In one of the construction projects, a bulldozer is used for a weekly rent of $150, with a work rate of 10 hours per day, 50 minutes per hour, and 6 days per week. If you know that the dimensions of the bulldozer blade are 3 lengths and 1 m height, the slope of the pushed soil is (1:1), its speed when loaded is 45 m/min and when returning is 80 m/min, and the time for loading, unloading, and changing is 0.35 minutes, the transported soil is sandy, weighing 1650 kg/m³ by Bank volume and 1300 kg/m3 by loose volume, the transport distance is 300 m. If you know that using a tractor shovel costs $0.5 per m³, make a decision about choosing the economical equipment to use in the project.
In one of the construction projects, a bulldozer is used for a weekly rent of $150, with a work rate of 10 hours per day, 50 minutes per hour, and 6 days per week. If you know that the dimensions of the bulldozer blade are 3 lengths and 1 m height, the slope of the pushed soil is (1:1), its speed when loaded is 45 m/min and when returning is 80 m/min, and the time for loading, unloading, and changing is 0.35 minutes, the transported soil is sandy, weighing 1650 kg/m³ by Bank volume and 1300 kg/m3 by loose volume, the transport distance is 300 m. If you know that using a tractor shovel costs $0.5 per m³, make a decision about choosing the economical equipment to use in the project.
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter10: Pricing Excavation And Backfill
Section: Chapter Questions
Problem 7RQ
Related questions
Question
subject

Transcribed Image Text:In one of the construction projects, a bulldozer is used for a weekly rent of $150,
with a work rate of 10 hours per day, 50 minutes per hour, and 6 days per week. If
you know that the dimensions of the bulldozer blade are 3 lengths and 1 m height,
the slope of the pushed soil is (1:1), its speed when loaded is 45 m/min and when
returning is 80 m/min, and the time for loading, unloading, and changing is 0.35
minutes, the transported soil is sandy, weighing 1650 kg/m³ by Bank volume and
1300 kg/m3 by loose volume, the transport distance is 300 m.
If you know that using a tractor shovel costs $0.5 per m³, make a decision about
choosing the economical equipment to use in the project.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 3 images

Recommended textbooks for you

Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,

Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,

Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning

Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning