Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
10th Edition
ISBN: 9780134181981
Author: Jay Heizer, Barry Render, Chuck Munson
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 14, Problem 32P
Using the data for the coffee table in Problem 14.31, build a labor
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
ss
An assembly line is to be designed to operate 7.5 hours per day and supply a steady demand of 300 units per day.
a)assign tasks to workstations using the longest operating time
b)suppose demand increase by 10%.how would you react to this?assume you can operatee only 7.5 hours per day
TASK
PRECEDING TASKS
PERFORMANCE TIME(seconds)
a
-
70
b
-
40
c
-
45
d
a
10
e
b
30
f
c
20
g
d
60
h
e
50
i
f
15
j
g
25
k
h,i
20
l
j,k
25
According to Appendix E, the answer is 80 units/hour. How?
.
Chapter 14 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- An assembly line is to be designed to operate 13 hours per day and supply a steady demand of 325 units per day. Here are the tasks and their performance times: TASK PRECEDINGTASKS PERFORMANCE TIME (SECONDS) TASK PRECEDINGTASKS PERFORMANCETIME (SECONDS) a — 48 g d 43 b — 58 h e 38 c — 73 i f 23 d a 63 j g 33 e b 88 k h, i 53 f c 23 l j, k 67 A) What is the efficiency of your line balance? B) Suppose demand increases by 10 percent. How would you react to this? Assume that you can operate only 13 hours per day in regular time. (Round your answers to the nearest whole number.)arrow_forwardPlease help to solve question d and e.arrow_forwardCan you show me how to do this review problem with steps?arrow_forward
- A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). A) is the bottleneck. b) The bottleneck time isminutes per unit (round your response to two decimal places). c) The throughput time of the overall system is enter your response here minutes (round your response to two decimal places). D) If the firm operates 8 hours per day, 20 days per month, the monthly capacity of the manufacturing process isunits (enter your response as a whole number).arrow_forwardAt Feebo Company, components U, V, W, and X are assembled in a cell in daily quantities of 70, 140, 280, and 35, respectively. Assuming a 480-minute workday, assume lot-for-lot, LT = 0. What is the MMP sequence? For the toolbar, press ALT F10 (PC) or ALT-FN+F10 (Mac)arrow_forwardPlease helparrow_forward
- A.J.’s Wildlife Emporium manufactures two unique birdfeeders (Deluxe and Super Duper) that are manufactured and assembled in up to three different workstations (X, Y, Z) using a small batch process. Each of the products is produced according to the flowchart in Figure. Additionally, the flowchart indicates each product’s price, weekly demand, and processing times per unit. Batch setup times are negligible.A.J. can make and sell up to the limit of its weekly demand and there are no penalties for not being able to meet all of the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone and is paid $16 per hour. The plant operates 40 hours per week, with no overtime. Overhead costs are $2,000 per week. Based on the information provided, as well as the information contained in the flowchart, answer the following questions. a. Using the traditional method, which bases decisions solely on a product’s contribution to profits and overhead, what is the…arrow_forwardExplain what are the risks of automating a production process and what are the risks for a service process?arrow_forwardH4. Explain properly and show all calculation stepsarrow_forward
- Operation managemetnarrow_forwarda. what is the bottleneck of this process? b. what is the hourly capacity of the process?arrow_forwardConstruct a Fishbone Diagram PROBLEM: Unable to meet the production quota resulting to opportunity loss CAUSES: High Rate of absenteeism (Laziness of workers) Idle Time of Workers (Laziness) Shortage of Materials Due to under-stock (supplier’s problem) Insufficient Number of Trucks (supplier’s problem) Longer Machine Downtime Lack of Technician (Machine cause) Bottleneck Poor Layout DATA: The company operates 9 hours a day with one hour organized lunch break Total working days per month is 20 days Production Quota is 40,000 units per day Actual Output is 16,000 units per day Rate of absenteeism is 8 workers per day Machine Capacity is 4000 units per…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY