
Concept explainers
Using the data for the coffee table in Problem 14.31, build a labor

To determine: The number of labor hours and employees needed each day.
Explanation of Solution
Given information:
- Table requires 1 top, 4 legs, 1/8 gallon of strain, 1/16 gallon of blue, 2 short braces, 2 long braces, and brass cap on the bottom of each leg.
- 100 gallons of glue as inventory.
- All items except brass caps, stain and glue are planned on a Lot for lot basis.
- Caps are purchased in 1000’s, stain and glue by gallon.
- Lead time = 1 (for each item).
- 640 coffee tables needed on day 5 and 6.
- 128 coffee tables needed on days 7 and 8.
- Labor standard for each top is 2 labor hours.
- Each leg with brass cap installation and each pair of braces need ¼ hour.
- Base assembly needs 1 labor hour.
- Final assembly of table requires 2 labor hours.
- Number of hours per day is 8.
Product structure:
Net requirements plan:
Table:
Period (Day) | ||||||||
Table | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 640 | 640 | 128 | 128 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 0 | 0 | 0 | ||||
Net requirement | 640 | 640 | 128 | 128 | ||||
Planned order receipt | 640 | 640 | 128 | 128 | ||||
Planned order release | 640 | 640 | 128 | 128 |
Day 5:
The gross requirement is 640 (1 assembly) of Coffee table derived from the given information. The On hand is 0. Therefore, the net requirement is 640. The lead time is 1 week. The planned order release will be 640 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 640 (1 assembly) of Coffee table derived from the given information. The On hand is 0. Therefore, the net requirement is 640. The lead time is 1 week. The planned order release will be 640 in day 5 which will be the planned order receipt in day 6.
Day 7:
The gross requirement is 128 (1 assembly) of Coffee table derived from the given information. The On hand is 0. Therefore, the net requirement is 128. The lead time is 1 week. The planned order release will be 128 in day 6 which will be the planned order receipt in day 7.
Day 8:
The gross requirement is 128 (1 assembly) of Coffee table derived from the given information. The On hand is 0. Therefore, the net requirement is 128. The lead time is 1 week. The planned order release will be 128 in day 7 which will be the planned order receipt in day 8.
Top:
Period (Day) | ||||||||
Top | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 640 | 640 | 128 | 128 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 0 | 0 | 0 | ||||
Net requirement | 640 | 640 | 128 | 128 | ||||
Planned order receipt | 640 | 640 | 128 | 128 | ||||
Planned order release | 640 | 640 | 128 | 128 |
Day 4:
The gross requirement is 640 (1 assembly) of Top derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 640. The lead time is 1 week. The planned order release will be 640 in day 3 which will be the planned order receipt in day 4.
Day 5:
The gross requirement is 640 (1 assembly) of Top derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 640. The lead time is 1 week. The planned order release will be 640 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 128 (1 assembly) of Top derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 128. The lead time is 1 week. The planned order release will be 128 in day 5 which will be the planned order receipt in day 6.
Day 7:
The gross requirement is 128 (1 assembly) of Top derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 128. The lead time is 1 week. The planned order release will be 128 in day 6 which will be the planned order receipt in day 7.
Stain:
Period (Day) | ||||||||
Stain | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 80 | 80 | 16 | 16 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 0 | 0 | 0 | ||||
Net requirement | 80 | 80 | 16 | 16 | ||||
Planned order receipt | 80 | 80 | 16 | 16 | ||||
Planned order release | 80 | 80 | 16 | 16 |
Day 4:
The gross requirement is 80 (1 assembly) of Stain derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 80. The lead time is 1 week. The planned order release will be 80 in day 3 which will be the planned order receipt in day 4.
Day 5:
The gross requirement is 80 (1 assembly) of Stain derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 80. The lead time is 1 week. The planned order release will be 80 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 16 (1 assembly) of Stain derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 16. The lead time is 1 week. The planned order release will be 16 in day 5 which will be the planned order receipt in day 6.
Day 7:
The gross requirement is 16 (1 assembly) of Stain derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 16. The lead time is 1 week. The planned order release will be 16 in day 6 which will be the planned order receipt in day 7.
Glue:
Period (Day) | ||||||||
Glue | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 40 | 40 | 8 | 8 | ||||
Scheduled receipt | ||||||||
On hand (100) | 100 | 60 | 20 | 12 | 4 | |||
Net requirement | 0 | 0 | 0 | 0 | ||||
Planned order receipt | ||||||||
Planned order release |
Day 4:
The gross requirement is 40 (1 assembly) of Glue derived from the planned order release of Table. The On hand is 100. Therefore, the net requirement is 0. Therefore there will be no planned order release. The excess inventory 60 will be available at week 5.
Day 5:
The gross requirement is 40 (1 assembly) of Glue derived from the planned order release of Table. The On hand is 60. Therefore, the net requirement is 0. Therefore there will be no planned order release. The excess inventory 20 will be available at week 6.
Day 6:
The gross requirement is 8 (1 assembly) of Glue derived from the planned order release of Table. The On hand is 20. Therefore, the net requirement is 0. Therefore there will be no planned order release. The excess inventory 12 will be available at week 7.
Day 7:
The gross requirement is 8 (1 assembly) of Glue derived from the planned order release of Table. The On hand is 12. Therefore, the net requirement is 0. Therefore there will be no planned order release. The excess inventory 8 will be available at week 8.
Base assembly:
Period (Day) | ||||||||
Base | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 640 | 640 | 128 | 128 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 0 | 0 | 0 | ||||
Net requirement | 640 | 640 | 128 | 128 | ||||
Planned order receipt | 640 | 640 | 128 | 128 | ||||
Planned order release | 640 | 640 | 128 | 128 |
Day 4:
The gross requirement is 640 (1 assembly) of base assembly derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 640. The lead time is 1 week. The planned order release will be 640 in day 3 which will be the planned order receipt in day 4.
Day 5:
The gross requirement is 640 (1 assembly) of base assembly derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 640. The lead time is 1 week. The planned order release will be 640 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 128 (1 assembly) of base assembly derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 128. The lead time is 1 week. The planned order release will be 128 in day 5 which will be the planned order receipt in day 6.
Day 7:
The gross requirement is 128 (1 assembly) of base assembly derived from the planned order release of Table. The On hand is 0. Therefore, the net requirement is 128. The lead time is 1 week. The planned order release will be 128 in day 6 which will be the planned order receipt in day 7.
Short brace:
Period (Day) | ||||||||
Short Brace | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 1,280 | 1,280 | 256 | 256 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 0 | 0 | 0 | ||||
Net requirement | 1,280 | 1,280 | 256 | 256 | ||||
Planned order receipt | 1,280 | 1,280 | 256 | 256 | ||||
Planned order release | 1,280 | 1,280 | 256 | 256 |
Day 3:
The gross requirement is 1,280 (2 assembly) of short brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 1,280. The lead time is 1 week. The planned order release will be 1,280 in day 2 which will be the planned order receipt in day 3.
Day 4:
The gross requirement is 1,280 (2 assembly) of short brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 1,280. The lead time is 1 week. The planned order release will be 1,280 in day 3 which will be the planned order receipt in day 4.
Day 5:
The gross requirement is 256 (2 assembly) of short brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 256. The lead time is 1 week. The planned order release will be 256 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 256 (2 assembly) of short brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 256. The lead time is 1 week. The planned order release will be 256 in day 5 which will be the planned order receipt in day 6.
Long brace:
Period (Day) | ||||||||
Long Brace | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 1,280 | 1,280 | 256 | 256 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 0 | 0 | 0 | ||||
Net requirement | 1,280 | 1,280 | 256 | 256 | ||||
Planned order receipt | 1,280 | 1,280 | 256 | 256 | ||||
Planned order release | 1,280 | 1,280 | 256 | 256 |
Day 3:
The gross requirement is 1,280 (2 assembly) of long brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 1,280. The lead time is 1 week. The planned order release will be 1,280 in day 2 which will be the planned order receipt in day 3.
Day 4:
The gross requirement is 1,280 (2 assembly) of long brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 1,280. The lead time is 1 week. The planned order release will be 1,280 in day 3 which will be the planned order receipt in day 4.
Day 5:
The gross requirement is 256 (2 assembly) of long brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 256. The lead time is 1 week. The planned order release will be 256 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 256 (2 assembly) of long brace derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 256. The lead time is 1 week. The planned order release will be 256 in day 5 which will be the planned order receipt in day 6.
Leg:
Period (Day) | ||||||||
Leg | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 2,560 | 2,560 | 512 | 512 | ||||
Scheduled receipt | ||||||||
On hand (0) | ||||||||
Net requirement | 2,560 | 2,560 | 512 | 512 | ||||
Planned order receipt | 2,560 | 2,560 | 512 | 512 | ||||
Planned order release | 2,560 | 2,560 | 512 | 512 |
Day 3:
The gross requirement is 2,560 (4 assembly) of leg derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 2,560. The lead time is 1 week. The planned order release will be 2,560 in day 2 which will be the planned order receipt in day 3.
Day 4:
The gross requirement is 2,560 (4 assembly) of leg derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 2,560. The lead time is 1 week. The planned order release will be 2,560 in day 3 which will be the planned order receipt in day 4.
Day 5:
The gross requirement is 512 (4 assembly) of leg derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 512. The lead time is 1 week. The planned order release will be 512 in day 4 which will be the planned order receipt in day 5.
Day 6:
The gross requirement is 512 (4 assembly) of leg derived from the planned order release of base assembly. The On hand is 0. Therefore, the net requirement is 256. The lead time is 1 week. The planned order release will be 512 in day 5 which will be the planned order receipt in day 6.
Brass caps:
Period (Day) | ||||||||
Brass caps | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 2,560 | 2,560 | 512 | 512 | ||||
Scheduled receipt | ||||||||
On hand (0) | 0 | 440 | 880 | 368 | 856 | 856 | 856 | |
Net requirement | 2,560 | 2,120 | 0 | 144 | ||||
Planned order receipt | 3,000 | 3,000 | 1,000 | |||||
Planned order release | 3,000 | 3,000 | 1,000 |
Day 2:
The gross requirement is 2,560 (1 assembly) of brass caps derived from the planned order release of legs. The On hand is 0. Therefore, the net requirement is 2,560. The lead time is 1 week. The planned order release will be 3,000 (1 Lot = 1,000) in day 1 which will be the planned order receipt in day 2. The excess inventory of 440 is available at day 3.
Day 3:
The gross requirement is 2,560 (1 assembly) of brass caps derived from the planned order release of legs. The On hand is 440. Therefore, the net requirement is 2,120. The lead time is 1 week. The planned order release will be 3,000 (1 Lot = 1,000) in day 2 which will be the planned order receipt in day 3. The excess inventory of 880 is available at day 4.
Day 4:
The gross requirement is 512 (1 assembly) of brass caps derived from the planned order release of legs. The On hand is 880. Therefore, the net requirement is 0. Therefore, there will be no planned release. The excess inventory of 368 is available at day 5.
Day 5:
The gross requirement is 512 (1 assembly) of brass caps derived from the planned order release of legs. The On hand is 368. Therefore, the net requirement is 144. The lead time is 1 week. The planned order release will be 1,000 (1 Lot = 1,000) in day 4 which will be the planned order receipt in day 5. The excess inventory of 856 is available at the next day.
Calculation of labor hours / day:
Master Schedule | Hours Required | Day 1 | Day 2 | Day 3 | Day 4 | Day 5 | Day 6 | Day 7 | Day 8 |
Table assembly | 2 | 1280 | 1280 | 256 | 256 | ||||
Top preparation | 2 | 1280 | 1280 | 256 | 256 | ||||
Assemble base | 1 | 640 | 640 | 128 | 128 | ||||
Long brace (2) | 0.25 | 320 | 320 | 64 | 64 | ||||
Short brace (2) | 0.25 | 320 | 320 | 64 | 64 | ||||
Leg (4) | 0.25 | 640 | 640 | 128 | 128 | ||||
Total Hours | 0 | 1280 | 3200 | 3456 | 1920 | 640 | 256 | ||
Employees need @ 8 hours / day | 0 | 160 | 400 | 432 | 240 | 80 | 32 |
The master production schedule is derived from net requirements plan.
Formula to calculate number of hours / each day:
Formula to calculate the number of employees per 8 hour day:
Day 2:
Calculation of total hours for each day for each component:
Long brace:
Short brace:
Leg:
Calculation of total hours / day:
The total hours is calculated by summing all the hours needed for each component in a day.
Calculation of number of employees per 8 hour day:
The number of employees is calculated by dividing the total hours per day with the number of hours per day.
Day 3:
Calculation of total hours for each day for each component:
Top preparation:
Assemble base:
Long brace:
Short brace:
Leg:
Calculation of total hours / day:
The total hours is calculated by summing all the hours needed for each component in a day.
Calculation of number of employees per 8 hour day:
The number of employees is calculated by dividing the total hours per day with the number of hours per day.
Day 4:
Calculation of total hours for each day for each component:
Table assembly:
Top preparation:
Assemble base:
Long brace:
Short brace:
Leg:
Calculation of total hours / day:
The total hours is calculated by summing all the hours needed for each component in a day.
Calculation of number of employees per 8 hour day:
The number of employees is calculated by dividing the total hours per day with the number of hours per day.
Day 5:
Calculation of total hours for each day for each component:
Table assembly:
Top preparation:
Assemble base:
Long brace:
Short brace:
Leg:
Calculation of total hours / day:
The total hours is calculated by summing all the hours needed for each component in a day.
Calculation of number of employees per 8 hour day:
The number of employees is calculated by dividing the total hours per day with the number of hours per day.
Day 6:
Calculation of total hours for each day for each component:
Table assembly:
Top preparation:
Assemble base:
Calculation of total hours / day:
The total hours is calculated by summing all the hours needed for each component in a day.
Calculation of number of employees per 8 hour day:
The number of employees is calculated by dividing the total hours per day with the number of hours per day.
Day 7:
Calculation of total hours for each day for each component:
Table assembly:
Calculation of total hours / day:
The total hours is calculated by summing all the hours needed for each component in a day.
Calculation of number of employees per 8 hour day:
The number of employees is calculated by dividing the total hours per day with the number of hours per day.
Want to see more full solutions like this?
Chapter 14 Solutions
Principles Of Operations Management
- Agree or disagree with the post When you get an insulting offer, the best thing to do is stay calm and professional. Try not to take it personally or react out of anger. Instead, ask questions to understand why the offer was so low. This helps you get a better idea of what the other person is thinking. After that, you can respond with a counteroffer that shows your value. Use simple facts like your skills, experience, and what others in your field are getting paid to back up your request. If the person still refuses to offer something fair, it’s okay to politely say no and walk away. Standing up for yourself in a respectful way shows confidence and helps others take you seriously. Agree or disagree with the postarrow_forwardRegarding perceptions that can occur when negotiating in different places and at different times, the continuation norm in e-negotiations is best described as _____. Group of answer choices A. negotiators' beliefs that negotiations are worth continuing B. the act of thinking about how things might have turned out differently C. the tendency for e-communicators to ascribe diabolical intentions to the other party D. the tendency for negotiators to behave as if they are communicating synchronously when in fact they are notarrow_forwardIn any discussion or meeting, there is a tendency for a minority of people to do most of the talking. A key determinant of who dominates the conversation is _____. Group of answer choices A. their status within the group B. their network of social connections C. their gender D. their agearrow_forward
- With regard to intergenerational negotiation, the _____ generation has vast numbers of relationships but few of them are deep. They spend more time communicating virtually than face-to-face. Their personal and work networks are vital to their on-the-fly learning and problem-solving skills. Armed with tools for working anywhere at any time, this generation puts more value in leading a balanced life and flexibility with their work and life demands. Group of answer choices A. mature B. boomer C. millennial D. Generation Xarrow_forwardIf a negotiator has less power than the counterparty and an unattractive BATNA, which communication medium might help the less-powerful negotiator claim more resources?arrow_forwardCould you help explain what the foundations of faith are? What are their strategies?arrow_forward
- Hi! Can you guys help me with this? Thank you! Please write-up summarizing the core message of the movie/documentary and the connection to the course material The documentary is Poisoned: The Dirty Truth About Your Food directed by Stephanie Soechtig from Netflix. * Here are the course material: Global Logistics Global Transportation; Global Inventory Management Global Operation Global Market Channels Purchasing Stategies: Outsourcing; Offshoring; Nearshoring; Multi-sourcing & Co-sourcing Make or Buy decisions Global Supply Chain Infrastructure: Transportation Infrastructure; Communication Infrastructure; Utilities Infrastructure; Technology Infrastructure Supply Chain Risks: • Supply Risks – disruption of supply, inventory and schedules. • Operational Risks – breakdown of operations, changes in technologies. • Demand Risks – variations in demand.• Security Risks – theft, sabotage, terrorism, counterfeiting.• Macro Risks – economic shifts, recession, wage hikes, varying…arrow_forwardHi! Can you guys help me with this? Thank you! Please write-up summarizing the core message of the movie/documentary and the connection to the course material The documentary is American Factory by Steven Bognar & Julia Reichert from Netflix * Here the course material: Global Logistics Global Transportation; Global Inventory Management Global Operation Global Market Channels Purchasing Stategies: Outsourcing; Offshoring; Nearshoring; Multi-sourcing & Co-sourcing Make or Buy decsions Global Supply Chain Infrastructure: Transportation Infrastructure; Communication Infrastructure; Utilities Infrastructure; Technology Infrastructure Supply Chain Risks: • Supply Risks – disruption of supply, inventory and schedules. • Operational Risks – breakdown of operations, changes in technologies. • Demand Risks – variations in demand.• Security Risks – theft, sabotage, terrorism, counterfeiting.• Macro Risks – economic shifts, recession, wage hikes, varying exchangerates.• Policy Risks –…arrow_forward1) View the video Alton Bridge (12.16 mins, Ctrl + Click on the link), and please answer the following questions: https://meida.gaspar.mheducation.com/GASPARPlayer/play.html?id=24qHEm8aNZExFciJtZQbqli a) According to the video, what are the various steps involved in managing projects? b) What were the different phases of the Alton Bridge project? c) What are the two widely used scheduling techniques, and under what phase of the Alton Bridge project are they discussed? Note: As a rough guideline, please try to keep the written submission to a paragraph or so for each of the questions. 2) The following is a table of activities associated with a mining project at Lunar Industries, their durations, and what activities each must precede: Activity Duration (weeks) Precedes A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 - The AOM project diagram is as given below: a) What is the critical path (list all activities in the…arrow_forward
- 1) View the video Alton Bridge (12.16 mins, Ctrl + Click on the link), and please answer the following questions: a) According to the video, what are the various steps involved in managing projects? b) What were the different phases of the Alton Bridge project? c) What are the two widely used scheduling techniques, and under what phase of the Alton Bridge project are they discussed? Note: As a rough guideline, please try to keep the written submission to a paragraph or so for each of the questions. 2) The following is a table of activities associated with a mining project at Lunar Industries, their durations, and what activities each must precede: Activity Duration (weeks) Precedes A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 - The AOM project diagram is as given below:arrow_forwardWith all the problems companies are currently facing, why do so many choose to expand into international markets? What are the advantages of expanding beyond the domestic market?arrow_forwardPerform resource leveling. Assume that each task can be performed independently of the other tasks.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
- Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage LearningPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning


