Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)
A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were expecting to be only54% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,419,000 and it was done for only $1,299,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,499,000 but was actually done for $8,999,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,499,000. To date, they have spent $4,999,000 on the superstructure.
Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)


Trending now
This is a popular solution!
Step by step
Solved in 4 steps










