EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
10th Edition
ISBN: 9780134183848
Author: HEIZER
Publisher: PEARSON CO
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 3, Problem 9P
a)
Summary Introduction
To develop:An AON network diagram with the given the various activities, their precedence and succession relationships, activity times and so on.
Introduction: In the activity on nodes (AON) project network diagram, the nodes denote activities and the arrows show only the precedence and succession sequence.
b)
Summary Introduction
To determine: The critical path.
c)
Summary Introduction
To determine: The total expected time.
d)
Summary Introduction
To draw: The Gantt chart for the project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Reliable Garage is completing production of the J2000 kit car. The following data are available for the project:a. Draw the network diagram for the project. b. Determine the project’s critical path and duration. c. What is the slack for each activity?
How can a business analyst communicate requirements (and associated models) for a project in project management.
Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office
space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin.
Activity
A
B
C
D
E
F
G
H
A
B
(c) Develop the activity schedule for the project.
Earliest
Activity
Start
с
D
E
Description
Survey building site
Develop initial design
Obtain board approval
F
G
Select architect
Establish budget
Finalize design
Obtain financing
Hire contractor
H
0
0
7
18
18
25
25
(a) Draw a project network. (Submit a file with a maximum size of 1 MB.)
Choose File No file chosen
This answer has not been graded yet.
38
(b) Identify the critical path. (Enter your answers as a comma-separated list.)
B.C.EFH
✓
Immediate
Predecessor
X
X
x
2
0
7
21
18
25
X 27
A, B
с
38
с
D, E
E
F, G
Latest
Start
x
x
X
Time
(weeks)
5
X
7
x
10
3
5
13
11
6
5
18
22
25
38
36
47
Earliest…
Chapter 3 Solutions
EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - The Rover 6 is a new custom-designed sports car....Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 1CSCh. 3 - Prob. 2CSCh. 3 - Prob. 3CSCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- sniparrow_forwardTask time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Time Activity (in hours) Immediate Predecessor(s) A B C D E F G 7.0 6.7 6.0 8.0 5.1 7.7 6.0 A B, C B, C D E, F This exercise contains only part a. a) The correct precedence diagram for the project is shown in C Figure 1 A B Figure 2 B F E F Earrow_forwardTask time estimates for the modificat ion of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: a) Draw the project network using AON.b) Identify the critical path.c) What is the expected project completion time?d) Draw a Gantt chart for the project.arrow_forward
- A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. Draw the project network. What is the minimum time required to finish the project? State the critical path. Activity Time (week) Immediate Predecessor A. Find client 4 --- B. Write prospectus 2 A C. Obtain approval from client and professor 3 B D. Complete programming 12 C E. Do industry background research 10 --- F. Write final paper 6 D, E G. Write oral report 5 D, Earrow_forwardA Make a network diagram and find the project completion time and critical path Activity Activity Description Excavate (7) Estimated Duration (Weeks) Immediate Predecessors 2 B Lay the foundation A 4 C Put up the rough wall B 10 D Put up the roof C 6 E Install the exterior plumbing C 4 F Install the interior plumbing E 5 G Put up the exterior siding D 7 H Do the exterior painting E, G 9 1 Do the electrical work C 7 J Put up the wallboard F, I 8 K Install the flooring J 4 Do the interior painting J 5 M Install the exterior fixtures H N Install the interior fixtures K, L 26arrow_forward1. Data for a simplified PERT network are given below: a. Set up a table and calculate Early Event Times (TE), Late Event Times (TL), Activity Free Slack (AFS), and Activity Total Slack (ATS). b. Determine the PERT "critical path(s)" and the mean and standard deviation for the project duration. c. Determine the probability of completing the project in 25 days or less. d. Determine that the project will take 27 days or more. e. Determine the probability of reaching event 35 in 20 days or less. Time Estimates (days) i АСТ b a m 10 A 1 3 5 15 B 2 5 10 20 C 4 7 10 25 E 8. 10 12 IP F 15 25 15 30 4 8 9. 20 35 G 5 7 14 25 35 L 7 10 16 30 35 d2 30 40 12 35 45 N 1 3 7 40 45 P 3 5 7arrow_forward
- Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Activity AB A E F G Time (in hours) 7.0 7.2 5.0 8.0 4.5 7.7 5.0 Immediate Predecessor(s) || | < B, C B, C D E, F This exercise contains only part a. a) The correct precedence diagram for the project is shown in Figure 1 Figure 2 Figure 3 Figure 1 B Figure 2 B Figure 3 A F E E LL F F Narrow_forwardReliable Garage is completing production of the J2000 kit car.The following data are available for the project:Activity Activity Time (days) Immediate Predecessor(s)A 2 —B 6 AC 4 BD 5 CE 7 CF 5 CG 5 FH 3 D, E, Ga. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?arrow_forwardFor the project described in the table, which includes activity durations and precedence relationships, address the following tasks: a) Construct and solve the AOA and AON network diagrams. b) Identify the total project duration. c) Identify the project's critical path(s). Activity K L M N 0 P QR S T Predecessor K K L L M M N, P Q Duration (Weeks) 2 8 10 6 3 3 7 5 2 8arrow_forward
- 9.2. Construct a Gantt chart for the project described by the following set of activities, and indicate the project completion time and the available slack for each activity:Activity Activity Predecessor Time (Weeks)1 — 32 — 73 1 24 2 55 2 66 4 17 5 4 Present a Gantt Chart that shows the timeline from start to end. This calls for drawing an A-O-N network diagram using the information given in the Table. Present a Table of Activity versus Slack (wks) and state which specific activities are on the Critical path.arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Immediate Activity Predecessor(s) Time (days) 4 5 3 III B 10 A, D 3 C 5 G E, F 12 This exercise contains only part a. a) The correct precedence diagram for the project is shown in ABCDEF Ñ GW 8 w or C A B F Figure 2 A B O-O Figure 3 B E E Earrow_forwardConsider a project having the following ten activities: Immediate Activity A Time (weeks) Predecessors none 7 B none 3 A 5 А, В С, D 6 E 4 F D 4 G C 9 E, G E, F H, I H 8 I J 5 a)Construct AON diagram for the following data. b) Identify path, path duration and critical path c) Conduct CPM analysis by identifying ES, EF, LS, LF d) What is the slack for each activity and the critical path?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY