Green Capital, Inc. (GC) is a small investment banking firm that specializes in securing funds for small to medium sized firms. GC is able to use a standardized project format for each engagement. Beth Bobby has been assigned to this client as project manager partner and has compiled the network information and activity times for the latest client. Activity 1 2 23 3 4 5 6 7 8 9 10 11 12 13 14 15 Predecessor 1 1 5 6,7 2 3 4 8 11 9, 12 10, 12, 14 Table 1 Optimistic (week) 16 30 60 18 17 4 12 6 18 20 40 11 12 11 0 Most Likely (week) 19 30 72 27 29 7 15 12 27 35 55 20 21 14 0 Pessimistic (week) 28 30 90 30 47 10 18 24 30 50 100 29 24 17 0

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%
Green Capital, Inc. (GC) is a small investment banking firm that specializes in securing funds
for small to medium sized firms. GC is able to use a standardized project format for each
engagement. Beth Bobby has been assigned to this client as project manager partner and
has compiled the network information and activity times for the latest client.
Activity
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Predecessor
1
5
6,7
2
3
4
8
11
9, 12
10, 12, 14
Table 1
Optimistic (week)
16
30
60
18
17
4
12
6
18
20
40
11
12
11
0
Most Likely (week)
19
30
72
27
29
7
15
12
27
35
55
20
21
14
0
Pessimistic (week)
28
30
90
30
47
10
18
24
30
50
100
29
24
17
0
Transcribed Image Text:Green Capital, Inc. (GC) is a small investment banking firm that specializes in securing funds for small to medium sized firms. GC is able to use a standardized project format for each engagement. Beth Bobby has been assigned to this client as project manager partner and has compiled the network information and activity times for the latest client. Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Predecessor 1 5 6,7 2 3 4 8 11 9, 12 10, 12, 14 Table 1 Optimistic (week) 16 30 60 18 17 4 12 6 18 20 40 11 12 11 0 Most Likely (week) 19 30 72 27 29 7 15 12 27 35 55 20 21 14 0 Pessimistic (week) 28 30 90 30 47 10 18 24 30 50 100 29 24 17 0
4. Construct a Gantt chart to represent the various activities of the project with a date.
The project is planning to start on 2nd January 2023, Monday. You can use any Free
Gantt chart template online.
a.
Explain the working day/hour and not working day of your company. Example
working day - Monday until Saturday 5pm and off day are Sunday & Public
Holiday.
Example of the Gantt chart view;
ID Duration
1 2 days
15 days
2
3 10 days
4
5
6
13 days
18 days
15 days
b. What are the completion date of the project and the new duration of the
project? Use the year 2023 Malaysia calendar as your reference. Your
submission must be at least a similar view from the example below.
7 10 days
8
5 days
Task Name
Order review
Order vendor parts
Produce other standard parts
Design custom parts
Software development
Manufacture custom hardware
Assemble
Test
Start
Tue 1/1
Thu 1/3
Thu 1/3
Thu 13
Thu 1/3
Wed 1/16
Thu 1/31
Sun 2/10
Finish
Wed 1/2
Thu 1/17
Sat 1/12
Tue 1/15
Sun 1/20
Wed 1/30
Sat 2/9
Thu 2/14
Late Start
Tue 1/1
Wed 1/16
Mon 1/21
Thu 1/3
Wed 1/23
Wed 1/16
Thu 1/31
Sun 2/10
Late Finish
Wed 1/2
Wed 1/30
Wed 1/30
Tue 1/15
Sat 2/9
Wed 1/30
Sat 2/9
Thu 2/14
1st Half
Free Slack Total Slack 12/23/12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17
0 days
13 days
18 days
0 days
20 days
0 days
0 days
0 days
0 days
13 days
18 days
0 days
20 days
0 days
0 days
0 days
1.
Transcribed Image Text:4. Construct a Gantt chart to represent the various activities of the project with a date. The project is planning to start on 2nd January 2023, Monday. You can use any Free Gantt chart template online. a. Explain the working day/hour and not working day of your company. Example working day - Monday until Saturday 5pm and off day are Sunday & Public Holiday. Example of the Gantt chart view; ID Duration 1 2 days 15 days 2 3 10 days 4 5 6 13 days 18 days 15 days b. What are the completion date of the project and the new duration of the project? Use the year 2023 Malaysia calendar as your reference. Your submission must be at least a similar view from the example below. 7 10 days 8 5 days Task Name Order review Order vendor parts Produce other standard parts Design custom parts Software development Manufacture custom hardware Assemble Test Start Tue 1/1 Thu 1/3 Thu 1/3 Thu 13 Thu 1/3 Wed 1/16 Thu 1/31 Sun 2/10 Finish Wed 1/2 Thu 1/17 Sat 1/12 Tue 1/15 Sun 1/20 Wed 1/30 Sat 2/9 Thu 2/14 Late Start Tue 1/1 Wed 1/16 Mon 1/21 Thu 1/3 Wed 1/23 Wed 1/16 Thu 1/31 Sun 2/10 Late Finish Wed 1/2 Wed 1/30 Wed 1/30 Tue 1/15 Sat 2/9 Wed 1/30 Sat 2/9 Thu 2/14 1st Half Free Slack Total Slack 12/23/12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 0 days 13 days 18 days 0 days 20 days 0 days 0 days 0 days 0 days 13 days 18 days 0 days 20 days 0 days 0 days 0 days 1.
Expert Solution
steps

Step by step

Solved in 5 steps with 7 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.