To determine: The standard time for the operation
Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.
Answer to Problem 22P
Thestandard time is calculated as 10.12 minutes.
Explanation of Solution
Given information:
The allowance factor is given as 10%. The observed time and performance rating for each element is given as follows:
Element | Performance rating | Observation (minutes per cycle) | ||||
1 | 2 | 3 | 4 | 5 | ||
Check mini-bar | 100 | 1.5 | 1.6 | 1.4 | 1.5 | 1.5 |
Make one bed | 90 | 2.3 | 2.5 | 2.1 | 2.2 | 2.4 |
Vacuum floor | 120 | 1.7 | 1.9 | 1.9 | 1.4 | 1.6 |
Clean bath | 100 | 3.5 | 3.6 | 3.6 | 3.6 | 3.2 |
Formulae to calculate the standard time:
Calculate the standard time:
Element | Performance rating | Observation (minutes per cycle) | Average time | Normal time | ||||
1 | 2 | 3 | 4 | 5 | ||||
Check mini-bar | 100% | 1.5 | 1.6 | 1.4 | 1.5 | 1.5 | 1.5 | 1.5 |
Make one bed | 90% | 2.3 | 2.5 | 2.1 | 2.2 | 2.4 | 2.3 | 2.07 |
Vacuum floor | 120% | 1.7 | 1.9 | 1.9 | 1.4 | 1.6 | 1.7 | 2.04 |
Clean bath | 100% | 3.5 | 3.6 | 3.6 | 3.6 | 3.2 | 3.5 | 3.5 |
Total | 9.11 |
Excel worksheet:
Calculate the average time to check mini-bar:
The average time is calculated by taking an average of the observation given, which is a summation of 1.5, 1.6, 1.4, 1.5, and 1.5 and dividing the result by 5. Hence, the average is 1.5 minutes.
Calculate the average time to make one bed:
The average time is calculated by taking an average of the observation given, which is summation of 2.3, 2.5, 2.1, 2.2, and 2.4 and dividing the result by 5. Hence, the average is 2.3 minutes.
Calculate the average time to vacuum floor:
The average time is calculated by taking an average of the observation given, which is summation of 1.7, 1.9, 1.9, 1.4, and 1.6 and dividing the result by 5. Hence, the average is 1.7 minutes.
Calculate the average time to clean bath:
The normal average time is calculated by taking an average of the observation given, which is summation of 3.5, 3.6, 3.6, 3.6, and 3.2 and dividing the result by 5. Hence, the average is 3.5 minutes.
Calculate the normal time to check mini-bar:
The normal time is calculated by multiplying average time and performance rating. The average time is given as 1.5 minutes, and performance rating is given as 100%. Hence, the normal time is 1.5 minutes.
Calculate the normal time to make one bed:
The normal time is calculated by multiplying average time and performance rating. The average time is given as 2.3 minutes, and performance rating is given as 90%. Hence, the normal time is 2.07 minutes.
Calculate the normal time to vacuum floor:
The normal time is calculated by multiplying average time and performance rating. The average time is given as 1.7 minutes, and performance rating is given as 120%. Hence, the normal time is 2.04 minutes.
Calculate the normal time to clean bath:
The normal time is calculated by multiplying average time and performance rating. The average time is given as 3.5 minutes, and performance rating is given as 100%. Hence, the normal time is 3.5 minutes.
Calculate the total normal time:
The normal time is calculate by adding the normal time to check the mini-bar, make one bed, vacuum floor, and clean bath.
Hence, the total normal time is 9.11 minutes.
Calculate the standard time:
The standard time is calculated by dividing the normal time with the value attained by subtracting the allowance factor from 1. Normal time is calculated as 9.11 minutes and the allowance factor is calculated as 0.10 or 10%.
Hence, the standard time is 10.12 minutes.
Want to see more full solutions like this?
Chapter 10 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- Latisha Simmons, a loan processor at Wentworth Bank, has been timed performing four work elements, with the results shown in the following table. Task Element 1 2 3 4 Performance Rating 110% 85% 90% 85% 1 0.6 0.6 0.5 1.4 Observation (minutes per cycle) 2 3 4 0.3 0.8 0.5 1.9 0.6 0.7 0.6 1.9 0.4 0.6 0.5 1.7 The allowances for tasks such as this are personal, 8%; fatigue, 12%; and delay, 3%. minutes (round your response to two a) The normal time for the complete operation : = decimal places). b) The standard time for this process = minutes (round your response to two decimal places). 0.5 0.8 0.5 1.4arrow_forwardDescribe some of the limitations of time study method ?arrow_forwardUse the data in the table below to answer questions 1 to 3. Observation 1 2 3 4 5 6 7 8 Time (seconds) 17 18 15 14 13 15 16 2 1. Using the data above, calculate the observed time for the task. 2. If the person observed worked at a pace that is 80% of normal, what should be the normal timefor this task? 3. If the person observed worked at a pace that is 80% of normal, and if the appropriate allowance for this task is 25% of job time, what should be the standard time?arrow_forward
- TOYS AND JOB DESIGN AT THE HOVEY AND BEARD COMPANY The following is a situation that occurred in the Hovey and Beard Company, as reported by J. V. Clark. This company manufactured a line of wooden toys. One part of the process involved spray painting partially assembled toys, after which the toys were hung on moving hooks that carried them through a drying oven. The operation, staffed entirely by women, was plagued with absenteeism, high turnover, and low morale. Each woman at her paint booth would take a toy from the tray beside her, position it in a fixture, and spray on the color according to the required pattern. She then would release the toy and hang it on the conveyor hook. The rate at which the hooks moved had been calculated so that each woman, once fully trained, would be able to hang a painted toy on each hook before it passed beyond her reach. The women who worked in the paint room were on a group incentive plan that tied their earnings to the…arrow_forwardBased on a careful work study in the Hofstetter Corp., the results shown in the following table have been observed: a) Compute the normal time for each work element.b) If the allowance for this type of work is 15%, what is the standard time?c) How many observations are needed for a 95% confidence level within ±5% accuracy? (Hint: Calculate the sample size of each element.)arrow_forwardK Latisha Simmons, a loan processor at Wentworth Bank, has been timed performing four work elements, with the results shown in the following table. Task Element 1 2 3 4 Performance Rating 115% 95% 85% 80% 1 0.5 0.6 0.7 1.6 Observation (minutes per cycle) 2 3 4 0.4 0.9 0.4 1.9 0.5 0.7 0.6 2.1 0.3 0.6 0.4 1.7 5 0.3 0.7 0.4 1.5 The allowances for tasks such as this are personal, 8%; fatigue, 10%; and delay, 2%. a) The normal time for the complete operation = minutes (round your response to two decimal places). b) The standard time for this process = minutes (round your response to two decimal places).arrow_forward
- After training, Mary Fernandez, a computer tech-nician, had an average observed time for memory-chip tests of 12 seconds. Mary’s performance rating is 100%. The firm has apersonal fatigue and delay allowance of 15%.a) Find the normal time for this process.b) Find the standard time for this process.arrow_forwardDescribe the job design to specify the work material and methods?arrow_forwardThe owner of Kat Motel wants to develop a time standard for the task of cleaning a cat cage. In a preliminary study, she observed one of her workers perform this task six times, with the following results: Observation 1 2 3 4 5 6 Time (seconds) 52.7 70 53.3 90.3 80.6 86.7 If the employee performance rating is 1.50, what is the standard time for this task with an allowance of 20 percent of job time is used? seconds.arrow_forward
- A worker-machine operation was found to involve 3.3 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The worker's time-averaged 1.9 minutes per cycle, and the worker was given a rating of 120% (machine rating is 100%). Midway through the study, the worker took a 10-minute rest break. Assuming an allowance factor of 12% of work time, determine the standard time for this job. Hints: you should consider both machine time and machine time together. Also, Allowance only applies to the man, not a machine.arrow_forwardWhat is the significance of work measurements and time standards to a business? Are there any drawbacks to putting these standards in place?arrow_forwardPeter Rourke, a loan processor a t Wentworth Bank,has been timed performing four work elements, with the resultsshown in the fo llowing table. The allowances for tasks such asth is are personal, 7%; fa tigue, 10%; and delay, 3%. a) What is the normal time?b) What is the standard time?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.