Concept explainers
a)
To develop: A net requirements plan for items.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the
b)
To develop: A net requirements plan for all items.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
Want to see the full answer?
Check out a sample textbook solutionChapter 14 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
- 14. Item A has a gross requirement of 2,000 in week 6. Currently, 500 units of Item A are on hand, with a scheduled receipt of 500 items in week 3. The lead time for item A is three weeks with an order quantity of 500. Complete the MRP record for item A.arrow_forwardIn the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 2 65 4 40 5 65 Gross requirements On hand Net requirements Planned order receipt Planned order release 42 Period Gross requirements Scheduled receipts 65 40 65 Item J LT = 1 Q = L4L Projected available balance Net requirements Planned order receipts Planned order releasesarrow_forwardA firm that produces electric golf carts has just received an order for 200 carts, which must be ready for delivery at the start of week 8. Information concerning the product structure, lead times, and quantities on hand is shown in the following table. Use this information to do each of the following: a. Develop a material requirements plan that will provide 200 golf carts by week 8, assuming lot-for-lot ordering. (Excel)arrow_forward
- Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of Hare in production and will be completed by the start of week 2. (Leave no cells blank - be certain to enter "O" wherever required.) B2) D(2) E(4) HO H3) Master Schedule Week Quantityarrow_forwardIn the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "o" wherever required.) WEEK NUMBER ITEM J Gross requirenents On-hand Net requirements Planned order receipt Planned order release 70 45 65 30 Perlod 2. Gross requirements 70 45 65 Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releasesarrow_forwardGiven the following MRP matrix for Item D, Complete the MRP matrix below to identify the projected on hand quantity at the end of period 5? Write you answer in the answer box. (Write the number only, DO NOT write the units, i.e. items, pieces, or units etc) ITEM: D Lot Size: Period POQ 2 4 5 7 120 Gross Requirements Schedule Receipts 60 90 150 150 180 270 Project on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases Page 9 of 20 Act Previous Page Next Page 36°C S.W 2020arrow_forward
- Assignment: Bill of Materials (BOM) How many units will be needed from B, C, D, E, F, and G if we want to produce 50 units of product A. Product (A) Level A Ci3) 1 Bi2) Ep) Fa Ej2) D12) 3 Di2) 2.arrow_forwardUse the following MRP record to answer the question. Item: LMN Description: Gross requirements. Scheduled receipts Projected on hand Date Planned receipts 30 Planned order releases Which one of the statements concerning item LMN is TRUE? O A. The projected on - hand inventory in week 8 is 70 units. B. The scheduled receipt of 80 units in week 3 should be expedited so that it is finished in week 2. OC. The planned order release quantity in week 3 is 80 units. O D. The planned receipt quantity in week 6 is 30 units. 1 2 3 60 80 4 Lot Size 80 units Lead Time: 3 weeks 5 30 30 80arrow_forwardProblem In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release Item J LT=1 Q=L4L 0 47 Period Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases 1 WEEK NUMBER 2 3 77 4 52 5 75 2 77 52 5 75arrow_forward
- Given the following MRP matrix for Item D, Complete the MRP matrix below to identify the projected on hand quantity at the end of period 5? Write you answer in the answer box. (Write the number only, DO NOT write the units, i.e. items, pieces, or units etc) ITEM: D Lot Size: Period РОQ 2 1 3 4 5 6. 7 Gross Requirements Schedule Receipts 60 90 150 150 180 270 120 Project on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases DELLarrow_forwardGiven the following MRP matrix for Item D, Complete the MRP matrix below to identify the projected on hand quantity at the end of period 5? Write you answer in the answer box. (Write the number only, DO NOT write the units, i.e. items, pieces, or units etc) ITEM: D Lot Size: Period POQ 2 3 4 7 60 90 150 150 180 270 120 Gross Requirements Schedule Receipts Project on Hand 150 Net Requirements Planned Order Receipts Planned Order Releasesarrow_forwardIn the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank-be certain to enter "0" wherever required.) ITEM 3 Gross requirements On-hand Net requirements Planned order receipt Planned order release Period Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases WEEK NUMBER 2 3 76 4 48 76 5 72 48 72arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.