Illinois Furniture, Inc., produces all types of office furniture. The “Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks:

Chapter 9, Problem 13P, Illinois Furniture, Inc., produces all types of office furniture. The Executive Secretary is a chair

a) Draw a precedence diagram of this operation.

b) What is the cycle time for this operation?

c) What is the theoretical minimum number of workstations?

d) Assign tasks to workstations.

e) What is the idle time per cycle?

f) How much total idle time is present in an 8-hour shift?

g) What is the efficiency of the assembly line, given your answer in (d)?

a)

Expert Solution
Check Mark
Summary Introduction

To draw: The precedence diagram.

Answer to Problem 13P

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 13P , additional homework tip  1

Explanation of Solution

Given information:

Task Time (minutes) Immediate predecessors
A 4 -
B 7 -
C 6 A, B
D 5 C
E 6 D
F 7 E
G 8 E
H 6 F, G
Total 49  
  • The chair is sold for $130.
  • Number of minutes available = 480 / day.
  • Average daily demand is 50 chairs.

Precedence diagram:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 13P , additional homework tip  2

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The cycle time.

Introduction:

Cycle time:

Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.

Answer to Problem 13P

The  cycle time is 9.6 minutes / unit.

Explanation of Solution

Given information:

Task Time (minutes) Immediate predecessors
A 4 -
B 7 -
C 6 A, B
D 5 C
E 6 D
F 7 E
G 8 E
H 6 F, G
Total 49  
  • The chair is sold for $130.
  • Number of minutes available = 480 / day.
  • Average daily demand is 50 chairs.

Formula to calculate cycle time:

Cycle time=Number of minutes available per dayAverage daily demand

Calculation of cycle time:

Cycle time=48050=9.6 minutes

The  cycle time is 9.6 minutes / unit.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The theoretical minimum number of workstations.

Answer to Problem 13P

The theoretical minimum number of workstations is 6 workstations.

Explanation of Solution

Given information:

Task Time (minutes) Immediate predecessors
A 4 -
B 7 -
C 6 A, B
D 5 C
E 6 D
F 7 E
G 8 E
H 6 F, G
Total 49  
  • The chair is sold for $130.
  • Number of minutes available = 480 / day.
  • Average daily demand is 50 chairs.

Formula to calculate theoretical minimum number of workstations:

Workstations=Total task timeCycle time

Calculation of theoretical minimum number of workstations:

Workstations=499.6=5.1=6 workstations

The theoretical minimum number of workstations is 6 workstations.

d)

Expert Solution
Check Mark
Summary Introduction

To assign: The different tasks to different workstations.

Explanation of Solution

Assignment of different tasks to different workstations:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 13P , additional homework tip  3

Task A is assigned to station 1. Task B is assigned to station 2. Task C is assigned to station 3. Task D is assigned to station 4. Task E is assigned to station 5. Task G is assigned to station 6. Task F is assigned to station 7. Task H is assigned to station 8.

e)

Expert Solution
Check Mark
Summary Introduction

To determine: The idle time per cycle.

Answer to Problem 13P

The  idle time is 15 minutes / cycle.

Explanation of Solution

Given information:

Task Time (minutes) Immediate predecessors
A 4 -
B 7 -
C 6 A, B
D 5 C
E 6 D
F 7 E
G 8 E
H 6 F, G
Total 49  
  • The chair is sold for $130.
  • Number of minutes available = 480 / day.
  • Average daily demand is 50 chairs.

Calculation of idle time per cycle:

Idle time=4+1+2+3+2+1+2=15 minutes / cycle

The  idle time is 15 minutes / cycle.

f)

Expert Solution
Check Mark
Summary Introduction

To determine: The total idle time present in an 8 hour shift.

Answer to Problem 13P

The  total idle time present in an 8 hour shift is 15 hours.

Explanation of Solution

Given information:

Task Time (minutes) Immediate predecessors
A 4 -
B 7 -
C 6 A, B
D 5 C
E 6 D
F 7 E
G 8 E
H 6 F, G
Total 49  
  • The chair is sold for $130.
  • Number of minutes available = 480 / day.
  • Average daily demand is 50 chairs.

Calculation of total idle time present in an 8 hour shift:

There are 480 minutes available in a day. The longest operation time is 8 minutes. Therefore the number of cycles in a day is given by:

Cycles=Number of minutes / dayLongest operation time=4808=60 cycles

The total idle time is calculated by multiplying the number of cycles with the total idle time per cycle.

Total idle time=15 minutes×60 cycles=900 minutes=15 hours

The total idle time present in an 8 hour shift is 15 hours.

g)

Expert Solution
Check Mark
Summary Introduction

To determine: The efficiency.

Introduction:

Efficiency:

Efficiency is the measure of  what is actually produced as opposed to what can be theoretically produced with the same amount of resources.

Answer to Problem 13P

The efficiency is 76.6%.

Explanation of Solution

Given information:

Task Time (minutes) Immediate predecessors
A 4 -
B 7 -
C 6 A, B
D 5 C
E 6 D
F 7 E
G 8 E
H 6 F, G
Total 49  
  • The chair is sold for $130.
  • Number of minutes available = 480 / day.
  • Average daily demand is 50 chairs.

Formula to calculate efficiency:

Efficiency=Total task timeNumber of workstations×Longest operation time×100

Calculation of efficiency:

Efficiency=498×8×100=4964×100=76.6%

The efficiency is 76.6%

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
CASE STUDY 9-1 Was Robert Eaton a Good Performance Management Leader? R obert Eaton was CEO and chairman of Chrys- ler from 1993 to 1998, replacing Lee Iacocca, who retired after serving in this capacity since 1978. Eaton then served as cochairman of the newly merged DaimlerChrysler organization from 1998 to 2000. In fact, Eaton was responsible for the sale of Chrysler Corporation to Daimler-Benz, thereby creating DaimlerChrysler. With 362,100 employees, DaimlerChrysler had achieved revenues of €136.4 billion in 2003. DaimlerChrysler's passenger car brands included Maybach, Mercedes-Benz, Chrysler, Jeep, Dodge, and Smart. Commercial vehicle brands included Mercedes-Benz, Freightliner, Sterling, Western Star, and Setra. From the beginning of his tenure as CEO, Eaton communicated with the people under him. He immediately shared his plans for the future with his top four executives, and upon the advice of his colleague, Bob Lutz, decided to look around the company before making any hasty…
Critically assess Martin’s coaching style.
Compare Robert Eaton’s performance management leadership presented in the case against the performance management leadership principles, functions, and behaviors.  What recommendations can be made about what he might do more effectively?  Explain and defend your answer.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY