PROJECT MANAGEMENT (LOOSELEAF)-W/ACCESS
7th Edition
ISBN: 9781260216011
Author: Larson
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 5, Problem 3E
Exercise Figure 5.1 is a project WBS with cost apportioned by percentages. If the total project cost is estimated to be $600,000, what are the estimated costs for the following deliverables?
a. Design
b. Programming
c. In-house testing
What weaknesses are inherent in this estimating approach?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Justify the use of earned value management (EVM) to control expenses and monitor the effectiveness of a project, and speculate as to why it is not used more often. How can one determine if a cost variation, a schedule variance, a cost performance index, or a schedule performance index is favorable or unfavorable? What are some general criteria to follow?
I need solve this question in project manager
Construct a project checklist model for screening these four alternatives and which is the best and worst choice for selection?
Chapter 5 Solutions
PROJECT MANAGEMENT (LOOSELEAF)-W/ACCESS
Ch. 5.1A - How many labor hours should the eighth satellite...Ch. 5.1A - How many labor hours for the whole project of...Ch. 5.1A - What price would you ask for the project? Why?Ch. 5.1A - Midway through the project your design and...Ch. 5.1A - Near the end of the project, Deutsch Telefon AG...Ch. 5 - Why are accurate estimates critical to effective...Ch. 5 - Prob. 2RQCh. 5 - Prob. 3RQCh. 5 - What are the major types of costs? Which costs are...Ch. 5 - Why is it difficult to estimate mega project...
Ch. 5 - Define what a white elephant is in project...Ch. 5 - Calculate the direct cost of labor tor a project...Ch. 5 - Mrs. Tolstoy and her husband, Serge, are planning...Ch. 5 - Exercise Figure 5.1 is a project WBS with cost...Ch. 5 - Firewall Project XT. Using the complexity...Ch. 5 - At this point, what would you do if you were the...Ch. 5 - Prob. 5.1.2CCh. 5 - What estimating techniques should be used for a...Ch. 5 - Assume you are either Mike or Josh; how would you...Ch. 5 - Prob. 5.2.2CCh. 5 - After cost, what other factors should be...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- Instead of 2.0 to 5.0 use 4.0 to 3.0arrow_forwardAfter six months of work on the project’s site, your company collected the following information relating to work done so far on the project BAC=$156,478.00, planned value=$95,565.24, Earned value =$92, 985.56, Actual cost =$95986.60. Calculate the cost and schedule performance indices and interpret your resultsarrow_forwardplease help, project management. I need part D,Eand 2 1) Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV=$22,000 EV=$20,000 AC=$25,000 BAC=$120,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Show your calculations. b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain. c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Explain. d) Use the SPI to estimate how long it will take to finish this project. e) Sketch the earned value chart for this project. 2) Write a one-page summary explaining how is project cost management different when using an Agile approach? Make sure to document any cited…arrow_forward
- Use the information in this table to calculate the weighted score for project 2 Criteria Weight Project1 Project2 Project3 Project4 Supports of key business objectives 5% 90 90 50 20 Has strong internal sponsor 10% 70 90 50 20 Has strong customer support 5% 50 90 50 20 Realistic level of technology 10% 25 90 50 70 Can be implemented in one year or less 30% 20 20 50 90 Provides positive NPV 10% 50 70 50 50 Has low risk in meeting scope, time, and cost goals 30% 20 50 50 90arrow_forwardThe optimistic cost for a project is $6,000. The pessimistic cost estimate is $24,000 and the most likely cost is $12,000. The project uses 3 sigma estimates. Using PERT what is the range of this estimate?arrow_forwardgiven the following information for a 1-year project, answer the following questions. Assume you have actual and earned value data at the end of the second month. Recall that PV is the plan value, Evie is the earned value, AC is the actual cost, and BAC is the budget at completion.pv =$ 23,000ev = 20,000ac= 25,000bac = 130,000a. what is the cost variance, schedule variance, cost performance index CPI and schedule performance index SPI for the project?B. how is the project progressing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?C. use the CPI to calculate the estimate at completion EAC for this project.d. use the SPI to estimate how long it will take to finish this project.e. sketch the earned value chart for this project, use the figure below as a guide. Assume the data for month one is half of the values given for Pv, Ev and ac at the end of month 2arrow_forward
- Project selection criteria are typically classified as _? Select one: a. Short-term and long-term b. Strategic and tactical c. Financial and non-financial O d. Required and optionalarrow_forwardIn order to promote the College of Engineering, IT and Environment, the college asks you to organize an information session to the prospective students and parents (which can be considered as a project). The project is expected to be completed within 3 weeks and this event should be held in CDU Casuarina campus. The project budget is AUD 3,000.00. Answer the following questions (you can make assumptions in answering the questions). Question 1 c) Assess the risks. d) Explain what can be considered as quality metrics for this projectarrow_forward7. The Custom Bike Company has set up a weighted scoring matrix for evaluation of potential projects. Below are five projects under consideration. a. Using the scoring matrix in the following chart, which project would you rate highest? Lowest? b. If the weight for "Strong Sponsor" is changed from 2.0 to 5.0, will the project selection change? What are the three highest weighted project scores with this new weight? c. Why is it important that the weights mirror critical strategic factors?arrow_forward
- If earned value management (EVM) is so beneficial, why is it not used more often? Explain how it may be used to track costs and evaluate the success of a project. When evaluating cost variation, schedule variance, cost performance index, and schedule performance, what criteria should be used as a starting point?arrow_forwardWhen planning, who is responsible to breakdown and define the different levels of the project plan? Process Owner Project Manager Project Scheduler Project Estimatorarrow_forwardJustify the usage of earned value management (EVM) to control costs and monitor project success, and hypothesize on why it is not utilized more often. What are some broad guidelines for determining if a cost variation, a schedule variance, a cost performance index, or a schedule performance index is positive or negative?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY