1. A project has been defined to contain the following list of activities along with their required times for completion. Activity No. Activity Time (Weeks) Immediate Predecessors 1 Collect requirements 2 2 Analyze processes 3 3 Analyze data 3 2 4 Design processes 7 2 Design data 2 6 Design screens 1 3,4 7 Design reports 4,5 8 Program 6,7 9 Test and document 8 7 10 Install 2 8,9 a. Draw a network diagram for the activities. b. Calculate the earliest expected completion time. c. Show the critical path. d. What would happen if activity 6 were revised to take 6 weeks instead of 1 week?
1. A project has been defined to contain the following list of activities along with their required times for completion. Activity No. Activity Time (Weeks) Immediate Predecessors 1 Collect requirements 2 2 Analyze processes 3 3 Analyze data 3 2 4 Design processes 7 2 Design data 2 6 Design screens 1 3,4 7 Design reports 4,5 8 Program 6,7 9 Test and document 8 7 10 Install 2 8,9 a. Draw a network diagram for the activities. b. Calculate the earliest expected completion time. c. Show the critical path. d. What would happen if activity 6 were revised to take 6 weeks instead of 1 week?
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
Related questions
Question
1, 2, 4 (first part)

Transcribed Image Text:Chapter Exercises
1. A project has been defined to contain the following list of activities along with their required times for completion.
Activity No.
Activity
Time (Weeks)
Immediate Predecessors
1
Collect requirements
2
2
Analyze processes
3
1
3
Analyze data
3
2
4
Design processes
7
2
Design data
6
2
6
Design screens
1
3,4
7
Design reports
4,5
8
Program
4
6,7
9
Test and document
8
7
10
Install
2
8,9
a. Draw a network diagram for the activities.
b. Calculate the earliest expected completion time.
c. Show the critical path.
d. What would happen if activity 6 were revised to take 6 weeks instead of 1 week?
2. Construct a Gantt chart for the project defined in Problem 1.
3. Look again at the activities outlined in Problem 1. Assume that during the first week of the project your team discovers that the activity duration estimates were all wrong. Rather than
3 weeks, Activity 2 will take only two weeks to complete, whereas both Activities 4 and 7 will take three times longer than originally estimated. Further, all other activities will take
twice as much time to complete. In addition, your team has noticed that additional training is needed. This new activity, number 11, will take one week to complete, and depends on
the completion of Activities 10 and 9. Create a new network diagram representing the new earliest expected completion times.
4. Using the web, find one example each of a functional, matrix, and project-oriented organization Prepa mi
argensations
beutte simiatr and a eICeS of these
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 8 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Recommended textbooks for you

Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education

Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON

Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning

Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education

Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON

Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning

Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON

Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON

Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON