Summary Introduction

To determine:

The difference between bottom-up and top-down estimating approach and the situation where bottom-up is preferred over top-down and vice-versa.

Introduction:

Top down approach makes a rough estimate of the project cost and time duration and then breaks into more details to get the activity time and cost.

Bottom up approach first makes concrete estimate of the activities’ time and cost and them consolidates them to make budget and cost estimates for the project.

Blurred answer
Students have asked these similar questions
How different businesses are using the technique Regression analysis to estimate cost of different areas?
Suppose that you are opening a new restaurant.  How would you go about forecasting demand and sales?
Can you give me an example of an analogous estimate and a parametric estimate?
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Text book image
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Text book image
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Text book image
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Text book image
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Text book image
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON