Solve the following project by hand and submit your notes: Activity Normal Time Crash Time Normal Cost Crash Cost Immediate (weeks) (weeks) Predecessor $2,000 $2,200 $500 $2,300 $900 $3,000 $1,400 $2,100 $2,800 $500 A 4. 3 2 3 3 $2,600 $1,200 $4,200 D 8. 6 A 3 B 4 2 $2,000 E, F How long will the project take? What is the total cost to complete the project in normal time? If the project is to be shortened by 1-week, which activity will be reduced and how much will the cost be increased? What is the maximum time that the project can be crashed? How much will the cost increase if it is crashed the maximum?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Show all work

Solve the following project by hand and submit your notes:
Activity
Normal Time
Crash Time
Normal Cost
Crash Cost
Immediate
(weeks)
(weeks)
Predecessor
$2,000
$2,200
$500
$2,300
$900
$3,000
$1,400
$2,100
$2,800
$500
$2,600
$1,200
$4,200
$2,000
A
3
B
2
3
3
8
6
A
E
6
3
В
F
3
G
4
2
Е, F
How long will the project take?
What is the total cost to complete the project in normal time?
If the project is to be shortened by 1-week, which activity will be reduced and how much will the cost be increased?
What is the maximum time that the project can be crashed? How much will the cost increase if it is crashed the maximum?
Transcribed Image Text:Solve the following project by hand and submit your notes: Activity Normal Time Crash Time Normal Cost Crash Cost Immediate (weeks) (weeks) Predecessor $2,000 $2,200 $500 $2,300 $900 $3,000 $1,400 $2,100 $2,800 $500 $2,600 $1,200 $4,200 $2,000 A 3 B 2 3 3 8 6 A E 6 3 В F 3 G 4 2 Е, F How long will the project take? What is the total cost to complete the project in normal time? If the project is to be shortened by 1-week, which activity will be reduced and how much will the cost be increased? What is the maximum time that the project can be crashed? How much will the cost increase if it is crashed the maximum?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Management theories
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.