Textbook Question
Chapter 5, Problem 4E
Firewall Project XT. Using the ‘complexity weighting” scheme shown in Table 5.3 and the function point complexity weight table shown below, estimate the total function point count. Assume historical data suggest five function points equal one person a month and six people can work on the project.
a. What is the estimated project duration?
b. If 20 people are available for the project, what is the estimated project duration?
c. If the project must be completed in six months, how many people will be needed for the project?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Please note that my roll number last digit is: (9). So please answer based on that
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?
Normal
Cost
$800
$200
$600
$750
$1,200
Normal
Crash
Activity Time (days) Time (days)
4
3
8
6
The total cost of crashing the project by 4 days is $
ABCDE
487
355
(Enter your response as a whole number.)
Total Cost
with Crashing Immediate Predecessor(s)
$1,500
$1,650
By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.)
Each Activity Should be
Reduced BY
(days)
Activity
A
B
C
D
E
$1,100
$600
$650
A
C
You are the project manager of the software installationproject in Table 7.12. You would like to find the minimum-costschedule for your project. There is a $1,000-per-week penaltyfor each week the project is delayed beyond week 25. In addi-tion, your project team determined that indirect project costsare $2,500 per week.a. What would be your target completion week?b. How much would you save in total project costs with yourschedule?
Chapter 5 Solutions
PROJECT MANAGEMENT (LOOSELEAF)-W/ACCESS
Ch. 5.1A - How many labor hours should the eighth satellite...Ch. 5.1A - How many labor hours for the whole project of...Ch. 5.1A - What price would you ask for the project? Why?Ch. 5.1A - Midway through the project your design and...Ch. 5.1A - Near the end of the project, Deutsch Telefon AG...Ch. 5 - Why are accurate estimates critical to effective...Ch. 5 - Prob. 2RQCh. 5 - Prob. 3RQCh. 5 - What are the major types of costs? Which costs are...Ch. 5 - Why is it difficult to estimate mega project...
Ch. 5 - Define what a white elephant is in project...Ch. 5 - Calculate the direct cost of labor tor a project...Ch. 5 - Mrs. Tolstoy and her husband, Serge, are planning...Ch. 5 - Exercise Figure 5.1 is a project WBS with cost...Ch. 5 - Firewall Project XT. Using the complexity...Ch. 5 - At this point, what would you do if you were the...Ch. 5 - Prob. 5.1.2CCh. 5 - What estimating techniques should be used for a...Ch. 5 - Assume you are either Mike or Josh; how would you...Ch. 5 - Prob. 5.2.2CCh. 5 - After cost, what other factors should be...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. . Normal Time Crash Time Cost to Crash Immediate Activity (weeks) (weeks) Predecessor(s) (S per week) 300 A 4 None None B 4 50 C 6. 300 250 A E 1 B. C.D D, E 4 200 H. 4 2 200 2. Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) 777arrow_forwardIFS233 Donell Consulting recently completed an IT training platform implementation with a public firm. The project concluded after the completion of a testing, piloting and sign-off from the project stakeholders. Though completed, the project manager was reviewing their notes, in which they listed all the important occurrences that were recorded during various project phases: ● The pilot of the training platform is about to begin, and the COO of the firm has informed the project team that they want an additional 1000 staff trained and included, and the firm will be increasing budget accordingly. The new systems analyst replacement just found an issue with the way in which the training platform is recording information inputted from users. Apparently, it does note read or collate all the metadata produced during user inputs, and only considers metadata that leads to a complete sequence of inputs. This is going to cause issues in how we record the users' activities as the client wants to…arrow_forwardPlease do not give solution in image formate thanku.arrow_forward
- Assuming that project ABC must be completed in seven months, how many people will be needed for this project? Historical data suggest five functional points equals one person a month. Use the "Complexity Weighting" scheme from your textbook and the function point complexity weight table for this project shown below. Number of inputs 10 Number of outputs 20 Number of inquires 10 Number of files 40 Number of interfaces 40 A 30-35 people B 35-40 people 40-45 people 45-50 people Questions Filter (6) A H Rated complexity low Rated complexity average Rated complexity average Rated complexity high Rated complexity higharrow_forwardRandall Systems in considering four projects A, B, C and D that have risks associated with the producing benefits. Based on the information given in the table below, which project is more desirable for the company? Project A Project B Project C Project D EUAW Prob. EUAW Prob. EUAW Prob. EUAW Prob. $2,000 0.2 $3,000 0.1 -$5,000 0.2 $4,000 0.4 $1,500 0.5 -$2,500 0.4 $6,500 0.5 $2,500 0.3 $3,000 0.3 $3,500 0.5 $1,000 0.3 -$2,000 0.3arrow_forwardAngel healthcare Ltd., has 2 investment opportunities, each costing $120000 and each have expected profit as shown below: Years Project "A' Project "B' ($) ($) 1 40000 30000 2 30000 40000 3 20000 35000 4 15000 30000 Year 1 2 3 PVIF @ 10% 0.909 0.826 0.751 4 0.683 Compute NPV & Profitability Index, Suggest which Project to be preffered at 10%cost of capitalarrow_forward
- The table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15. Activity Immediate Predecessor(s) Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A None 2 1 7,000 10,000 B None 2 2 3,000 3,000 C A 3 1 12,000 40,000 D B 3 2 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 3 5,000 15,000 G E 3 2 9,000 18,000 H F, G 8 6 14,000 32,000 Construct a network diagram for the project. What are the project completion time and the total cost under normal conditions? What is the shortest time duration for this project regardless of cost? What is the resulting total cost? What is the…arrow_forwardThe table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Normal Time Crash Time Activity (weeks) (weeks) Cost to Crash ($ per week) Immediate Predecessor(s) A 5 4 200 B 9 8 300 None None C 4 2 200 A 4 2 250 A E 3 3 B F 3 3 C, D G 3 1 150 D, E 6 4 350 F G 7 4 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Activity A Time according to schedule (weeks) Activity Time according to schedule (weeks) F G B C D Earrow_forwardplease answer both the questions in details also why other option is wrong. make sure both the questions are answered else i will give negative. please solve within 30 minutes. its urgent.arrow_forward
- You are the project manager of the software installation project in Table. You would like to find the minimum- cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week. a. What would be your target completion week? b. How much would you save in total project costs with your schedule?arrow_forwardplease solve for question Carrow_forwardImage of Diagram included Using the diagram, find: The critical path. How long it will take to complete the project? How does simulation determine the probabilities of various project completion times? What is "slack" and why is it important? Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? How is the uncertainty in project scheduling dealt with? Should the critical path activities be managed differently from noncritical path activities? Explain.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY