A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were expecting to be only57% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,427,000 and it was done for only $1,307,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,507,000 but was actually done for $9,007,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,507,000. To date, they have spent $5,007,000 on the superstructure. Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.) Schedule variance Schedule performance index Cost performance index

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem
very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70%
complete. The planners were expecting to be only57% through the third activity at this time. The first activity involves prepping the site
for the bridge. It was expected that this would cost $1,427,000 and it was done for only $1,307,000. The second activity was the
pouring of concrete for the bridge. This was expected to cost $10,507,000 but was actually done for $9,007,000. The third and final
activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,507,000. To date, they have
spent $5,007,000 on the superstructure.
be running
Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your
"performance index" values to 3 decimal places.)
Schedule variance
Schedule performance index
Cost performance index
Transcribed Image Text:A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were expecting to be only57% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,427,000 and it was done for only $1,307,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,507,000 but was actually done for $9,007,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,507,000. To date, they have spent $5,007,000 on the superstructure. be running Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.) Schedule variance Schedule performance index Cost performance index
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.