Concept explainers
a)
To develop: A gross requirements plan for all the items.
Introduction:
Gross requirements plan:
The gross requirements plan is the plan where the independent and dependent demand for a product or a component before the on-hand inventory and the scheduled receipts are netted with.
a)
Explanation of Solution
Given information:
Product structure:
Master production
MPS for X1 | ||||||
Period | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 20 | 100 |
Inventory and lead time:
Item | X1 | B1 | B2 | A1 | C | D | E |
Lead time | 1 | 2 | 2 | 1 | 1 | 1 | 3 |
On hand | 50 | 20 | 20 | 5 | 0 | 0 | 10 |
Item X1:
Week | ||||||||||||
Item X1 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 20 | 100 | |||||||||
Order release | 50 | 20 | 100 |
The gross requirements are 50, 20 and 100 (1 assembly of X1) in weeks 8, 10 and 12 respectively derived from the master production schedule of X1. The lead time is 1 week. Therefore, the order release will be 50, 20 and 100 in weeks 7, 9 and 11 respectively.
Item B1:
Week | ||||||||||||
Item B1 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 20 | 100 | |||||||||
Order release | 50 | 20 | 100 |
The order release of X1 will become the gross requirements of B1. The gross requirements are 50, 20 and 100 (1 assembly of B1) in weeks 7, 9 and 11 respectively. The lead time is 2 weeks. Therefore, the order release will be 50, 20 and 100 in weeks 5, 7 and 9 respectively.
Item B2:
Week | ||||||||||||
Item B2 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 40 | 200 | |||||||||
Order release | 100 | 40 | 200 |
The order release of X1 will become the gross requirements of B2. The gross requirements are 100, 40 and 200 (2 assemblies of B2) in weeks 7, 9 and 11 respectively. The lead time is 2 weeks. Therefore, the order release will be 100, 40 and 200 in weeks 5, 7 and 9 respectively.
Item A1:
Week | ||||||||||||
Item A1 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 20 | 100 | |||||||||
Order release | 50 | 20 | 100 |
The order release of B1 will become the gross requirements of A1. The gross requirements are 50, 20 and 100 (1 assembly of A1) in weeks 5, 7 and 9 respectively. The lead time is 1 week. Therefore, the order release will be 50, 20 and 100 in weeks 4, 6 and 8 respectively.
Item C:
Week | ||||||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 200 | 80 | 400 | |||||||||
Order release | 200 | 80 | 400 |
The order release of B2 will become the gross requirements of C. The gross requirements are 200, 80 and 400 (2 assemblies of C) in weeks 5, 7 and 9 respectively. The lead time is 1 week. Therefore, the order release will be 200, 80 and 400 in weeks 4, 6 and 8 respectively.
Item D:
Week | ||||||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | 40 | 200 | |||||||||
Order release | 100 | 40 | 200 |
The order release of B2 will become the gross requirements of D. The gross requirements are 100, 40 and 200 (2 assemblies of C) in weeks 5, 7 and 9 respectively. The lead time is 1 week. Therefore, the order release will be 100, 40 and 200 in weeks 4, 6 and 8 respectively.
Item E:
Week | ||||||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 200 | 50 | 80 | 20 | 400 | 100 | ||||||
Order release | 200 | 50 | 80 | 20 | 400 | 100 |
The order release of B1 and D will become the gross requirements of E. The gross requirements are 50, 20 and 100 (1 assembly of E) in weeks 5, 7 and 9 respectively. The lead time is 3 weeks. Therefore, the order release will be 50, 20 and 100 in weeks 2, 4 and 6 respectively.
The gross requirements are 200, 80 and 400 (2 assembly of E) in weeks 4, 6 and 8 respectively. The lead time is 3 weeks. Therefore, the order release will be 200, 80 and 400 in weeks 1, 3 and 5 respectively.
b)
To develop: A net requirements plan for all the items.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
b)
Explanation of Solution
Given information:
Product structure:
Master production schedule for X1:
MPS for X1 | ||||||
Period | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 20 | 100 |
Inventory and lead time:
Item | X1 | B1 | B2 | A1 | C | D | E |
Lead time | 1 | 2 | 2 | 1 | 1 | 1 | 3 |
On hand | 50 | 20 | 20 | 5 | 0 | 0 | 10 |
Item X1:
Week | ||||||||||||
Item X1 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 50 | 20 | 100 | |||||||||
Scheduled receipt | ||||||||||||
On hand (50) | 50 | 0 | 0 | |||||||||
Net requirement | 0 | 20 | 100 | |||||||||
Planned order receipt | 20 | 100 | ||||||||||
Planned order release | 20 | 100 |
Week 8:
The gross requirement is 50 (1 assembly)derived from the master production schedule of X1. The on hand inventory is 50. Hence, the net requirement is 0. The lead time is 1 week. Therefore, there will be no planned order release.
Week 10:
The gross requirement is 20 (1 assembly) derived from the master production schedule of X1. The on hand inventory is 0. Hence, the net requirement is 20. The lead time is 1 week. Therefore, the planned order release will be 20 in week 9 which will be the planned order receipt in week 10.
Week 12:
The gross requirement is 100 (1 assembly) derived from the master production schedule of X1. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 1 week. Therefore, the planned order release will be 100 in week 11 which will be the planned order receipt in week 12.
Item B1:
Week | ||||||||||||
Item B1 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 20 | 100 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (20) | 20 | 0 | ||||||||||
Net requirement | 0 | 100 | ||||||||||
Planned order receipt | 100 | |||||||||||
Planned order release | 100 |
Week 9:
The gross requirement is 20 (1 assembly) derived from the planned order release of X1. The on hand inventory is 20. Hence, the net requirement is 0. The lead time is 2 weeks. Therefore, there will be no planned order release.
Week 11:
The gross requirement is 100 (1 assembly) derived from planned order release of X1. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 2 weeks. Therefore, the planned order release will be 100 in week 9 which will be the planned order receipt in week 11.
Item B2:
Week | ||||||||||||
Item B2 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 40 | 200 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (20) | 20 | 0 | ||||||||||
Net requirement | 20 | 200 | ||||||||||
Planned order receipt | 20 | 200 | ||||||||||
Planned order release | 20 | 200 |
Week 9:
The gross requirement is 40 (2 assembly) derived from the planned order release of X1. The on hand inventory is 20. Hence, the net requirement is 20. The lead time is 2 weeks. Therefore, the planned order release will be 20 in week 7 which will be the planned order receipt in week 9.
Week 11:
The gross requirement is 200 (2 assembly) derived from planned order release of X1. The on hand inventory is 0. Hence, the net requirement is 200. The lead time is 2 weeks. Therefore, the planned order release will be 200 in week 9 which will be the planned order receipt in week 11.
Item A1:
Week | ||||||||||||
Item A1 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 100 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (5) | 5 | |||||||||||
Net requirement | 95 | |||||||||||
Planned order receipt | 95 | |||||||||||
Planned order release | 95 |
Week 9:
The gross requirement is 100 (1 assembly) derived from the planned order release of B1. The on hand inventory is 5. Hence, the net requirement is 95. The lead time is 1 week. Therefore, the planned order release will be 95 in week 8 which will be the planned order receipt in week 9.
Item C:
Week | ||||||||||||
Item C | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 40 | 400 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | 0 | ||||||||||
Net requirement | 40 | 400 | ||||||||||
Planned order receipt | 40 | 400 | ||||||||||
Planned order release | 40 | 400 |
Week 7:
The gross requirement is 40 (2 assembly) derived from the planned order release of B2. The on hand inventory is 0. Hence, the net requirement is 40. The lead time is 1 week. Therefore, the planned order release will be 40 in week 6 which will be the planned order receipt in week 7.
Week 9:
The gross requirement is 400 (2 assembly) derived from planned order release of B2. The on hand inventory is 0. Hence, the net requirement is 400. The lead time is 1 week. Therefore, the planned order release will be 400 in week 8 which will be the planned order receipt in week 9.
Item D:
Week | ||||||||||||
Item D | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 20 | 200 | ||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | 0 | ||||||||||
Net requirement | 20 | 200 | ||||||||||
Planned order receipt | 20 | 200 | ||||||||||
Planned order release | 20 | 200 |
Week 7:
The gross requirement is 20 (1 assembly) derived from the planned order release of B2. The on hand inventory is 0. Hence, the net requirement is 20. The lead time is 1 week. Therefore, the planned order release will be 20 in week 6 which will be the planned order receipt in week 7.
Week 9:
The gross requirement is 200 (1 assembly) derived from planned order release of B2. The on hand inventory is 0. Hence, the net requirement is 200. The lead time is 1 week. Therefore, the planned order release will be 200 in week 8 which will be the planned order receipt in week 9.
Item E:
Week | ||||||||||||
Item E | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 40 | 400 | 100 | |||||||||
Scheduled receipt | ||||||||||||
On hand (10) | 10 | 0 | 0 | |||||||||
Net requirement | 30 | 400 | 100 | |||||||||
Planned order receipt | ||||||||||||
Planned order release | 30 | 400 | 100 |
Week 6:
The gross requirement is 40 (2 assembly) derived from the planned order release of B2. The on hand inventory is 10. Hence, the net requirement is 30. The lead time is 3 weeks. Therefore, the planned order release will be 30 in week 3 which will be the planned order receipt in week 6.
Week 8:
The gross requirement is 400 (2 assembly) derived from the planned order release of B2. The on hand inventory is 0. Hence, the net requirement is 400. The lead time is 3 weeks. Therefore, the planned order release will be 400 in week 5 which will be the planned order receipt in week 8.
Week 9:
The gross requirement is 100 (1 assembly) derived from the master production schedule of B1. The on hand inventory is 0. Hence, the net requirement is 100. The lead time is 3 weeks. Therefore, the planned order release will be 100 in week 6 which will be the planned order receipt in week 9.
Want to see more full solutions like this?
Chapter 14 Solutions
Principles Of Operations Management
- Emotional intelligence is defined as the ability to understand and manage your emotions, as well as recognize and influence the emotions of those around you. True Falsearrow_forwardAt the Ford automobile Highland plant, assume the one-millionth vehicle was produced in 1916 at a cost of $8084 (in 2013 US$), by how much did the Ford company reduce his cost with each doubling of cumulative output from 1916 to 1927?arrow_forwardAt the Ford automobile Highland plant,in 1913, how long did the average worker stay with the plant and what was the average tenure of a worker?arrow_forward
- Community Federal Bank in Dothan, Alabama, recently increased its fees to customers who use employees as tellers. Management is interested in whether its new tee policy has increased the number of customers now using its automatic teller machines to that point that more machines are required. The following table provides the number of automatic teller transactions by week. Use trend projection with regression to forecast usage for weeks 13-16.arrow_forwardDavison Electronics manufactures three LED television monitors, identified as Model A, Model B, and Model C. Davison Electronics four manufacturing plants. Each model has its lowest possible production cost when produced at Plant 1. However, Plant 1 does not have the capacity to handle the total production of all three models. As a result, at least some of the production must be routed to the other manufacturing plants. The following table shows the minimum production requirements for next month, the plant capacities in units per month, and the production cost per unit at each plant: Model Production Cost per Unit Minimum Production Requirements Plant 1 Plant 2 Plant 3 Plant 4 A $25 $28 $37 $34 48,000 B $26 $35 $36 $41 75,000 C $20 $31 $26 $23 60,000 Production Capacity 65,000 50,000 32,000 43,000 Davison’s objective is to determine the cost-minimizing production planarrow_forwardAnecdotally, entrepreneurs frequently encounter two critical dilemmas in managing human resources: the timing of hiring and the decision regarding hiring a generalist versus a specialist for their growing venture. Deciding when to expand a team is crucial, as premature hiring (i.e., hiring too soon) can strain resources, while delayed hiring (i.e., hiring too late) might hinder growth opportunities. Moreover, the choice between hiring a generalist or a specialist depends on the specific needs and stage of the venture, with each option presenting distinct advantages and challenges. To address these issues, a management scholar seeks to identify the factors shaping the hiring cycle throughout the entrepreneurial journey and to understand the criteria for choosing between generalists and specialists at various stages of a venture. The scholar has assembled a sample of 20 experienced South African entrepreneurs who have encountered both failure and success in the financial technology…arrow_forward
- 3. [25 pts.] Four projects are available for investment. The projects require the cash flows and yield the net present values (NPV) (in millions) shown in the following table. Project id. 1 2 Cash outflow at time 0 (million Lira) 8 8 NPV (million Lira) 12 11 3 4 6 5 8 6 If 20 million Lira is available for investment at time 0, find the investment plan that maximizes NPV. All investments are required to be 0 or 1 (fractional investment values are not permitted). a. Formulate the mathematical model. (Write the decision variables, objective function and the constraints.) [10 pts.] b. Find the optimal solution by using Branch and Bound method (Draw the branch and bound tree clearly, write also lower bounds(LB)) (Left branches x=0, right branches x =1) [15 pts.].arrow_forwardexamine the production concept and operations management, what are the key steps required to achieve success? Be specific in your response.arrow_forwardProduce a 3000 report with references on one international organization of your choice and Address the following: Provide a brief introduction of the organisation and sector it operates in, including its mission and vision statements, its core values, a summary of its financial performance and a general overview of the business’s operational activities. From the relevant literature explain the Total Quality Management (TQM) processes the chosen organization follows and identify one quality challenge/issue that the organization faced or is currently facing. Explain how the organization managed/or still managing the particular quality challenge/issue. Critically analyze whether the organization failed or succeeded in achieving and maintaining quality performance. Provide a few critical recommendations for business managers in order to highlight the importance of Total Quality Management (TQM) within an organization.arrow_forward
- 問題2 Production system design involves determining the arrangement of workstations and the... O allocation of resources to workstations design of the process O production schedule all of the abovearrow_forwardElaborate on the need for and the benefits of an effective supply chain management (SCM) system in the context of a globalized and networked economy. In your answer, explain how organizations like Dell and Hewlett-Packard leverage supply chain networks to maintain competitiveness, and analyse the impact of globalization, technological advancements, and business environment changes on supply chain structures. Additionally, evaluate the key components of SCM, including distribution network configuration, inventory management, and cash-flow management, and discuss how these components contribute to creating an effective and integrated supply chain. (15) 3.2. Critically evaluate the requirements for effective inventory management within an organization. In your answer, discuss the importance of inventory accounting systems, the role of cost information (holding, ordering, and shortage costs), and the significance of classification systems like ABC analysis. Additionally, analyse how…arrow_forwardAssess the role of EDI in ensuring supply chain security and data integrity. How does EDI contribute to reducing vulnerabilities in supply chain operations, and what best practices should organizations adopt to maintain a secure and reliable EDI system? (10) 1.3. Examine how the adoption of modern EDI systems influences the strategic decision-making process in supply chain management. How does EDI provide supply chain managers with actionable insights, and what are the implications of these insights for long-term supply chain planning? (10) 1.4. Evaluate the potential challenges and risks associated with the modernization of EDI systems in supply chain management. How can organizations effectively manage these challenges to ensure successful EDI implementation and ongoing optimization? (10)arrow_forward
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
- Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage LearningPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,