
Concept explainers
a)
To construct: A product structure.
Introduction:
Product structure:
The product structure is a visual representation of the components needed for a product assembly and the sequence at which they must be developed. It will clearly depict the parents and children components at each level.
a)

Answer to Problem 13P
Product structure:
Explanation of Solution
Given information:
- 1000 20” fans due in week 7.
- Each fan is made of a housing assembly, two grills, fan assembly and an electrical unit.
- Housing assembly is made of frame, two supports, and a handle.
- Fan assembly is made up of a hub and five blades.
- Electrical unit consists of a motor, switch and a knob.
Component | Lead time | On-hand inventory | Lot size |
|
20" Fan | 1 | 100 | ||
Housing | 1 | 100 | ||
Frame | 2 | |||
Supports (2) | 1 | 50 | 100 | |
Handle | 1 | 400 | 500 | |
Grills (2) | 2 | 200 | 500 | |
Fan assembly | 3 | 150 | ||
Hub | 1 | |||
Blades (5) | 2 | 100 | ||
Electrical unit | 1 | |||
Motor | 1 | |||
Switch | 1 | 20 | 12 | |
Knob | 1 | 25 | 200 in week 2 |
Product structure:
The product is a 20” fan. It is made of four components. Each fan is made of a housing assembly, two grills, fan assembly and an electrical unit. Housing assembly is made of frame, two supports, and a handle. Fan assembly is made up of a hub and five blades. Electrical unit consists of a motor, switch and a knob.
b)
To construct: A time-phased product structure.
Introduction:
Time-phased product structure:
The time-phased product structure will represent the product visually with the details of when each component must begin production. It should be done to ensure that all the components are on time.
b)

Answer to Problem 13P
Time-phased product structure:
Explanation of Solution
Given information:
- 1000 20” fans due in week 7.
- Each fan is made of a housing assembly, two grills, fan assembly and an electrical unit.
- Housing assembly is made of frame, two supports, and a handle.
- Fan assembly is made up of a hub and five blades.
- Electrical unit consists of a motor, switch and a knob.
Component | Lead time | On-hand inventory | Lot size | Scheduled receipt |
20" Fan | 1 | 100 | ||
Housing | 1 | 100 | ||
Frame | 2 | |||
Supports (2) | 1 | 50 | 100 | |
Handle | 1 | 400 | 500 | |
Grills (2) | 2 | 200 | 500 | |
Fan assembly | 3 | 150 | ||
Hub | 1 | |||
Blades (5) | 2 | 100 | ||
Electrical unit | 1 | |||
Motor | 1 | |||
Switch | 1 | 20 | 12 | |
Knob | 1 | 25 | 200 in week 2 |
Time-phased product structure:
The end product is the fan which must be ready at week 7. All the other components must be completed on week 6. The components at the lower level must be completed first before proceeding to the higher levels. Each component at each level is begun depending on the lead time of the product.
The products are started in advance so that they are developed and ready on time so that the dependent parent will be ready to develop its product. The process is repeated until all the subassemblies are ready to make the final product.
c)
To develop: A net requirements plan.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
c)

Explanation of Solution
Given information:
- 1000 20” fans due in week 7.
- Each fan is made of a housing assembly, two grills, fan assembly and an electrical unit.
- Housing assembly is made of frame, two supports, and a handle.
- Fan assembly is made up of a hub and five blades.
- Electrical unit consists of a motor, switch and a knob.
Component | Lead time | On-hand inventory | Lot size | Scheduled receipt |
20" Fan | 1 | 100 | ||
Housing | 1 | 100 | ||
Frame | 2 | |||
Supports (2) | 1 | 50 | 100 | |
Handle | 1 | 400 | 500 | |
Grills (2) | 2 | 200 | 500 | |
Fan assembly | 3 | 150 | ||
Hub | 1 | |||
Blades (5) | 2 | 100 | ||
Electrical unit | 1 | |||
Motor | 1 | |||
Switch | 1 | 20 | 12 | |
Knob | 1 | 25 | 200 in week 2 |
Net requirements plan:
20’’ Fan:
Week | ||||||||||||
20" Fan | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 1,000 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | |||||||||||
Net requirement | 900 | |||||||||||
Planned order receipt | 900 | |||||||||||
Planned order release | 900 |
Week 7:
The gross requirement is 1,000 (1 assembly). The on hand inventory is 100. Hence, the net requirement is 900. The lead time is 1 week. Therefore, the planned order release will be 900 in week 6 which will be the planned order receipt in week 7.
Housing:
Week | ||||||||||||
Housing | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 900 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | |||||||||||
Net requirement | 800 | |||||||||||
Planned order receipt | 800 | |||||||||||
Planned order release | 800 |
Week 6:
The gross requirement is 900 (1 assembly) derived from the planned order release of 20” fan. The on hand inventory is 100. Hence, the net requirement is 800. The lead time is 1 week. Therefore, the planned order release will be 800 in week 5 which will be the planned order receipt in week 6.
Grills:
Week | ||||||||||||
Grills | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 1,800 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (200) | 200 | 400 | ||||||||||
Net requirement | 1,600 | |||||||||||
Planned order receipt | 2,000 | |||||||||||
Planned order release | 2,000 |
Week 6:
The gross requirement is 1,800 (2 assembly) derived from the planned order release of 20” fan. The on hand inventory is 200. Hence, the net requirement is 1,600. The lead time is 2 weeks. Therefore, the planned order release will be 2,000 (Lot Size = 500) in week 4 which will be the planned order receipt in week 6. The excess inventory will be available at week 7.
Fan assembly:
Week | ||||||||||||
Fan assembly | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 900 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (150) | 150 | |||||||||||
Net requirement | 750 | |||||||||||
Planned order receipt | 750 | |||||||||||
Planned order release | 750 |
Week 6:
The gross requirement is 900 (1 assembly) derived from the planned order release of 20” fan. The on hand inventory is 150. Hence, the net requirement is 750. The lead time is 2 weeks. Therefore, the planned order release will be 750 in week 4 which will be the planned order receipt in week 6.
Electrical unit:
Electrical Unit | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 900 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | |||||||||||
Net requirement | 900 | |||||||||||
Planned order receipt | 900 | |||||||||||
Planned order release | 900 |
Week 6:
The gross requirement is 900 (1 assembly) derived from the planned order release of 20” fan. The on hand inventory is 0. Hence, the net requirement is 900. The lead time is 1 week. Therefore, the planned order release will be 900 in week 5 which will be the planned order receipt in week 6.
Frame:
Frame | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 800 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | |||||||||||
Net requirement | 800 | |||||||||||
Planned order receipt | 800 | |||||||||||
Planned order release | 800 |
Week 5:
The gross requirement is 800 (1 assembly) derived from the planned order release of Housing. The on hand inventory is 0. Hence, the net requirement is 800. The lead time is 2 weeks. Therefore, the planned order release will be 800 in week 3 which will be the planned order receipt in week 5.
Supports:
Week | ||||||||||||
Supports | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 1,600 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (50) | 50 | |||||||||||
Net requirement | 1,550 | |||||||||||
Planned order receipt | 1,600 | |||||||||||
Planned order release | 1,600 |
Week 5:
The gross requirement is 1,600 (2 assembly) derived from the planned order release of Housing. The on hand inventory is 50. Hence, the net requirement is 1,550. The lead time is 1 week. Therefore, the planned order release will be 1,600 (Lot size = 100) in week 4 which will be the planned order receipt in week 5. The excess inventory is available at week 6.
Handle:
Week | ||||||||||||
Handle | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 800 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (400) | 400 | 100 | ||||||||||
Net requirement | 400 | |||||||||||
Planned order receipt | 500 | |||||||||||
Planned order release | 500 |
Week 5:
The gross requirement is 800 (1 assembly) derived from the planned order release of Housing. The on hand inventory is 400. Hence, the net requirement is 400. The lead time is 1 week. Therefore, the planned order release will be 500 (Lot size = 500) in week 4 which will be the planned order receipt in week 5. The excess inventory is available at week 6.
Hub:
Week | ||||||||||||
Hub | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 750 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | |||||||||||
Net requirement | 750 | |||||||||||
Planned order receipt | 750 | |||||||||||
Planned order release | 750 |
Week 3:
The gross requirement is 750 (1 assembly) derived from the planned order release of fan assembly. The on hand inventory is 0. Hence, the net requirement is 750. The lead time is 1 week. Therefore, the planned order release will be 750 in week 2 which will be the planned order receipt in week 3.
Blades:
Week | ||||||||||||
Blades | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 3,750 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | 50 | ||||||||||
Net requirement | 3,750 | |||||||||||
Planned order receipt | 3,800 | |||||||||||
Planned order release | 3,800 |
Week 3:
The gross requirement is 3,750 (5 assembly) derived from the planned order release of fan assembly. The on hand inventory is 0. Hence, the net requirement is 3,750. The lead time is 2 weeks. Therefore, the planned order release will be 3,800 (Lot size = 100) in week 1 which will be the planned order receipt in week 3. The excess inventory will be available at week 4.
Motor:
Week | ||||||||||||
Motor | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 900 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | |||||||||||
Net requirement | 900 | |||||||||||
Planned order receipt | 900 | |||||||||||
Planned order release | 900 |
Week 5:
The gross requirement is 900 (1 assembly) derived from the planned order release of Electrical unit. The on hand inventory is 0. Hence, the net requirement is 900. The lead time is 1 week. Therefore, the planned order release will be 900 in week 4 which will be the planned order receipt in week 5.
Switch:
Week | ||||||||||||
Switch | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 900 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (20) | 20 | 8 | ||||||||||
Net requirement | 880 | |||||||||||
Planned order receipt | 888 | |||||||||||
Planned order release | 888 |
Week 5:
The gross requirement is 900 (1 assembly) derived from the planned order release of Electrical unit. The on hand inventory is 20. Hence, the net requirement is 880. The lead time is 1 week. Therefore, the planned order release will be 888 (Lot Size = 12) in week 4 which will be the planned order receipt in week 5. The excess inventory will be available at week 6.
Knob:
Week | ||||||||||||
Knob | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 900 | |||||||||||
Scheduled receipt | 200 | |||||||||||
On hand (0) | 200 | 200 | 200 | |||||||||
Net requirement | 700 | |||||||||||
Planned order receipt | 700 | |||||||||||
Planned order release | 700 |
Week 2:
There is a scheduled receipt of 200 which can be used as inventory.
Week 5:
The gross requirement is 900 (1 assembly) derived from the planned order release of Electrical unit. The on hand inventory is 0. But, there is a scheduled receipt of 200. Hence, the net requirement is 7000. The lead time is 1 week. Therefore, the planned order release will be 700 in week 4 which will be the planned order receipt in week 5.
Want to see more full solutions like this?
Chapter 14 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- Following their early success and growth, Listo hired a number of new managers and employees. In response to the expansion of staff, Listo reorganized by adding layers of supervisors and managers between executive management and line staff; however, growth occurred so rapidly that proper training was not provided to the new employees. Management was less concerned with the employees’ opinions and was more focused on production and profit. Instead of enlisting employees’ opinions, more directive orders were given. The change and increased complexity associated with adding new layers to the hierarchy resulted in the organization’s goals and objectives becoming unclear. Employees began to complain about the new bureaucratic processes and the slow pace of decision-making. While the organization has been growing in size, productivity has slowed and quality has decreased. The turnover rate is higher than it has ever been, and the number of sick days that people take has doubled over the past…arrow_forwardFollowing their early success and growth, Listo hired a number of new managers and employees. In response to the expansion of staff, Listo reorganized by adding layers of supervisors and managers between executive management and line staff; however, growth occurred so rapidly that proper training was not provided to the new employees. Management was less concerned with the employees’ opinions and was more focused on production and profit. Instead of enlisting employees’ opinions, more directive orders were given. The change and increased complexity associated with adding new layers to the hierarchy resulted in the organization’s goals and objectives becoming unclear. Employees began to complain about the new bureaucratic processes and the slow pace of decision-making. While the organization has been growing in size, productivity has slowed and quality has decreased. The turnover rate is higher than it has ever been, and the number of sick days that people take has doubled over the past…arrow_forwardDiscuss in detail any five types of authority. give citations and referencearrow_forward
- Can you guys help me with this? Thank you! Business Environment: Provide insights into the guidelines for conducting business in the chosen country and working there as an expatriate. This information is vital for understanding the practicalities of engagement in that particular environment. The country in here is India Put the answer as bullet points, provide sources that have relevant information for the answer on economic factorsarrow_forwardCan you guys help me with this? Thank you! Intriguing Facts: Incorporate engaging facts about the country that enhance its value and uniqueness within the global supply chain landscape. These can include cultural anecdotes, technological innovations, or historical achievements. The country in here is India Put the answer as bullet points, provide sources that have relevant information for the answer on economic factorsarrow_forwardCan you guys help me with this? Thank you! Economic Factors: Evaluate the country's economic performance by analyzing key indicators such as GDP (Gross Domestic Product), GDP per capita, exports, and imports. These metrics provide insight into the country's economic prowess and its position in global trade. The country in here is India Put the answer as bullet points, provide sources that have relevant information for the answer on economic factorsarrow_forward
- provide scholarly reseach and define legal and complince risk and reputational risk in banking. Additionally 1. What more can be done about it 2. the department where the risk is exposed to 3. what strategy can be used 4. responsible personarrow_forwardRead the case in the link below and Develop a risk management programme appropriate for this case using the attached template. https://finopsinfo.com/investors/citis-900m-blunder-casts-light-on-poor-loan-ops/arrow_forwardDo the inherent differences between private and public sector objectives—profit versus publicgood—render private sector category management practices unsuitable for public sectorpurchasing, where open tendering is the norm?You have now undergone the Category Management classes and your superiors have requestedfor your input on how to integrate some of the learnings into the public sector policy. Discuss and elaborate what are the activities and governance you would introduce in yourrecommendations without violating the principle of transparency and accountability withinyour organisation. This is based on Singapore context. Pls provide a draft with explanation, examples and useful links for learning purposes. Citations will be good too. This is a module in SUSS called category management and supplier evaluationarrow_forward
- provide scholarly answers for what risk was associated with the Citibank bank loosing 50 million in August 2020arrow_forwardConclusion: The report recommendations and broad conclusion to the essay. TOTAL 5 100arrow_forwardAs part of your new role, as a strategy consultant and member of the steering committee, discuss what logistics and transportation strategies you will execute to achieve operational efficiencies and facilitate economic growth in SA. The committee would like to have a implementable strategic transport and logistics plan to realise the roadmap vision based on the subsection numbering given below! QUESTION ONE Introduction: Must include an overview and history of South Africa's Road, rail and freight transport network. Marks 5arrow_forward
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing

