Chapter 9, Problem 23P

a)

Summary Introduction

To determine: The theoretical minimum number of workstations.

a)

Expert Solution
Check Mark

Answer to Problem 23P

The theoretical minimum number of workstations is 5 workstations.

Explanation of Solution

Given information:

Task Time (seconds) Immediate predecessors
A 40 -
B 30 A
C 50 A
D 40 B
E 6 B
F 25 C
G 15 C
H 20 D, E
I 18 F, G
J 30 H, I
Total 274  
  • Output is 60 iStars / hour

Calculation of cycle time:

The requirement is to produce 60 iStars / hour. Hence, the cycle time for one iStar will be:

Cycle time=60 iStars / hour60minutes / hour×60 seconds=1×60 seconds=60 seconds / iStar

Formula to calculate theoretical minimum number of workstations:

Workstations=Total task timeCycle time

Calculation of theoretical minimum number of workstations:

Workstations=27460=4.57=5 workstations

The theoretical minimum number of workstations is 5 workstations.

b)

Summary Introduction

To balance: The assembly line.

b)

Expert Solution
Check Mark

Explanation of Solution

Precedence diagram:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 23P

List of most following tasks:

Tasks Following tasks
A 9
B 4
C 4
D 2
E 2
F 2
G 2
H 1
I 1
J 0

Assignment of different tasks to different workstations:

Workstation Elligible tasks Selected tasks Task time (seconds) Available cycle time (seconds) Remarks
1 60
A A 40 20
B,C 20 (Idle time) Cycle time is less than task time
2 60
B, C C 7 50 Tie broken randomnly
B, F, G 10 (Idle time) Cycle time is less than task time
3 60
B, F, G B 30 30 Task B has most following tasks.
D, E, F, G F 25 24 Tie broken randomnly
D, E, G 1 (Idle time) Cycle time is less than task time
4 60
D, E, G D 40 20 Tie broken randomnly
E, G G 15 5 Tie broken randomnly
E,I 5 (Idle time) Cycle time is less than task time
5 60
E, I E 6 54 Task E has most following tasks.
I, H H 20 34 Tie broken randomnly
I I 18 2 Task I is only elligible task
2 (Idle time)
6 60
J J 30 30 Task J is the remaining task
30 (Idle time)
Workstation Task assigned Idle time
1 A 20
2 C 10
3 B, F 1
4 D, G 5
5 E, H, I 2
6 J 30
Total 68

c)

Summary Introduction

To determine: The actual number of workstations.

c)

Expert Solution
Check Mark

Answer to Problem 23P

The actual number of workstations is 6.

Explanation of Solution

Workstation Task assigned Idle time
1 A 20
2 C 10
3 B, F 1
4 D, G 5
5 E, H, I 2
6 J 30
Total 68

The actual number of workstations is 6.

d)

Summary Introduction

To determine: The efficiency.

Introduction:

Efficiency:

Efficiency is the measure of  what is actually produced as opposed to what can be theoretically produced with the same amount of resources.

d)

Expert Solution
Check Mark

Answer to Problem 23P

The efficiency is 76.11%.

Explanation of Solution

Formula to calculate efficiency:

Efficiency=Total task timeNumber of workstations×Cycle time×100

Calculation of efficiency:

Efficiency=2746×60×100=274,00360=76.11%

The efficiency is 76.11%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
• We Are HIRING Salesforce Developer (2 - 4 Years) @ Cloudodyssey It Solutions Requirement : Appropriate knowledge on Salesforce standard objects Leads, Account, Contacts, Opportunity, Products, Lead process, Sales process, is required. • Hands-on experience in Salesforce Experience Cloud, Sales Cloud and Lightning. • • Hands experience with Salesforce development, administration, system integrations, Lightning Design System, and bug fixes. Experience in configuration, integration, APIs creation, testing and deployment of Salesforce.com functionality. Eloquent verbal and written communication skills. • Familiar with Agile framework. Work Location: Bangalore SUBMIT YOUR CV hello@cloudodyssey.co
Agree or disagree with post On the surface, the numbers in financial statements do present a snapshot of a company's financial position and performance. However, just looking at the raw numbers often doesn't tell the whole story or reveal underlying trends and relationships that are crucial for making informed decisions. Think of it like looking at individual pieces of a puzzle. Each number is a piece, providing some information. But to see the complete picture – the company's overall financial health, its performance over time, how it compares to its peers, and its potential future – you need to assemble those pieces using different analytical tools.  For example: Horizontal analysis helps us understand how specific financial statement items have changed over multiple periods. Is revenue growing? Are expenses increasing at a faster rate than sales? This reveals trends that a single year's numbers wouldn't show. Vertical analysis allows us to see the relative size of each item within…
What can you do in response to an insulting offer?
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Principles of Management
    Management
    ISBN:9780998625768
    Author:OpenStax
    Publisher:OpenStax College
  • Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing