5. A crawler hoe having a 3-cy bucket and whose cost per hour, including the wages to an operator, is $86, will excavate and load haul units under each of the stated conditions. The maximum digging depth of the machine is 25 ft. Determine the cost per bank cubic yard for each condition. Condition (1) (2) (3) (4) Material Sandy clay Hard clay Rock, well blasted Sand and gravel Depth of excavation (ft) Angle of swing (degrees) 10 60 88 18 15 20 90 90 00 150 Percent swell Efficiency factor (min-hr) 45 50 24 20 50 50 55 35 13

Principles of Foundation Engineering (MindTap Course List)
9th Edition
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter12: Pile Foundations
Section: Chapter Questions
Problem 12.13P: A concrete pile 16 in. 16 in. in cross section is shown in Figure P12.13. Calculate the ultimate...
icon
Related questions
Question
100%
5. A crawler hoe having a 3-cy bucket and whose cost per hour, including the wages to an
operator, is $86, will excavate and load haul units under each of the stated conditions.
The maximum digging depth of the machine is 25 ft. Determine the cost per bank cubic
yard for each condition.
Condition
(1)
(2)
(3)
(4)
Material
Sandy clay
Hard clay
Rock, well
blasted
Sand and gravel
Depth of excavation (ft)
Angle of swing (degrees)
10
60
88
18
15
20
90
90
00
150
Percent swell
Efficiency factor (min-hr) 45
50
24
20
50
50
55
35
13
Transcribed Image Text:5. A crawler hoe having a 3-cy bucket and whose cost per hour, including the wages to an operator, is $86, will excavate and load haul units under each of the stated conditions. The maximum digging depth of the machine is 25 ft. Determine the cost per bank cubic yard for each condition. Condition (1) (2) (3) (4) Material Sandy clay Hard clay Rock, well blasted Sand and gravel Depth of excavation (ft) Angle of swing (degrees) 10 60 88 18 15 20 90 90 00 150 Percent swell Efficiency factor (min-hr) 45 50 24 20 50 50 55 35 13
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Geotechnical Engineering (MindTap…
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Construction Materials, Methods and Techniques (M…
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning