1. A project has been defined to contain the following list of activities along with their required times for completion. Activity No. Activity Time (Weeks) Immediate Predecessors 1 Collect requirements 2 2 Analyze processes 3 3 Analyze data 3 2 4 Design processes 7 2 Design data 2 6 Design screens 1 3,4 7 Design reports 4,5 8 Program 6,7 9 Test and document 8 7 10 Install 2 8,9 a. Draw a network diagram for the activities. b. Calculate the earliest expected completion time. c. Show the critical path. d. What would happen if activity 6 were revised to take 6 weeks instead of 1 week?

Understanding Business
12th Edition
ISBN:9781259929434
Author:William Nickels
Publisher:William Nickels
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
icon
Related questions
Question

1, 2, 4 (first part)

Chapter Exercises
1. A project has been defined to contain the following list of activities along with their required times for completion.
Activity No.
Activity
Time (Weeks)
Immediate Predecessors
1
Collect requirements
2
2
Analyze processes
3
1
3
Analyze data
3
2
4
Design processes
7
2
Design data
6
2
6
Design screens
1
3,4
7
Design reports
4,5
8
Program
4
6,7
9
Test and document
8
7
10
Install
2
8,9
a. Draw a network diagram for the activities.
b. Calculate the earliest expected completion time.
c. Show the critical path.
d. What would happen if activity 6 were revised to take 6 weeks instead of 1 week?
2. Construct a Gantt chart for the project defined in Problem 1.
3. Look again at the activities outlined in Problem 1. Assume that during the first week of the project your team discovers that the activity duration estimates were all wrong. Rather than
3 weeks, Activity 2 will take only two weeks to complete, whereas both Activities 4 and 7 will take three times longer than originally estimated. Further, all other activities will take
twice as much time to complete. In addition, your team has noticed that additional training is needed. This new activity, number 11, will take one week to complete, and depends on
the completion of Activities 10 and 9. Create a new network diagram representing the new earliest expected completion times.
4. Using the web, find one example each of a functional, matrix, and project-oriented organization Prepa mi
argensations
beutte simiatr and a eICeS of these
Transcribed Image Text:Chapter Exercises 1. A project has been defined to contain the following list of activities along with their required times for completion. Activity No. Activity Time (Weeks) Immediate Predecessors 1 Collect requirements 2 2 Analyze processes 3 1 3 Analyze data 3 2 4 Design processes 7 2 Design data 6 2 6 Design screens 1 3,4 7 Design reports 4,5 8 Program 4 6,7 9 Test and document 8 7 10 Install 2 8,9 a. Draw a network diagram for the activities. b. Calculate the earliest expected completion time. c. Show the critical path. d. What would happen if activity 6 were revised to take 6 weeks instead of 1 week? 2. Construct a Gantt chart for the project defined in Problem 1. 3. Look again at the activities outlined in Problem 1. Assume that during the first week of the project your team discovers that the activity duration estimates were all wrong. Rather than 3 weeks, Activity 2 will take only two weeks to complete, whereas both Activities 4 and 7 will take three times longer than originally estimated. Further, all other activities will take twice as much time to complete. In addition, your team has noticed that additional training is needed. This new activity, number 11, will take one week to complete, and depends on the completion of Activities 10 and 9. Create a new network diagram representing the new earliest expected completion times. 4. Using the web, find one example each of a functional, matrix, and project-oriented organization Prepa mi argensations beutte simiatr and a eICeS of these
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 8 images

Blurred answer
Knowledge Booster
Introduction to Business presentation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Understanding Business
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
Management (14th Edition)
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract…
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
Management Information Systems: Managing The Digi…
Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON
Business Essentials (12th Edition) (What's New in…
Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON
Fundamentals of Management (10th Edition)
Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON