch. 17 - Alices Alterations has eight jobs to be completed...Ch. 17 - Jobs A. B, C, and D must be processed through the...Ch. 17 - Sequence the following jobs by (a) SPT, (b) DDATE,...Ch. 17 - Prob. 14PCh. 17 - Claims received by Healthwise Insurance Company...Ch. 17 - Jobs processed through Percys machine shop pass...Ch. 17 - Prob. 17PCh. 17 - Sassy U makes fashion jeans out of a variety of...Ch. 17 - Restore is a small repair shop that makes...Ch. 17 - Precision Painters, Inc., has five house painting...Ch. 17 - Tracy has six chapters on her desk that must be...Ch. 17 - Updike Upholstery cuts and sews fabric for custom...Ch. 17 - The following data have been compiled for an...Ch. 17 - The input/output report for Work Center 6 is as...Ch. 17 - Kim Johnson, R.N., the charge nurse of the...Ch. 17 - Rosemary Hanes needs help in scheduling volunteers...Ch. 17 - Schedule the wail staff at Vincents Restaurant...Ch. 17 - Mr. Baskins, manager of Tom and Jerrys Ice Cream...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A Support Labor Staff lifts bricks from 30, 53-ft long trailers in their 8-hr shift using forklifts. The typical 53-ft trailer holds 26 pallets of bricks. The warehouse receives in the first half of the shift and ships in the second half of the shift. The work standard for forklift operations is listed below: Load/unload pallet from trailer 45 sec Move from dock to warehouse or warehouse to dock 120 sec Load/unload pallet from Truck 30 sec Move within warehouse 60 sec Calculate the number of forklifts needed to process all the pallets is most nearly: А. 7 В. 9 С. 10 D. 11arrow_forwardConsider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There exists unlimited demand unless stated otherwise. Time to Complete Task (seconds): Task 1: 30 Task 2: 25 Task 3: 15 Task 4: 20 Task 5: 15 Task 6: 20 Task 7: 50 Task 8: 15 Task 9: 20 Task 10: 25 Task 11: 15 Task 12: 20 The current conveyor-paced assembly-line configuration assigns the workers in the following way: • Worker 1: Tasks 1, 2, 3 • Worker 2: Tasks 4, 5, 6 • Worker 3: Tasks 7, 8, 9 • Worker 4: Tasks 10, 11, 12 What is the direct labor content (in seconds per unit)?arrow_forwardA process improvement team is working to improve the production output at the Johnson Manufacturing plant’sHeader Cell that manufactures a key component, headers, used in commercial air conditioners. A header is partof the circulatory system of a commercial air conditioner that moves coolant between various components suchas the evaporator coil and the condenser coil. Currently, the header production cell is scheduled separately fromthe main work in the plant. Often, individual headers are not sequenced to match the product they go into on thefinal assembly line in a timely fashion, and so the product can sit in queue waiting for a headerarrow_forward
- Pine Valley Furniture Pine Valley Furniture recently implemented a new internship program and has begun recruiting interns from nearby university campuses. As part of this program, interns have the opportunity to work alongside a systems analyst. This shadowing opportunity provides invaluable insights into the systems analysis and design process. Recently you were selected for a six-month internship at Pine Valley Furniture, and Jim Woo has been assigned as your supervisor. At an initial meeting with Jim Woo, he explains that Pine Valley Furniture is currently involved with two important systems development projects, the customer tracking system and WebStore. The purpose of the customer tracking system is to enable the PVF marketing group to track customer purchase activity and sales trends better. The WebStore project will help move the company into the twenty-first century by facilitating online furniture purchases, with an initial focus on corporate furniture buying. During your…arrow_forwardConsider a law firm with 15 lawyers and 3 paralegals. The firm is struggling to keep up with the high demand for its services, particularly during the busy litigation seasons. It has been observed that the lawyers spend a significant amount of their time on administrative tasks that could potentially be handled by paralegals. After a careful study of the work distribution within the firm, it was determined that 35% of the activities carried out by the lawyers are administrative in nature. Given that each lawyer works 50 hours a week, please determine: (a) How many additional paralegals should the firm hire to handle the administrative tasks currently performed by the lawyers? (b) If the lawyers' time spent on administrative tasks is redirected to billable legal work, by what percentage could the firm potentially increase its billable hours?arrow_forwardGalaxy Candy Company manufactures two popular candy bars, the Eclipse bar and the Nova bar. Both candy bars go through a mixing operation where the various ingredients are combined, and the Coating Department where the bars from the Mixing Department are coated with chocolate. The Eclipse bar is coated with both white and dark chocolate to produce a swirled effect. A material shortage of an ingredient in the Nova bar limitsproduction to 300 batches per hour. Production and sales data are presented in the following table. Mixing CoatingAvailable capacity in hours 525 500Use of capacity in hours per batch of product: Eclipse 1.5 2.0 Nova…arrow_forward
- Chris has three different workstations: one for drip coffee, one for espresso drinks, and one to prepare food. During the morning rush, Chris has 5 people working: one person at the drip coffee station, two at the espresso station, and two at the food prep station. These employees are not cross-trained, and thus must stay at their station. On average, it takes the person at the drip coffee station 1 minute to make the coffee. On average, it takes one person working at the espresso station 3 minutes to make one espresso drink. On average, it takes one person working at the food station 4.5 minutes to prepare the food for one customer. The customer mix is as follows. 10% order just a drip coffee, 30% order a drip coffee and food, 35% order just an espresso drink, and 25% order an espresso drink plus food. A total of 40 customers/ hour frequent Chris'. What is the implied utilization at the espresso station? Provide your answer in decimal form, and round to 4 decimal places. (So, if your…arrow_forwardABC Solutions is a traditional company in a textile industry with a combined workforce of 150 staff. Due to increased levels of competition, this company is now increasingly finding it difficult to compete – especially as the larger companies seem to be a little more innovative, agile and responsive to client requirements. Management have noticed that staff, especially the highly skilled ones, are now leaving the company to seek work elsewhere (in these larger companies). This has meant appointing new staff and undertaking a considerable amount of re-training to replace those that have left the company. Apart from impacting on core business operations, ABC Solutions has started witnessing a drop in its profit margin. Given this position, senior management at ABC Solutions have decided to implement a performance measurement tool (PMT) that would allow them to align the strategic, management and operational requirements of the business. They are therefore considering the adoption of the…arrow_forwardDon't used Chat gptarrow_forward
- Help ! Choice Bank receives credit card applications that need to be reviewed for a decision. There are two types of applications; preapproved, and non-preapproved. Preapproved applications only need a quick review and therefore take 6 minutes to process. Applications that are not preapproved need a secondary credit check and take 15 minutes to process. The bank receives 10 preapproved applications every hour and 6 applications that are not preapproved every hour. What is the utilization of the process? Group of answer choices 50 % 62.5 % 68.75 % 75 % 100 %arrow_forwardThe Safe Zone Restaurant, a 24-hour restaurant, faces changing requirements from hour to hour. More workers are needed for peak hours, and fewer are needed in between. The following table shows the worker requirement for the first 12 hours in the restaurant: Table 8. Staff Requirement at the Safe Zone Restaurant Time Period 10 11 12 1 PM|2 PM|3 PM|4 PM|5 PM|6 PM 7 PM|8 PM|9 PM АM | АM | РМ Requirement 7 Assigned On Duty Overstaffed 9 10 10 8 6 6. 8 8 12 12 8 a) You are required to apply the first-hour principle to staff each hour with the required number of cafeteria staff, showing how many staff are on duty each given hour, the number of staff you have assigned to work each hour and any overstaffing for each hour. i. Schedule the staff to work in 8-hour shifts. ii. Schedule the staff to work in 4-hour shifts. b) Indicate with at least one reason, which schedule would be more optimal from an Operations Scheduling perspective?arrow_forwardA small-size cargo company in Dubai has been operating since the year 2000. The total workforce comprises ten employees, out of which five are in sales, three are in operations, one is handling legal and accounts matters, and one manager is also the owner of the company. Total annual turnover is enough to run the company smoothly. Recently another director has joined who brought large investment to the company. The Board of directors has decided to expand the business in other cities and establish offices overseas in potential locations. This expansion policy will directly be linked to the new manpower needs. Therefore, the board has decided to open an HR department with one HR manager and three staff to look after HR operations. The new HR manager has noticed that the company has a very convenient way of recording the data, where all transactions are recorded on excel documents. “this may not work in the new setup with many branches around the world”, he mentioned in the BOD meeting.…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,