
Concept explainers
The Action Toy Company has decided to manufacture a new train set the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek:
a) Draw a precedence diagram of this operation.
b) Given the demand, what is the cycle time for this operation?
c) What is the theoretical minimum number of workstations?
d) Assign tasks to workstations.
e) How much total idle time a present each cycle?
f) What is the efficiency of the assembly line with five stations? With six stations?
a)

To draw: The precedence diagram.
Answer to Problem 15P
Explanation of Solution
Given information:
Task | Time (seconds) | Immediate predecessors |
A | 20 | - |
B | 30 | A |
C | 15 | A |
D | 15 | A |
E | 10 | B, C |
F | 30 | D, E |
Total | 120 |
- Weekly demand is 4,800 units / 40 hours workweek.
Precedence diagram:
b)

To determine: The cycle time.
Introduction:
Cycle time:
Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.
Answer to Problem 15P
The cycle time is 30 seconds / unit.
Explanation of Solution
Given information:
Task | Time (seconds) | Immediate predecessors |
A | 20 | - |
B | 30 | A |
C | 15 | A |
D | 15 | A |
E | 10 | B, C |
F | 30 | D, E |
Total | 120 |
- Weekly demand is 4,800 units / 40 hours workweek.
Formula to calculate cycle time:
Calculation of cycle time:
The cycle time is 30 seconds / unit.
c)

To determine: The theoretical minimum number of workstations.
Answer to Problem 15P
The theoretical minimum number of workstations is 4 workstations.
Explanation of Solution
Given information:
Task | Time (seconds) | Immediate predecessors |
A | 20 | - |
B | 30 | A |
C | 15 | A |
D | 15 | A |
E | 10 | B, C |
F | 30 | D, E |
Total | 120 |
- Weekly demand is 4,800 units / 40 hours workweek.
- Average daily demand is 50 chairs.
Formula to calculate theoretical minimum number of workstations:
Calculation of theoretical minimum number of workstations:
The theoretical minimum number of workstations is 4 workstations.
d)

To assign: The different tasks to different workstations.
Explanation of Solution
Assignment of different tasks to different workstations:
Workstation | Elligible tasks | Selected tasks | Task time (seconds) | Available cycle time (seconds) | Remarks |
1 | 30 | ||||
A | A | 20 | 10 | Task A is the only elligible ask | |
10 (Idle Time) | No other elligible task is available | ||||
2 | 30 | ||||
B, C, D | B | 30 | 0 | Task B has the highest task time | |
3 | 30 | ||||
C, D | C | 15 | 15 | Task C is assigned | |
D | D | 15 | 0 | Task D is assigned | |
4 | 30 | ||||
E | E | 10 | 20 | Task E is the only elligible task available | |
20 (Idle time) | The available cycle time is less than the task time | ||||
5 | F | F | 30 | 0 | Task F is assigned |
Workstation | Task assigned | Idle time |
1 | A | 10 |
2 | B | 0 |
3 | C, D | 0 |
4 | E | 20 |
5 | F | 0 |
Total | 30 |
e)

To determine: The idle time per cycle.
Answer to Problem 15P
The idle time is 30 seconds / cycle.
Explanation of Solution
Given information:
Task | Time (seconds) | Immediate predecessors |
A | 20 | - |
B | 30 | A |
C | 15 | A |
D | 15 | A |
E | 10 | B, C |
F | 30 | D, E |
Total | 120 |
- Weekly demand is 4,800 units / 40 hours workweek.
- Average daily demand is 50 chairs.
Calculation of idle time per cycle:
The idle time is 30 seconds / cycle.
f)

To determine: The efficiency.
Introduction:
Efficiency:
Efficiency is the measure of what is actually produced as opposed to what can be theoretically produced with the same amount of resources.
Answer to Problem 15P
The efficiency with five and six workstations is 80% and 66.6% respectively.
Explanation of Solution
Given information:
Task | Time (seconds) | Immediate predecessors |
A | 20 | - |
B | 30 | A |
C | 15 | A |
D | 15 | A |
E | 10 | B, C |
F | 30 | D, E |
Total | 120 |
- Weekly demand is 4,800 units / 40 hours workweek.
- Average daily demand is 50 chairs.
Formula to calculate efficiency:
Calculation of efficiency for five workstations:
Calculation of efficiency for six workstations:
The efficiency with five and six workstations is 80% and 66.6% respectively.
Want to see more full solutions like this?
Chapter 9 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- PepsiCo South Africa says the incident where a woman discovered part of a rodent in her loaf of bread, is anisolated occurrence.Durban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and…arrow_forwardThe deaths are included in the discharges; this includes deaths occurring in less than 48 hours and postoperative deaths. Rehabilitation had 362 discharges, 22 deaths, 1<48 hours, 0 Postoperative. what is the gross death rate for the rehabilitation service?arrow_forwardA copy machine is available 24 hours a day. On a typical day, the machine produces 100 jobs. Each job takes about 3 minutes on the machine, 2 minutes of which is processing time and 1 minute is setup time (logging in, defining the job). About 20 percent of the jobs need to be reworked, in which case the setup time and the processing time have to be repeated. The remainder of the time, the equipment is idle. What is the OEE of the equipment?arrow_forward
- How do you think we can keep updating Toyota's ideas as new technologies come out and what customers want keeps changing?arrow_forwardGiven how TPS has helped change things in so many fields, do you think there are parts of it that might be hard to use in areas that aren’t about making things, like in healthcare or services? If so, why do you think that might be?arrow_forwardDo you feel there is anything positive about rework?arrow_forward
- Do you think technology can achieve faster setup times? How would it be implemented in the hospital workforce?arrow_forwardIn your experience or opinion, do you think process changes like organizing workspaces make a bigger difference, or is investing in technology usually the better solution for faster setups?arrow_forwardHave you seen rework done in your business, and what was done to prevent that from occurring again?arrow_forward
- Research a company different than case studies examined and search the internet and find an example of a business that had to rework a process. How was the organization affected to rework a process in order to restore a good flow unit? Did rework hurt a process or improve the organization's operational efficiency? • Note: Include a reference with supportive citations in the discussion reply in your post.arrow_forwardSetup time is very important in affecting a process and the capacity of a process. How do you reduce setup time? Give examples of reducing setup time. Please Provide a referenecearrow_forwardDo you think TPS was successful? If so, how? Are there other companies that have used TPS? If so, give examples. Please provide a referencearrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningManagement, Loose-Leaf VersionManagementISBN:9781305969308Author:Richard L. DaftPublisher:South-Western College Pub


