Concept explainers
a)
To determine: The change in the items due to the change in the lead time of item G.
Introduction:
Net requirements plan:
The Net requirements plan is the plan which is established on the Gross requirements plan formed by deducting the stock on and the
a)

Answer to Problem 16P
The change will take place only with item G because it has no children. The Lead time of 4 weeks will preempt the Planned order release by 1 one week.
Explanation of Solution
Given information:
- 10 units for service and production department for B and F.
- 10 units of A at week 8.
- Lead time of G has been changed to 4 weeks.
Part | A | B | C | D | E | F | G | H |
On hand | 0 | 2 | 10 | 5 | 4 | 5 | 1 | 10 |
Product structure:
Net requirements plan:
Item A:
Week | ||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | |||||||
Scheduled receipt | ||||||||
On-hand (0) | 0 | |||||||
Net requirement | 10 | |||||||
Planned order receipt | 10 | |||||||
Planned order release | 10 |
Week 8:
The gross requirement is 10 (1 assembly). The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 7 which will be the Planned order receipt in week 8.
Item B:
Week | ||||||||
Item B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (2) | 2 | 0 | ||||||
Net requirement | 8 | 10 | ||||||
Planned order receipt | 8 | 10 | ||||||
Planned order release | 8 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 2. Hence, the Net requirement is 8. The lead time is 1 week. Therefore, the planned order release will be 8 in week 5 which will be the planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the planned order release will be 10 in week 6 which will be the planned order receipt in week 7.
Item F:
Week | ||||||||
Item F | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 5 | 10 | ||||||
Planned order receipt | 5 | 10 | ||||||
Planned order release | 5 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.
Item D:
Week | ||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 8 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 8 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 5. Hence, the Net requirement is 3. The lead time is 1 week. Therefore, the Planned order release will be 3 in week 4 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 5 which will be the Planned order receipt in week 6.
Item G (Lead Time = 3):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 3 weeks. Therefore, the Planned order release will be 4 in week 2 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 3 weeks. Therefore, the Planned order release will be 10 in week 3 which will be the Planned order receipt in week 6.
Item G (Lead Time = 4):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 4 weeks. Therefore, the Planned order release will be 4 in week 1 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 4 weeks. Therefore, the Planned order release will be 10 in week 2 which will be the Planned order receipt in week 6.
Item H:
Week | ||||||||
Item H | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 5 | ||||||
Net requirement | 5 | |||||||
Planned order receipt | 5 | |||||||
Planned order release | 5 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 10. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 6.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Item C:
Week | ||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 13 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 13 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 10. Hence, the Net requirement is 3. The lead time is 2 weeks. Therefore, the Planned order release will be 3 in week 3 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 2 weeks. Therefore, the Planned order release will be 10 in week 4 which will be the Planned order receipt in week 6.
Item E:
Week | ||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 3 | 15 | ||||||
Scheduled receipt | ||||||||
On-hand (4) | 4 | 1 | ||||||
Net requirement | 14 | |||||||
Planned order receipt | 14 | |||||||
Planned order release | 14 |
Week 4:
The gross requirement is 3 (1 assembly) derived from the Planned order release of D. The on-hand inventory is 4. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 5.
Week 5:
The gross requirement is 15 (1 assembly) derived from the Planned order release of H. The on-hand inventory is 1. Hence, the Net requirement is 14. The lead time is 1 week. Therefore, the Planned order release will be 14 in week 4 which will be the Planned order receipt in week 5.
Hence, the change will take place only with item G because it has no children. The Lead time of 4 weeks will preempt the Planned order release by 1 one week.
b)
To determine: The implications of the production plan because of change in the lead time of item G.
Introduction:
Net requirements plan:
The Net requirements plan is the plan which is established on the Gross requirements plan formed by deducting the stock on and the Scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
b)

Answer to Problem 16P
The production plan will be altered such that item F and four units of A will be delayed by 1 week.
Explanation of Solution
Given information:
- 10 units for service and production department for B and F.
- 10 units of A at week 8.
- Lead time of G has been changed to 4 weeks.
Part | A | B | C | D | E | F | G | H |
On Hand | 0 | 2 | 10 | 5 | 4 | 5 | 1 | 10 |
Product structure:
Net requirements plan:
Item A:
Week | ||||||||
Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | |||||||
Scheduled receipt | ||||||||
On-hand (0) | 0 | |||||||
Net requirement | 10 | |||||||
Planned order receipt | 10 | |||||||
Planned order release | 10 |
Week 8:
The gross requirement is 10 (1 assembly). The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 7 which will be the Planned order receipt in week 8.
Item B:
Week | ||||||||
Item B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (2) | 2 | 0 | ||||||
Net requirement | 8 | 10 | ||||||
Planned order receipt | 8 | 10 | ||||||
Planned order release | 8 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 2. Hence, the Net requirement is 8. The lead time is 1 week. Therefore, the Planned order release will be 8 in week 5 which will be the Planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.
Item F:
Week | ||||||||
Item F | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 10 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 5 | 10 | ||||||
Planned order receipt | 5 | 10 | ||||||
Planned order release | 5 | 10 |
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Week 7:
The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.
Item D:
Week | ||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 8 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (5) | 5 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 8 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 5. Hence, the Net requirement is 3. The lead time is 1 week. Therefore, the Planned order release will be 3 in week 4 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 5 which will be the Planned order receipt in week 6.
Item G (Lead Time = 3):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 3 weeks. Therefore, the Planned order release will be 4 in week 2 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 3 weeks. Therefore, the Planned order release will be 10 in week 3 which will be the Planned order receipt in week 6.
Item G (Lead Time = 4):
Week | ||||||||
Item G | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (1) | 1 | 0 | ||||||
Net requirement | 4 | 10 | ||||||
Planned order receipt | 4 | 10 | ||||||
Planned order release | 4 | 10 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 4 weeks. Therefore, the Planned order release will be 4 in week 1 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 4 weeks. Therefore, the Planned order release will be 10 in week 2 which will be the Planned order receipt in week 6.
Item H:
Week | ||||||||
Item H | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 5 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 5 | ||||||
Net requirement | 5 | |||||||
Planned order receipt | 5 | |||||||
Planned order release | 5 |
Week 5:
The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 10. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 6.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.
Item C:
Week | ||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 13 | 10 | ||||||
Scheduled receipt | ||||||||
On-hand (10) | 10 | 0 | ||||||
Net requirement | 3 | 10 | ||||||
Planned order receipt | 3 | 10 | ||||||
Planned order release | 3 | 10 |
Week 5:
The gross requirement is 13 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 10. Hence, the Net requirement is 3. The lead time is 2 weeks. Therefore, the Planned order release will be 3 in week 3 which will be the Planned order receipt in week 5.
Week 6:
The gross requirement is 10 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 2 weeks. Therefore, the Planned order release will be 10 in week 4 which will be the Planned order receipt in week 6.
Item E:
Week | ||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 3 | 15 | ||||||
Scheduled receipt | ||||||||
On-hand (4) | 4 | 1 | ||||||
Net requirement | 14 | |||||||
Planned order receipt | 14 | |||||||
Planned order release | 14 |
Week 4:
The gross requirement is 3 (1 assembly) derived from the Planned order release of D. The on-hand inventory is 4. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 5.
Week 5:
The gross requirement is 15 (1 assembly) derived from the Planned order release of H. The on-hand inventory is 1. Hence, the Net requirement is 14. The lead time is 1 week. Therefore, the Planned order release will be 14 in week 4 which will be the Planned order receipt in week 5.
If this week is week 1 of the production plan, the increase in the lead time will make that only 1 assembly of G will be available for F in week 5. Hence, item F and consequently 4 units of item A will be delayed by a time of 1 week.
c)
To determine: The options the
c)

Explanation of Solution
Options the production manager has to manage these changes:
The production manager can do the following. They are:
- The production manager can inform the customer in advance that the 4 units will be delayed by a time of 1 week.
- The production manager can ask the supplier of item G to expedite the production or the delivery.
- The production manager can reduce the time take for production of item F or A.
Want to see more full solutions like this?
Chapter 14 Solutions
Principles Of Operations Management
- Apple is a global technology company renowned for its innovation and design. To create its products, Apple has established a world class global supply chain to bring their products to market. What strategies is Apple using to source and manufacture its products? How does Apple view its responsibility to its suppliers and those who build its products?arrow_forwardCritical Path Method (CPM) is an important Project Management Tool that has wide industry application in modern day Project Management. By using an example of the project of your choice, critically examine the practical application of CPM as a Project Management Tool.arrow_forwardwhat is an other difination for principle?arrow_forward
- Need help or ideas to design out two slides as my script and writing quite long to squeese into two slides. But can just point form in slides with correct title and a good script for me to present two slides in only 2.5 mins. Following is my draft, pls guide me step by step on powerpoint creation and good script to present findings. My draft: Slide 1: Foreign Labor Exploitation in Dyson's Supply Chain Introduction Dyson's former Malaysian supplier, ATA IMS Bhd, became embroiled in serious labor exploitation allegations in 2021. These concerns surfaced when whistleblowers exposed unethical labor practices affecting migrant workers, primarily from Nepal and Bangladesh. Key Forms of Exploitation Debt Bondage Due to Recruitment Fees Workers were forced to pay exorbitant recruitment fees before securing employment, often taking loans at high interest rates. This financial burden trapped them in debt bondage, leaving them with little choice but to accept exploitative working…arrow_forwardNot use ai pleasearrow_forwardThe Business Development Bank of Canada. (2023). Canadian economic outlook for 2024: Shifting into neutral. https://www.bdc.ca/en/articles-tools/blog/canadian-economic-outlook-for-2024-shifting-into-neutral “Despite persistently high inflation and rising interest rates, the news was generally better than expected for the Canadian economy in 2023” (BDC Blog 2024). Discussion Question: In your view, what are the most pressing problems for Canadian companies or consumers in 2024? Explain your answer using current examples of companies or consumer concerns.arrow_forward
- how have idividual objectives led to the current situation at TeraCog? what should Emaa do?arrow_forwardCan you write me an email about addressing an issue to mentor my supervisor the right way of deligating operations dutiesarrow_forwardCan you right me an email about addressing an issue to mentor the right why of deligating operations dutiesarrow_forward
- Define delegation. Discuss in detail the four reasons why managers do delegation? Also statethe four main types of delegation.arrow_forwardB) Going forward, is Lean/JIT worth the risks? Should it be embraced (why?), abandoned (if so, why & what are the costs), or modified (how?) Do you think Lean works or not? Please write a complete response (about 1-2 paragraphs each part). Each team member should discuss and contribute so that the group agrees on their joint response. Please help each other and build upon and/or challenge others' points (in a respectful way!)arrow_forwardDiscuss the principle reasons that employee benefits have risen over the past 20 years, along with how best an organization can provide employees with a fair wage yet also provide some level of employee benefit coverage.arrow_forward
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningContemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage Learning
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,