Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
10th Edition
ISBN: 9780134181981
Author: Jay Heizer, Barry Render, Chuck Munson
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 14, Problem 26P
M. de Koster, of Rene Enterprises, has the master production plan shown below:
Lead time = 1 period; setup cost = $200; holding cost = $10 per week; stockout cost = $10 per week. Your job is to develop an ordering plan and costs for:
a) Lot-for-lot.
b) EOQ.
c) POQ.
d) Which plan has the lowest cost?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Please show the solution, thanks!
Using the gross requirements schedule below*, prepare an alternative ordering system that orders every 3 weeks for 3 weeks ahead (a periodic order quantity). What is the cost of this
ordering system?
Period
1 2 3 4 5 6 7
Gross requirements 25 20 40 0 10 50 30
The cost of this ordering system is $
Prepare a net requirements plan (enter your responses as whole numbers).
*Holding cost = $1/unit/week; setup cost = $200; lead time = 1 week; beginning inventory = 25 units.
Period
Gross requirements
On-hand at beginning of period
On-hand at end of period
Net requirements
Order receipt
Order release
(enter your response as a whole number).
25
1
25
2
20
3
40
4
5
0 10
8
0
6
50
9 10
30 65
7
30
8 9 10
0
30 65
Hand written out please step by step
Chapter 14 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - MRP at Wheeled Coach Wheeled Coach, the worlds...Ch. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The annual demand of Bulldogs Inc. sole product totaled 450,000 units. Due to uncertainty in supply of items, the maximum possible lead time for the orders is 2 weeks and 1 day. A safety stock of 6,250 units is determined. What is the normal lead time? (Use 360 days) A. 10 days B. 9 days C. 1 week and 5 days D. 1 weekarrow_forwardPlease help me with this practice problem. Please be specific of where to put the equations and what equations to use. Images would be helpful. Thank youarrow_forwardDemand for chicken soup at a supermarket is always 25 cases a day and the lead time is always 4 days. Theshelves were just restocked with chicken soup, leaving an on-hand inventory of only 10 cases. No backorderscurrently exist, but there is one open order in the pipeline for 200 cases. What is the inventory position? Shoulda new order be placed?arrow_forward
- Dennis Sport World, a chain of sporting goods stores, sells 360,000 tennis balls per year. The tennis balls cost Dennis Sport World RM15 per dozen. Annual inventory carrying costs are 20 percent of inventory price. The cost of placing and receiving an order are RM72. Assume the inventory replenishment occurs virtually instantaneously. Based on recent experience, Dennis Sport World uses 7 days delivery time for planning purposes. (Assume 360 days in a year) TASKS a) Calculate the Economic Order Quantity. b) Calculate the number of orders to be placed. c) Calculate the total annual inventory costs. d) Determine the reorder point.arrow_forwardShown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Ball bearings Order Policy: 500 units Lead Time: 1 week Quantity on Hand: 400 1 2 3 Forecast 550 250 350 Customer 300 350 250 orders (booked) Projected on-hand 350 500 150 inventory MPS quantity 500 500 0 Week [」 ༔ g - 4 5 6 7 8 9 10 350 350 200 300 400 450 150 150 100 150 100 100 350 500 300 500 100 150 500 500 0 500 0 500arrow_forwardWhat is the difference between a requirements philosophy and a replenishment philosophy of inventory management? Why is this difference important?arrow_forward
- should be handwritten/Typed and don't use Excel.arrow_forwardPlease do not give solution in image format thankuarrow_forwardFill in the blanks in the following Inventory Record using POQ inventory policy assuming: Lead Time 50, and scheduled receipts of 40 in week 1 A = 2, P=3, on hand inventory LT= Quantity= Lot Size = On hand = 2 P=3 50 = Gross requirements Scheduled receipts Projected on hand Planned-order receipts Planned-order releases B D 1 90 40 2 D 3 20 A 4 40 5 6 60 C 7 B co 8 60arrow_forward
- Use ABC analysis to determine the items deserving mostattention and tightest inventory control.arrow_forwardUsing the gross requirements schedule below*, prepare an alternative ordering system that always orders 100 units the week prior to a shortage (a fixed order quantity of 100). What is the cost of this ordering system? D Period 1 2 3 Gross requirements 35 30 40 4 5 6 7 8 9 10 0 10 40 30 0 30 55 *Holding cost = $1/unit/week; setup cost = $100; lead time = 1 week; beginning inventory = 35 units. Prepare a net requirements plan (enter your responses as whole numbers). The holding cost of this ordering system is $ The setup cost of this ordering system is $ The total cost of this ordering system is $ Period Gross requirements On-hand at beginning of period 35 On-hand at end of period Net requirements Order receipt Order release (enter your response as a whole number). (enter your response as a whole number). (enter your response as a whole number). 1 35 2 3 30 40 4 0 7 8 9 10 0 30 55 5 6 10 40 30arrow_forwardM. de Koster, of Rene Enterprises, has the master production plan shown here: Lead time = I period; setup cost= $200; holding cost = $10 perweek; stockout cost = $10 per week. Your job is to develop an ordering plan and costs for:a) Lot-for-lot. b) EOQ.c) POQ. d) Which plan has the lowest cost?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY