A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 60% complete. The planners were only expecting to be 50% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,420,000 and it was done for only $1,300,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,500,000 but was actually done for $9,000,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,500,000. To date they have spent $5,000,000 on the superstructure. Calculate the schedule variance, schedule performance index, and cost index for the project to date. How is the project going

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 60% complete. The planners were only expecting to be 50% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,420,000 and it was done for only $1,300,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,500,000 but was actually done for $9,000,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,500,000. To date they have spent $5,000,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost index for the project to date. How is the project going?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.