Question
Book Icon
Chapter 10, Problem 25P

a)

Summary Introduction

To determine: The normal time for the operation

Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.

a)

Expert Solution
Check Mark

Answer to Problem 25P

Thenormal time calculated as 3.23 minutes.

Explanation of Solution

Given information:

The allowance for tasks is given as 7% for personal, 10% for fatigue, and 3% for delay. The observed time and performance rating for each element is given as follows:

Element Performance rating Observation (minutes per cycle)
1 2 3 4 5
1 110% 0.5 0.4 0.6 0.4 0.4
2 95% 0.6 0.8 0.7 0.6 0.7
3 90% 0.6 0.4 0.7 0.5 0.5
4 85% 1.5 1.8 2 1.7 1.5

Formulae to calculate normal time:

Average time=Observationsn

Normal time=Average time×Performance rating

Calculate the normal time:

Element Performance rating Observation (minutes) Average time Normal time
1 2 3 4 5
1 110% 0.5 0.4 0.6 0.4 0.4 0.46 0.51
2 95% 0.6 0.8 0.7 0.6 0.7 0.68 0.65
3 90% 0.6 0.4 0.7 0.5 0.5 0.54 0.49
4 85% 1.5 1.8 2 1.7 1.5 1.7 1.45

Excel worksheet:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 10, Problem 25P

Calculate the average time for the first element:

Average time=Observationn=0.5+0.4+0.6+0.4+0.45=2.35=0.46 minutes

The average time is calculated by taking an average of the observation given, which is summation of 0.5, 0.4, 0.6, 0.4, and 0.4 and dividing the result by 5. Hence, the average is 0.46 minutes.

Calculate the average time for the second element:

Average time=Observationn=0.6+0.8+0.7+0.6+0.75=3.45=0.68 minutes

The average time is calculated by taking an average of the observation given, which is summation of 0.6, 0.8, 0.7, 0.6, and 0.7 and dividing the result by 5. Hence, the average is 0.68 minutes.

Calculate the average time for the third element:

The average time is calculated by taking an average of the observation given, which is summation of 0.6, 0.4, 0.7 0.5, and 0.5 and dividing the result by 5. Hence, the average is 0.54 minutes.

Average time=Observationn=0.6+0.4+0.7+0.5+0.55=2.75=0.54 minutes

Calculate the average time for the fourth element:

The average time is calculated by taking an average of the observation given, which is summation of 1.5, 1.8, 2.0, 1.7, and 1.5 and dividing the result by 5. Hence, the average is 1.7 minutes.

Average time=Observationn=1.5+1.8+2.0+1.7+1.55=8.55=1.7 minutes

Calculate the normal time for the first element:

The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.46 minutes, and performance rating is given as 110%. Hence, the normal time is 0.51 minutes.

Normal time=Average time×Performance rating=0.46×110%=0.46×1.1=0.51 minutes

Calculate the normal time for the second element:

The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.68 minutes, and performance rating is given as 95%. Hence, the normal time is 0.65 minutes.

Normal time=Average time×Performance rating=0.68×95%=0.68×1.05=0.65 minutes

Calculate the normal time for the third element:

The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.54 minutes, and performance rating is given as 90%. Hence, the normal time is 0.49 minutes.

Normal time=Average time×Performance rating=0.54×90%=0.54×0.90=0.49 minutes

Calculate the normal time for the fourth element:

The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 1.7 minutes, and performance rating is given as 85%. Hence, the normal time is 1.45 minutes.

Normal time=Average time×Performance rating=1.7×85%=1.7×0.85=1.45 minutes

Calculate the total normal time:

The normal time is calculated by adding the normal time of all the elements.

Normal time=Sum of normal times=0.51+0.65+0.49+1.45=3.08 minutes

Hence, the total normal time is 3.08 minutes.

b)

Summary Introduction

To determine: The standard time for the operation.

Introduction: Time study is the basis that helps set the standard time, it would time a sample of the performance of the worker.

b)

Expert Solution
Check Mark

Answer to Problem 25P

Thestandard time is calculated as 5.4 minutes.

Explanation of Solution

Given information:

The allowance for tasks is given as 7% for personal, 10% for fatigue, and 3% for delay. The observed time and performance rating for each element are given as follows:

Element Performance rating Observation (minutes per cycle)
1 2 3 4 5
1 110% 0.5 0.4 0.6 0.4 0.4
2 95% 0.6 0.8 0.7 0.6 0.7
3 90% 0.6 0.4 0.7 0.5 0.5
4 85% 1.5 1.8 2 1.7 1.5

Formulae to calculate standard time:

Allowance factor=Personal+Fatigue+Delay

Standard time=Normal time1Allowance factor

Calculate the allowance factor:

The allowance factor is calculated by adding personal allowance, fatigue, and delay allowance. Personal allowance is given as 7%, fatigue is 10%, and delay allowance is 3%. Hence, the allowance factor is 20%.

Allowance factor=Personal+Fatigue+Delay=7%+10%+3%=20%

Calculate the standard time:

The standard time is calculated by dividing the normal time with the value attained by subtracting the allowance factor from 1. The normal time is calculated as 3.08 minutes and the allowance factor is calculated as 20%

Standard time=Normal time1Allowance factor=3.08 minutes10.20=3.08 minutes0.80=3.85 minutes

Hence, the standard time is 3.85 minutes.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
What is Bitcoin? How important is it to businesses and individuals? How does it cause environmental damage and is that damage worth continued uses of Bitcoin? Read the following articles to help answer these questions: United Nations University. (2023, October 24). UN study reveals the hidden environmental impacts of bitcoin: Carbon is not the only harmful by-product. https://unu.edu/press-release/un-study-reveals-hidden-environmental-impacts-bitcoin-carbon-not-only-harmful-product#:~:text=Bitcoin%2C%20the%20most%20popular%20cryptocurrency,the%20worldwide%20Bitcoin%20mining%20network. Salam, E. (2023, April 26). Bitcoin is terrible for the environment – can it ever go green? The Guardian. https://www.theguardian.com/technology/2023/apr/26/bitcoin-mining-climate-crisis-environmental-impact
419 X .com/courses/1546/assignments/49499?module_item_id=111573 Unlimited Attempts Allowed ✓ Details Directions: Record a video of yourself giving a business presentation. Imagine you are tasked with researching a professional development topic on business communication for 40 coworkers. You are then expected to give a 4 - 5 minute presentation on the topic. Choose any topic related to business communication, such as intercultural communication, effective leadership, professional writing, etc. Research the topic and prepare a 4 - 5 minute presentation that could be given over video conference call (such as Zoom). You may use visual aids if you choose. Upload a video file of your presentation. Provide all needed citations. Requirements: 4-5 minutes long Contains visual and audio Create your own work; do not plagiarize Cite your sources using APA citations Choose a submission type T
acts Container chips (s 150 cussion: Conflict X + e.com/courses/1546/discussion_topics/15722?module_item_id=111559 24 Winter > Discussions > Week 8 Discussion: Conflict 时☆ 26 Replies, 26 Unread Week 8 Discussion: Conflict Write a 200 - 300 word discussion post based on the prompt below. Reply to at least one other student in 50 - 100 words. Can you think of a time when a conflict led to a new opportunity, better understanding, or other positive result? If not, think of a past conflict and imagine a positive outcome. Discuss the impact of this conflict on your workplace relationships, productivity, and innovation. Source: Business Communication for Success. (2015). University of Minnesota Libraries Publishing. Attribution-NonCommerical-ShareAlike. Edit View Insert Format Tools Table 12ptv Paragraph BIUA T2
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Foundations of Business - Standalone book (MindTa...
Marketing
ISBN:9781285193946
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,