EBK PRINCIPLES OF OPERATIONS MANAGEMENT
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175859
Author: Munson
Publisher: VST
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 14, Problem 12P

a)

Summary Introduction

To develop: A net requirements plan for items.

Introduction:

Net requirements plan:

The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Product structure:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 14, Problem 12P , additional homework tip  1

Period 8 9 10 11 12
Gross requirements: A 100 50 150
Gross requirements: H 100 50

Inventory and lead time:

Item A B C D E F G H J K
Lead time 1 2 2 1 2 2 1 1 2 2
On hand 0 100 50 50 75 75 75 0 100 100
  • 1 assembly for each item

Item A:

Week
Item A 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 100 50 150
Scheduled  receipt
On hand (0) 0 0 0
Net requirement 100 50 150
Planned order receipt 100 50 150
Planned order release 100 50 150

Week 8:

The gross requirement is 100 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 8.

Week 10:

The gross requirement is 50 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 9 which will be the planned order receipt in week 10.

Week 12:

The gross requirement is 150 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 11 which will be the planned order receipt in week 12.

Item H:

Week
Item H 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 100 50
Scheduled  receipt
On hand (0) 0 0
Net requirement 100 50
Planned order receipt 100 50
Planned order release 100 50

Week 9:

The gross requirement is 100 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 1000. The lead time is 1 week. Therefore, the planned order release will be 100 in week 8 which will be the planned order receipt in week 10.

Week 11:

The gross requirement is 50 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 9 which will be the planned order receipt in week 11.

Item B:

Week
Item B 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 100 50 150
Scheduled  receipt
On hand (100) 100 0 0
Net requirement 0 50 150
Planned order receipt 50 150
Planned order release 50 150

Week 7:

The gross requirement is 100 (1 assembly) derived from planned order release of A. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.

Week 9:

The gross requirement is 50 (1 assembly) derived from the planned order release of A. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 7 which will be the planned order receipt in week 9.

Week 11:

The gross requirement is 150 (1 assembly) derived from planned order release of A. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 9 which will be the planned order receipt in week 11.

Item C:

Week
Item C 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 100 100 50 50 150
Scheduled  receipt
On hand (50) 50 0 0 0 0
Net requirement 50 100 50 50 150
Planned order receipt 50 100 50 50 150
Planned order release 50 100 50 50 150

Week 7:

The gross requirement is 100 (1 assembly) derived from planned order release of A. The on hand inventory is 50. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 5 which will be the planned order receipt in week 7.

Week 8:

The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 8.

Week 9:

The gross requirement is 50 (1 assembly) derived from the planned order release of A. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 7 which will be the planned order receipt in week 9.

Week 10:

The gross requirement is 50 (1 assembly) derived from planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.

Week 11:

The gross requirement is 150 (1 assembly) derived from planned order release of A. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 9 which will be the planned order receipt in week 11.

Item J:

Week
Item J 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 100 50
Scheduled  receipt
On hand (100) 100 0
Net requirement 0 50
Planned order receipt 0 50
Planned order release 50

Week 8:

The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.

Week 10:

The gross requirement is 50 (1 assembly) derived from the planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.

Item K:

Week
Item K 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 100 50
Scheduled  receipt
On hand (100) 100 0
Net requirement 0 50
Planned order receipt 50
Planned order release 50

Week 8:

The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.

Week 10:

The gross requirement is 50 (1 assembly) derived from the planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.

Item D:

Week
Item D 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 50 150
Scheduled  receipt
On hand (50) 50 0
Net requirement 150
Planned order receipt 150
Planned order release 150

Week 7:

The gross requirement is 50 (1 assembly) derived from planned order release of B. The on hand inventory is 500. Hence, the net requirement is 0. Therefore, there will be no planned order release.

Week 9:

The gross requirement is 150 (1 assembly) derived from the planned order release of B. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 8 which will be the planned order receipt in week 9.

Item E:

Week
Item E 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 50 100 150
Scheduled  receipt
On hand (75) 75 25 0
Net requirement 0 75 150
Planned order receipt 75 150
Planned order release 75 150

Week 7:

The gross requirement is 50 (1 assembly) derived from planned order release of B. The on hand inventory is 75. Hence, the net requirement is 0. Therefore, there will be no planned order release.

Week 8:

The gross requirement is 100 (1 assembly) derived from the planned order release of J and K. The on hand inventory is 25. Hence, the net requirement is 75. The lead time is 2 weeks. Therefore, the planned order release will be 75 in week 6 which will be the planned order receipt in week 8.

Week 9:

The gross requirement is 150 (1 assembly) derived from planned order release of B. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 7 which will be the planned order receipt in week 9.

Item F:

Week
Item F 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 50 100 50 100 150
Scheduled  receipt
On hand (75) 75 25 0 0 0
Net requirement 0 75 50 100 150
Planned order receipt 75 50 100 150
Planned order release 75 50 100 150

Week 5:

The gross requirement is 50 (1 assembly) derived from planned order release of C. The on hand inventory is 75. Hence, the net requirement is 0. Therefore, there will be no planned order release.

Week 6:

The gross requirement is 100 (1 assembly) derived from planned order release of C. The on hand inventory is 25. Hence, the net requirement is 75. The lead time is 2 weeks. Therefore, the planned order release will be 75 in week 4 which will be the planned order receipt in week 6.

Week 7:

The gross requirement is 50 (1 assembly) derived from the planned order release of C. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 5 which will be the planned order receipt in week 7.

Week 8:

The gross requirement is 100 (1 assembly) derived from planned order release of C and J. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 8.

Week 9:

The gross requirement is 150 (1 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 7 which will be the planned order receipt in week 9.

Item G:

Week
Item G 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 50 100 50 100 150
Scheduled  receipt
On hand (75) 75 25 0 0 0
Net requirement 0 75 50 100 150
Planned order receipt 75 50 100 150
Planned order release 75 50 100 150

Week 5:

The gross requirement is 50 (1 assembly) derived from planned order release of C. The on hand inventory is 75. Hence, the net requirement is 0. Therefore, there will be no planned order release.

Week 6:

The gross requirement is 100 (1 assembly) derived from planned order release of C. The on hand inventory is 25. Hence, the net requirement is 75. The lead time is 1 week. Therefore, the planned order release will be 75 in week 5 which will be the planned order receipt in week 6.

Week 7:

The gross requirement is 50 (1 assembly) derived from the planned order release of C. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 6 which will be the planned order receipt in week 7.

Week 8:

The gross requirement is 100 (1 assembly) derived from planned order release of C and K. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 8.

Week 9:

The gross requirement is 150 (1 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 8 which will be the planned order receipt in week 9.

b)

Summary Introduction

To develop: A net requirements plan for all items.

Introduction:

Net requirements plan:

The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Product structure:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 14, Problem 12P , additional homework tip  2

Period 8 9 10 11 12
Gross requirements: A 100 50 150
Gross requirements: H 100 50

Inventory and lead time:

Item A B C D E F G H J K
Lead time 1 2 2 1 2 2 1 1 2 2
On hand 0 100 50 50 75 75 75 0 100 100
  • 1 assembly for each item
  • 2 assemblies for item B, C and F.

Item A:

Week
Item A 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 100 50 150
Scheduled  receipt
On hand (0) 0 0 0
Net requirement 100 50 150
Planned order receipt 100 50 150
Planned order release 100 50 150

Week 8:

The gross requirement is 100 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 8.

Week 10:

The gross requirement is 50 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 9 which will be the planned order receipt in week 10.

Week 12:

The gross requirement is 150 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 11 which will be the planned order receipt in week 12.

Item H:

Week
Item H 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 100 50
Scheduled  receipt
On hand (0) 0 0
Net requirement 100 50
Planned order receipt 100 50
Planned order release 100 50

Week 9:

The gross requirement is 100 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 1000. The lead time is 1 week. Therefore, the planned order release will be 100 in week 8 which will be the planned order receipt in week 10.

Week 11:

The gross requirement is 50 (1 assembly). The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 9 which will be the planned order receipt in week 11.

Item B:

Week
Item B 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 200 100 300
Scheduled  receipt
On hand (100) 100 0 0
Net requirement 100 100 300
Planned order receipt 100 100 300
Planned order release 100 100 300

Week 7:

The gross requirement is 200 (2 assembly) derived from planned order release of A. The on hand inventory is 100. Hence, the net requirement is 100. Therefore, the planned order release will be 100 in week 5 which will be the planned order receipt in week 7.

Week 9:

The gross requirement is 100 (2 assembly) derived from the planned order release of A. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 9.

Week 11:

The gross requirement is 300 (2 assembly) derived from planned order release of A. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 2 weeks. Therefore, the planned order release will be 300 in week 9 which will be the planned order receipt in week 11.

Item C:

Week
Item C 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 200 200 100 100 300
Scheduled  receipt
On hand (50) 50 0 0 0 0
Net requirement 150 200 100 100 300
Planned order receipt 150 200 100 100 300
Planned order release 150 200 100 100 300

Week 7:

The gross requirement is 200 (2 assembly) derived from planned order release of A. The on hand inventory is 50. Hence, the net requirement is 150. The lead time is 2 weeks. Therefore, the planned order release will be 150 in week 5 which will be the planned order receipt in week 7.

Week 8:

The gross requirement is 200 (2 assembly) derived from planned order release of H. The on hand inventory is 0. Hence, the net requirement is 200. The lead time is 2 weeks. Therefore, the planned order release will be 200 in week 6 which will be the planned order receipt in week 8.

Week 9:

The gross requirement is 100 (2 assembly) derived from the planned order release of A. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 9.

Week 10:

The gross requirement is 100 (2 assembly) derived from planned order release of H. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 8 which will be the planned order receipt in week 10.

Week 11:

The gross requirement is 300 (2 assembly) derived from planned order release of A. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 2 weeks. Therefore, the planned order release will be 300 in week 9 which will be the planned order receipt in week 11.

Item J:

Week
Item J 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 100 50
Scheduled  receipt
On hand (100) 100 0
Net requirement 0 50
Planned order receipt 0 50
Planned order release 50

Week 8:

The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.

Week 10:

The gross requirement is 50 (1 assembly) derived from the planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.

Item K:

Week
Item K 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 100 50
Scheduled  receipt
On hand (100) 100 0
Net requirement 0 50
Planned order receipt 50
Planned order release 50

Week 8:

The gross requirement is 100 (1 assembly) derived from planned order release of H. The on hand inventory is 100. Hence, the net requirement is 0. Therefore, there will be no planned order release.

Week 10:

The gross requirement is 50 (1 assembly) derived from the planned order release of H. The on hand inventory is 0. Hence, the net requirement is 50. The lead time is 2 weeks. Therefore, the planned order release will be 50 in week 8 which will be the planned order receipt in week 10.

Item D:

Week
Item D 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 100 100 300
Scheduled  receipt
On hand (50) 50 0 0
Net requirement 50 100 300
Planned order receipt 50 100 300
Planned order release 50 100 300

Week 6:

The gross requirement is 100 (1 assembly) derived from the planned order release of B. The on hand inventory is 50. Hence, the net requirement is 50. The lead time is 1 week. Therefore, the planned order release will be 50 in week 5 which will be the planned order receipt in week 6.

Week 8:

The gross requirement is 100 (1 assembly) derived from the planned order release of B. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 7 which will be the planned order receipt in week 8.

Week 8:

The gross requirement is 300 (1 assembly) derived from the planned order release of B. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 1 week. Therefore, the planned order release will be 300 in week 9 which will be the planned order receipt in week 10.

Item E:

Week
Item E 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 100 100 100 300
Scheduled  receipt
On hand (75) 75 0 0 0
Net requirement 25 100 100 300
Planned order receipt 25 100 100 300
Planned order release 25 100 100 300

Week 5:

The gross requirement is 100 (1 assembly) derived from planned order release of B. The on hand inventory is 75. Hence, the net requirement is 25. The lead time is 2 weeks. Therefore, the planned order release will be 25 in week 3 which will be the planned order receipt in week 5.

Week 7:

The gross requirement is 100 (1 assembly) derived from planned order release of B. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 5 which will be the planned order receipt in week 7.

Week 8:

The gross requirement is 100 (1 assembly) derived from the planned order release of J and K. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 8.

Week 9:

The gross requirement is 300 (1 assembly) derived from planned order release of B. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 2 weeks. Therefore, the planned order release will be 300 in week 7 which will be the planned order receipt in week 9.

Item F:

Week
Item F 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 300 400 200 300 600
Scheduled  receipt
On hand (75) 75 0 0 0 0
Net requirement 225 400 200 300 600
Planned order receipt 225 400 200 300 600
Planned order release 225 400 200 300 600

Week 5:

The gross requirement is 300 (2 assembly) derived from planned order release of C. The on hand inventory is 75. Hence, the net requirement is 225. The lead time is 2 weeks.  Therefore, the planned order release will be 225 in week 3 which will be the planned order receipt in week 5.

Week 6:

The gross requirement is 400 (2 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 400. The lead time is 2 weeks. Therefore, the planned order release will be 400 in week 4 which will be the planned order receipt in week 6.

Week 7:

The gross requirement is 200 (2 assembly) derived from the planned order release of C. The on hand inventory is 0. Hence, the net requirement is 200. The lead time is 2 weeks. Therefore, the planned order release will be 200 in week 5 which will be the planned order receipt in week 7.

Week 8:

The gross requirement is 300 (2 assembly) derived from planned order release of C and J. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 2 weeks. Therefore, the planned order release will be 300 in week 6 which will be the planned order receipt in week 8.

Week 9:

The gross requirement is 600 (2 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 600. The lead time is 2 weeks. Therefore, the planned order release will be 600 in week 7 which will be the planned order receipt in week 9.

Item G:

Week
Item G 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 150 200 100 150 300
Scheduled  receipt
On hand (75) 75 0 0 0 0
Net requirement 75 200 100 150 300
Planned order receipt 75 200 100 150 300
Planned order release 75 200 100 150 300

Week 5:

The gross requirement is 150 (1 assembly) derived from planned order release of C. The on hand inventory is 75. Hence, the net requirement is 75. The lead time is 1 week. Therefore, the planned order release will be 75 in week 4 which will be the planned order receipt in week 5.

Week 6:

The gross requirement is 200 (1 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 200. The lead time is 1 week. Therefore, the planned order release will be 200 in week 5 which will be the planned order receipt in week 6.

Week 7:

The gross requirement is 100 (1 assembly) derived from the planned order release of C. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 7.

Week 8:

The gross requirement is 150 (1 assembly) derived from planned order release of C and K. The on hand inventory is 0. Hence, the net requirement is 150. The lead time is 1 week. Therefore, the planned order release will be 150 in week 7 which will be the planned order receipt in week 8.

Week 9:

The gross requirement is 300 (1 assembly) derived from planned order release of C. The on hand inventory is 0. Hence, the net requirement is 300. The lead time is 1 week. Therefore, the planned order release will be 300 in week 8 which will be the planned order receipt in week 9.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
What is Bitcoin? How important is it to businesses and individuals? How does it cause environmental damage and is that damage worth continued uses of Bitcoin? Read the following articles to help answer these questions: United Nations University. (2023, October 24). UN study reveals the hidden environmental impacts of bitcoin: Carbon is not the only harmful by-product. https://unu.edu/press-release/un-study-reveals-hidden-environmental-impacts-bitcoin-carbon-not-only-harmful-product#:~:text=Bitcoin%2C%20the%20most%20popular%20cryptocurrency,the%20worldwide%20Bitcoin%20mining%20network. Salam, E. (2023, April 26). Bitcoin is terrible for the environment – can it ever go green? The Guardian. https://www.theguardian.com/technology/2023/apr/26/bitcoin-mining-climate-crisis-environmental-impact
419 X .com/courses/1546/assignments/49499?module_item_id=111573 Unlimited Attempts Allowed ✓ Details Directions: Record a video of yourself giving a business presentation. Imagine you are tasked with researching a professional development topic on business communication for 40 coworkers. You are then expected to give a 4 - 5 minute presentation on the topic. Choose any topic related to business communication, such as intercultural communication, effective leadership, professional writing, etc. Research the topic and prepare a 4 - 5 minute presentation that could be given over video conference call (such as Zoom). You may use visual aids if you choose. Upload a video file of your presentation. Provide all needed citations. Requirements: 4-5 minutes long Contains visual and audio Create your own work; do not plagiarize Cite your sources using APA citations Choose a submission type T
acts Container chips (s 150 cussion: Conflict X + e.com/courses/1546/discussion_topics/15722?module_item_id=111559 24 Winter > Discussions > Week 8 Discussion: Conflict 时☆ 26 Replies, 26 Unread Week 8 Discussion: Conflict Write a 200 - 300 word discussion post based on the prompt below. Reply to at least one other student in 50 - 100 words. Can you think of a time when a conflict led to a new opportunity, better understanding, or other positive result? If not, think of a past conflict and imagine a positive outcome. Discuss the impact of this conflict on your workplace relationships, productivity, and innovation. Source: Business Communication for Success. (2015). University of Minnesota Libraries Publishing. Attribution-NonCommerical-ShareAlike. Edit View Insert Format Tools Table 12ptv Paragraph BIUA T2

Chapter 14 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 28PCh. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1CSCh. 14 - Prob. 2CSCh. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - Prob. 2.1VCCh. 14 - Prob. 2.2VCCh. 14 - Prob. 2.3VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
    Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
  • Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Principles of Management
    Management
    ISBN:9780998625768
    Author:OpenStax
    Publisher:OpenStax College
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY