Cornerstones of Cost Management (Cornerstones Series)
Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN: 9781305970663
Author: Don R. Hansen, Maryanne M. Mowen
Publisher: Cengage Learning
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 4, Problem 9CE

Patterson Company produces wafers for integrated circuits. Data for the most recent year are provided:

Chapter 4, Problem 9CE, Patterson Company produces wafers for integrated circuits. Data for the most recent year are

aCalculated using number of dies as the single unit-level driver.

bCalculated by multiplying the consumption ratio of each product by the cost of each activity.

Required:

  1. 1. Using the five most expensive activities, calculate the overhead cost assigned to each product. Assume that the costs of the other activities are assigned in proportion to the cost of the five activities.
  2. 2. Calculate the error relative to the fully specified ABC product cost and comment on the outcome.
  3. 3. What if activities 1, 2, 5, and 8 each had a cost of $650,000 and the remaining activities had a cost of $50,000? Calculate the cost assigned to Wafer A by a fully specified ABC system and then by an approximately relevant ABC approach. Comment on the implications for the approximately relevant approach.

1.

Expert Solution
Check Mark
To determine

Compute the overheads assigned to each product of P Company using the five most expensive activities assuming the cost of other activities are assigned in proportion to the cost of the five activities.

Explanation of Solution

Overhead consumption ratio: An overhead consumption ratio is a measurement tool used to calculate the proportion of the overhead activity that is consumed by a particular product.

Approximately relevant activity based costing: Approximately relevant activity based costing

Compute the overhead cost to be assigned to both products of P Company using the five most expensive activities.

Activity

Budgeted cost

($)

Expected consumption ratio
Wafer AWafer B
Testing products720,000 (1)60 %40 %
Handling water lots360,000 (2)45 %55 %
Inserting dies840,000 (3)70 %30 %
Purchasing materials480,000 (4)20 %80 %
Moving materials600,000 (5)50 %50 %
Total activity cost3,000,000 

Table (1)

Working notes:

(1) Calculate the budgeted cost for the activity of testing hours of P Company.

Budgeted cost = Original costs + [(Original costTotal cost of expensive activities )×Total cost of inexpensive activities]=$600,000+[($600,000$2,500,000)×$500,000]=$600,000+[.24×$500,000]=$600,000+$120,000=$720,000

(2) Calculate the budgeted cost for the activity of handling water lots of P Company.

Budgeted cost = Original costs + [(Original costTotal cost of expensive activities )×Total cost of inexpensive activities]=$300,000+[($300,000$2,500,000)×$500,000]=$300,000+[.12×$500,000]=$300,000+$60,000=$360,000

(3) Calculate the budgeted cost for the activity of testing hours of P Company.

Budgeted cost = Original costs + [(Original costTotal cost of expensive activities )×Total cost of inexpensive activities]=$700,000+[($700,000$2,500,000)×$500,000]=$700,000+[.28×$500,000]=$700,000+$140,000=$840,000

(4) Calculate the budgeted cost for the activity of purchasing materials of P Company.

Budgeted cost = Original costs + [(Original costTotal cost of expensive activities )×Total cost of inexpensive activities]=$400,000+[($400,000$2,500,000)×$500,000]=$400,000+[.16×$500,000]=$400,000+$80,000=$480,000

(5) Calculate the budgeted cost for the activity of purchasing materials of P Company.

Budgeted cost = Original costs + [(Original costTotal cost of expensive activities )×Total cost of inexpensive activities]=$500,000+[($500,000$2,500,000)×$500,000]=$500,000+[.2×$500,000]=$500,000+$100,000=$600,000

Compute the total approximately relevant activity based cost for all activities by using consumption ratios.

Wafer A:

Activity

Consumption ratio

(%)

Budgeted activity cost

($)

Reduced ABC system

($)

 (a)(b)(a)×(b)
Testing products60 %720,000432,000
Handling water lots45 %360,000162,000
Inserting dies70 %840,000588,000
Purchasing materials20 %480,00096,000
Moving materials50 %600,000300,000
Total activity cost 1,578,000

Table (2)

Wafer B:

Activity

Consumption ratio

(%)

Budgeted activity cost

($)

Reduced ABC system

($)

 (a)(b)(a)×(b)
Testing products40 %720,000288,000
Handling water lots55 %360,000198,000
Inserting dies30 %840,000252,000
Purchasing materials80 %480,000384,000
Moving materials50 %600,000300,000
Total activity cost 1,422,000

Table (3)

2.

Expert Solution
Check Mark
To determine

Compute the relative error for both products with respect to fully specified activity based costing and provide information on the result.

Explanation of Solution

Calculate the relative error for both products with respect to fully specified activity based costing and provide information on the result. 

Wafer A:

Relative error =(Reduced Activity based costTotal activity cost assigned)Total activity cost assigned=($1,578,000$1,500,000)$1,500,000=0.052=5.2%

Wafer B:

Relative error =(Reduced Activity based costTotal activity cost assigned)Total activity cost assigned=($1,422,000$1,500,000)$1,500,000=(0.052)=(5.2%)

From the above calculated result, the maximum error is 5.2 percent with respect to activity based cost assignments that indicates a positive result indicated better accuracy.

3.

Expert Solution
Check Mark
To determine

Calculate the cost assigned to Wafer A by a fully specified activity based costing system and activity based costing system. Activities of developing test program, making probe cards, engineering designs, and purchasing materials costs $650,000 each and the remaining activities costs $50,000. Provide information on the implications for the relevant approach.

Explanation of Solution

Wafer A:

Activity based cost =[Activity cost×(Total consumption ratios)]+[Activity cost of remaining activities×(Total consumption ratios)]=[$650,000×(25%+10%15%+20%)]+[$50,000×(60%+55%+45%70%+35%+65%+50%+30%)]=[$650,000×(.25+.10+.15+.20)]+[$50,000×(.60+.55+.45+.7+.35+.65+.5+.3)]=[$650,000×0.7]+[$50,000×4.1]=$455,000+$205,000=$660,000

Compute the approximately relevant cost for the activities 1, 2, 5, and 8 of P Company.

Reassigned cost=Activity based cost+Engineering hours×Purchasing materials=$650,000+.25×$400,000=$750,000

Compute the approximately relevant cost for Wafer A.

Approximately relevant cost =Reassigned cost×(Expected consumption ratios of Wafer A)=$750,000(25%+10%+15%+20%)=$750,000(.25+.10+.15+.20)=$525,000

Compute the error term of P Company with respect to the costing techniques used.

Difference in costing=Activity based costApproximately relevanet cost=$660,000$525,000=$135,000

Compute the relative error between the costing techniques used by P Company.

Relative error=(Approximately relevant costActivity based cost)Activity based cost=($525,000$660,000)$660,000=($165,000)$660,000=20.5%

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
What differentiates process-based validation from outcome testing? (A) Systematic review steps assess control effectiveness (B) Final results alone matter (C) Process review wastes time (D) Outcomes tell complete story
Need answer the financial accounting question
Question: - How does resource attribution mapping enhance cost allocation? 1. Attribution wastes effort 2. Equal splitting works better 3. Usage patterns determine proper distribution methods 4. Simple rules suffice always.

Chapter 4 Solutions

Cornerstones of Cost Management (Cornerstones Series)

Ch. 4 - Identify and define two types of activity drivers.Ch. 4 - What are unit-level activities? Batch-level...Ch. 4 - Prob. 13DQCh. 4 - Prob. 14DQCh. 4 - Prob. 15DQCh. 4 - Prob. 1CECh. 4 - Warner Company has the following data for the past...Ch. 4 - Lansing. Inc., provided the following data for its...Ch. 4 - Larsen, Inc., produces two types of electronic...Ch. 4 - Roberts Company produces two weed eaters: basic...Ch. 4 - Golding Bank provided the following data about its...Ch. 4 - Golding Bank provided the following data about its...Ch. 4 - Electan Company produces two types of printers....Ch. 4 - Patterson Company produces wafers for integrated...Ch. 4 - Selected activities and other information are...Ch. 4 - Ripley, Inc., costs products using a normal...Ch. 4 - Predetermined Overhead Rate, Application of...Ch. 4 - Craig Company uses a predetermined overhead rate...Ch. 4 - Departmental Overhead Rates Mariposa, Inc.,...Ch. 4 - McCourt Company produces two types of leather...Ch. 4 - Deoro Company has identified the following...Ch. 4 - Prob. 17ECh. 4 - Secondary Activities Refer to the interview in...Ch. 4 - Bob Randall, cost accounting manager for Hemple...Ch. 4 - Prob. 20ECh. 4 - Bob Randall, cost accounting manager for Hemple...Ch. 4 - Silven Company has identified the following...Ch. 4 - Silven Company has identified the following...Ch. 4 - Gee Manufacturing produces two models of camshafts...Ch. 4 - Cushing, Inc., costs products using a normal...Ch. 4 - Nonunit-level drivers are prominent in...Ch. 4 - Plata Company has identified the following...Ch. 4 - Assume that the inspection activity has an...Ch. 4 - Consider the information given on two products and...Ch. 4 - Primera Company produces two products and uses a...Ch. 4 - Fisico Company produces exercise bikes. One of its...Ch. 4 - Prob. 32PCh. 4 - Glencoe First National Bank operated for years...Ch. 4 - Autotech Manufacturing is engaged in the...Ch. 4 - The Bienestar Cardiology Clinic has two major...Ch. 4 - Reducir, Inc., produces two different types of...Ch. 4 - Refer to the data given in Problem 4.36 and...Ch. 4 - Escuha Company produces two type of calculators:...
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Text book image
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Cost Accounting - Definition, Purpose, Types, How it Works?; Author: WallStreetMojo;https://www.youtube.com/watch?v=AwrwUf8vYEY;License: Standard YouTube License, CC-BY