EBK PRINCIPLES OF OPERATIONS MANAGEMENT
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175859
Author: Munson
Publisher: VST
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 14, Problem 27P

Grace Greenberg, production planner for Science and Technology Labs, in New Jersey, has the master production plan shown below:

Chapter 14, Problem 27P, Grace Greenberg, production planner for Science and Technology Labs, in New Jersey, has the master

Lead time = 1 period; setup cost = $200; holding cost = $10 per week; stockout cost = $10 per week. Develop an ordering plan and costs for Grace, using these techniques:

a) Lot-for-lot.

b) EOQ.

c) POQ.

d) Which plan has the lowest cost?

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The ordering plan and cost for Lot for lot.

Introduction:

Lot for Lot:

The lot for lot method of requirements plan is the process where the planned order release will be equal to the net requirement of the period.

Net requirements plan:

The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.

Answer to Problem 27P

The cost for Lot for lot is $1,200.

Explanation of Solution

Given information:

Period (weeks)
Item A 1 2 3 4 5 6 7 8 9 10 11 12 Total
Gross requirements 35 40 10 25 10 45 165

Holding cost = $10 / week

Setup cost = $200

Lead time = 1 period

Stockout cost = $10 / week

Lot for lot:

Net requirements plan:

Period (weeks)
Item A 1 2 3 4 5 6 7 8 9 10 11 12 Total
Gross requirements 35 40 10 25 10 45 165
Scheduled receipt
On hand (0) 0 0 0 0 0 0
Ending inventory 0 0 0 0 0 0 0
Net requirement 35 40 10 25 10 45
Planned order receipt 35 40 10 25 10 45
Planned order release 35 40 10 25 10 45

Week 2:

The gross requirement is 35 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 35. The lead time is 1 week. Therefore, the planned order release will be 35 in week 1 which will be the planned order receipt in week 2.

Week 4:

The gross requirement is 40 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 40. The lead time is 1 week. Therefore, the planned order release will be 40 in week 3 which will be the planned order receipt in week 4.

Week 6:

The gross requirement is 10 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 10. The lead time is 1 week. Therefore, the planned order release will be 10 in week 5 which will be the planned order receipt in week 6.

Week 9:

The gross requirement is 25 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 25. The lead time is 1 week. Therefore, the planned order release will be 25 in week 8 which will be the planned order receipt in week 9. There is no ending inventory.

Week 10:

The gross requirement is 10 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 10. The lead time is 1 week. Therefore, the planned order release will be 10 in week 9 which will be the planned order receipt in week 10.

Week 12:

The gross requirement is 45 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 45. The lead time is 1 week. Therefore, the planned order release will be 45 in week 11 which will be the planned order receipt in week 12. There is no ending inventory.

Number of planned orders = 6

Inventory holding units= 0

Formula to calculate total cost of the plan:

Total cost=(Number of planned orders×Setup cost)+(Inventory holding period×Holding cost)

Calculation of total cost:

The total cost is calculated by adding the product of number of planned order and setup cost with the product of inventory holding period and holding cost.

Total cost=(6×$200)+(0×$10)=$1,200+$0=$1,200

Hence, the cost for Lot for lot is $1,200.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The ordering plan and cost for EOQ.

Introduction:

Economic order quantity (EOQ):

The economic order quantity is the number of units a firm must add to their stock while making each order. The notion of EOQ is to reduce the total cost of inventory of the firm.

Net requirements plan:

The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.

Answer to Problem 27P

The cost for EOQ is $2,370.

Explanation of Solution

Given information:

Period (weeks)
Item A 1 2 3 4 5 6 7 8 9 10 11 12 Total
Gross requirements 35 40 10 25 10 45 165

Holding cost = $10 / week

Setup cost = $200

Lead time = 1 period

Stockout cost = $10 / week

Formula to calculate EOQ:

EOQ=2×Total gross requirements×Setup costHolding cost×Number of periods

Calculation of EOQ:

EOQ=2×165×20010×12=66000120=550=23.45 units

The EOQ can be rounded off to 23 units.

Net requirements plan:

Period (weeks)
Item A 1 2 3 4 5 6 7 8 9 10 11 12 Total
Gross requirements 35 40 10 25 10 45 165
Scheduled receipt
On hand (0) 0 11 11 17 17 7 7 7 5 18 18
Ending inventory 11 11 17 17 7 7 7 5 18 18 19 137
Net requirement 35 29 0 18 5 27
Planned order receipt 46 46 0 23 23 46
Planned order release 46 46 23 23 46

Week 2:

The gross requirement is 35 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 35. The lead time is 1 week. Therefore, the planned order release will be 46 (1 Lot = 23) in week 1 which will be the planned order receipt in week 2. The ending inventory is 11 which will be available at week 3.

Week 3:

The on hand inventory is 11. Since there is no requirement, the ending inventory at week 3 is 11 which will be available at week 4.

Week 4:

The gross requirement is 40 (1 assembly). The on hand inventory is 11. Hence, the net requirement is 29. The lead time is 1 week. Therefore, the planned order release will be 46 (1 Lot = 23) in week 3 which will be the planned order receipt in week 4. The ending inventory is 17 which will be available at week 5.

Week 5:

The on hand inventory is 17. Since there is no requirement, the ending inventory at week 5 is 17 which will be available at week 6.

Week 6:

The gross requirement is 10 (1 assembly). The on hand inventory is 17. Hence, the net requirement is 0. Therefore there will be no planned order assembly. The ending inventory is 7 which will be available at week 7.

Week 7:

The on hand inventory is 7. Since there is no requirement, the ending inventory at week 7 is 7 which will be available at week 8.

Week 8:

The on hand inventory is 7. Since there is no requirement, the ending inventory at week 8 is 7 which will be available at week 9.

Week 9:

The gross requirement is 25 (1 assembly). The on hand inventory is 7. Hence, the net requirement is 18. The lead time is 1 week. Therefore, the planned order release will be 23 (1 Lot = 23) in week 8 which will be the planned order receipt in week 9. The ending inventory is 5 which will be available at week 10.

Week 10:

The gross requirement is 10 (1 assembly). The on hand inventory is 5. Hence, the net requirement is 5. The lead time is 1 week. Therefore, the planned order release will be 23 (1 Lot = 23) in week 9 which will be the planned order receipt in week 10. The ending inventory is 18 which will be available at week 11.

Week 11:

The on hand inventory is 18. Since there is no requirement, the ending inventory at week 11 is 18 which will be available at week 12.

Week 12:

The gross requirement is 45 (1 assembly). The on hand inventory is 18. Hence, the net requirement is 27. The lead time is 1 week. Therefore, the planned order release will be 46 (1 Lot = 23) in week 11 which will be the planned order receipt in week 12. The ending inventory is 19 which will be available in the next week.

Number of planned order releases = 5

Total Ending inventory = 137

Calculation of total setup cost:

Total setup cost=Number of planned order releases×Setup cost=5×$200=$1,000

Calculation of total holding cost:

Total holding cost=Total ending inventory×Holding cost=137×$10=$1,370

Calculation of total cost:

The total cost is calculated by summing the total setup cost and total holding cost.

Total cost=$1,000+$1370=$2,370

Hence, the total cost for EOQ is $2,370

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The ordering plan and cost for POQ.

Introduction:

Periodic order quantity (POQ):

The POQ is the standard quantity of units that will be ordered over a fixed period of time. This method is followed when the usage of raw materials is consistent and is predictable.

Net requirements plan:

The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.

Answer to Problem 27P

The cost for POQ is $1,100.

Explanation of Solution

Given information:

Period (weeks)
Item A 1 2 3 4 5 6 7 8 9 10 11 12 Total
Gross requirements 35 40 10 25 10 45 165

Holding cost = $10 / week

Setup cost = $200

Lead time = 1 period

Stockout cost = $10 / week

Net requirements plan:

The planned ordered release in the POQ plan is planned in a way such that the demand for next two periods is satisfied.

Net requirements plan:

Period (weeks)
Item A 1 2 3 4 5 6 7 8 9 10 11 12 Total
Gross requirements 35 40 10 25 10 45 165
Scheduled receipt
On hand (0) 0 0 0 0 0 0 0 0 10 0 0
Ending inventory 0 0 0 0 0 0 0 10 0 0 0 10
Net requirement 35 40 10 25 45
Planned order receipt 35 40 10 35 45
Planned order release 35 40 10 35 45

Week 2:

The gross requirement is 35 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 35. The lead time is 1 week. Therefore, the planned order release will be 35 in week 1 which will be the planned order receipt in week 2. There is no ending inventory.

Week 4:

The gross requirement is 40 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 40. The lead time is 1 week. Therefore, the planned order release will be 40 in week 3 which will be the planned order receipt in week 4. There is no ending inventory.

Week 6:

The gross requirement is 10 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 10. Therefore, the planned order release will be 10 in week 5 which will be the planned order receipt in week 6. There is no ending inventory.

Week 9:

The gross requirement is 25 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 25. The lead time is 1 week. Therefore, the planned order release will be 35 in week 8 which will be the planned order receipt in week 9. The ending inventory is 10 which will be available at week 10.

Week 10:

The gross requirement is 10 (1 assembly). The on hand inventory is 10. Hence, the net requirement is 0. Therefore there will be no planned order inventory.

Week 12:

The gross requirement is 45 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 45. The lead time is 1 week. Therefore, the planned order release will be 45 in week 11 which will be the planned order receipt in week 12. There is no ending inventory.

Number of planned orders = 5

Inventory holding units= 10

Formula to calculate total cost of the plan:

Total cost=(Number of planned orders×Setup cost)+(Inventory holding period×Holding cost)

Calculation of total cost:

The total cost is calculated by adding the product of number of planned order and setup cost with the product of inventory holding period and holding cost.

Total cost=(5×$200)+(10×$10)=$1,000+$100=$1,100

Hence, the cost for POQ is $1,100.

d)

Expert Solution
Check Mark
Summary Introduction

To determine: The plan which has the lowest cost.

Answer to Problem 27P

The plan which has the lowest cost is POQ.

Explanation of Solution

The total cost for Lot for lot is $1,200. The total cost for EOQ is $2,370. The total cost for POQ is $1,100. The total cost is less for POQ when compared with EOQ and Lot for lot. ($1,100 < $2,370, $1,200)

Hence, the plan which has the lowest cost is POQ.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
M. de Koster, of Rene Enterprises, has the master production plan shown here:                                    Lead time = I period; setup cost= $200; holding cost = $10 perweek; stockout cost = $10 per week. Your job is to develop an ordering plan and costs for:a) Lot-for-lot. b) EOQ.c) POQ. d) Which plan has the lowest cost?
opm please help ....
please answer within 30 minutes

Chapter 14 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 28PCh. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1CSCh. 14 - Prob. 2CSCh. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - Prob. 2.1VCCh. 14 - Prob. 2.2VCCh. 14 - Prob. 2.3VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY