given the following information for a 1-year project, answer the following questions. Assume you have actual and earned value data at the end of the second month. Recall that PV is the plan value, Evie is the earned value, AC is the actual cost, and BAC is the budget at completion. pv =$ 23,000 ev = 20,000 ac= 25,000 bac = 130,000 a. what is the cost variance, schedule variance, cost performance index CPI and schedule performance index SPI for the project? B. how is the project progressing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? C. use the CPI to calculate the estimate at completion EAC for this project. d. use the SPI to estimate how long it will take to finish this project.
given the following information for a 1-year project, answer the following questions. Assume you have actual and earned value data at the end of the second month. Recall that PV is the plan value, Evie is the earned value, AC is the actual cost, and BAC is the budget at completion.
pv =$ 23,000
ev = 20,000
ac= 25,000
bac = 130,000
a. what is the cost variance,
B. how is the project progressing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
C. use the CPI to calculate the estimate at completion EAC for this project.
d. use the SPI to estimate how long it will take to finish this project.
e. sketch the earned value chart for this project, use the figure below as a guide. Assume the data for month one is half of the values given for Pv, Ev and ac at the end of month 2