EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
10th Edition
ISBN: 9780134183848
Author: HEIZER
Publisher: PEARSON CO
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 3, Problem 1P
The work breakdown structure (WBS) for building a house (levels 1 and 2) is shown below:
a) Add two level-3 activities to each of the level-2 activities to provide more detail to the WBS.
b) Select one of your level-3 activities and add two level-4 activities below it.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The work breakdown structure (WBS) for building a house (levels 1 and 2) is shown below: a) Add two level-3 activities to each of the level-2 activities to provide more detail to the WBS. b) Select one of your level-3 activities and add two level-4 activities below it.
The work breakdown structure (WBS) for building a house (levels I and 2) is shown below: a) Add two level-3 activities to each of the level-2 activities to provide more detail to the WBS.b) Select one of your level-3 activities and add two level-4 activities below it.
Develop a Work Breakdown Structure (WBS) for the following case study by using Top-down Approach.
You are hired as a project manager to develop the Campus Management System (CMS) of a famous educational complex. CMS is designed to promote automated university administration and provides a medium for teachers, staff and administration to work in harmony. CMS has a complete role based access where in various resources are made available depending upon the role assigned. The Student module includes students to add, modify and view features designed to ease registration. The Academic Management module deals with academic history of the students and it allows determining student's expertise level through his obtained grades. The Fee Management module keeps track of fees paid and dues and allows printing of fee voucher. The Course Management module allows maintaining different courses, the respective instructors and session details. The Alerts and Notification module is email based alerts…
Chapter 3 Solutions
EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - The Rover 6 is a new custom-designed sports car....Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 1CSCh. 3 - Prob. 2CSCh. 3 - Prob. 3CSCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- James Lawson has decided to run for a seat as Congressman from the House of Representatives, District 34, in Florida. He views his 8-month campaign for office as a majorproject and wishes to create a work breakdown structure (WBS) to help control the detailed scheduling. So far, he has developed the following pieces of the WBS: Help Lawson by providing details where the blank lines appear. Are there any other major (Jevel-2) activities to create? If so, add an ID no. 1.6 and insert them.arrow_forwardTwo techniques for reducing rework expenses should be provided. Consider the need of progressive delivery across both tactics.arrow_forwardYou are alone at home and have to prepare a bread sandwich for yourself. The following preparation activities and time taken are given in the table below: Task Description Predecessor Time (Minutes) A Purchase of bread - 20 B Take cheese and apply on bread A 5 C Get onions from freezer A 1 D Fry onions with pepper B,C 6 E Purchase sauce for bread - 15 F Toast bread B,C 4 G Assemble bread and fried onions F 2 H Arrange in plat G 1 Determine: a. While purchasing sauce, you met a friend and spoke to him for 6 minutes. Did this cause any delay in the preparation?arrow_forward
- Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow: Task Information for Kiko Teddy Bear Work Element Task Description ImmediatePredecessor Task Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C…arrow_forwardKiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow: Task Information for Kiko Teddy Bear Work Element Task Description ImmediatePredecessor Task Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C…arrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: A- Time B- Code Description (hrs) Immediate Predecessor(s) C- A Find location; determine resource requirements 25 None Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes 55 A D- C 100 A E- 30 В E Position lumber in correct locations 20 D, C F- F Nail lumber together 10 E G- Put sand in and under the equipment Put dirt around the equipment G 25 F H F H- Put grass all over the garden, landscape, paint 35 G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. 20 40 60 80 100 120 140 160 180 200 220arrow_forward
- The project manager of the gas station project shown inFigure 7.3 needs to change the project’s WBS so that itcan be compared with cost and productivity informationcollected by the company. Level II should be changedto General Field Administration, Earthwork, ConcreteWork, Masonry Work, Metal Work, Carpentry, and Others.Complete the WBS of this project using this new arrangementfor Level II.arrow_forwardPower Builders Inc. is planning for an upcoming job with a large client. They have listed the specific activities and steps to be performed, and estimated the time to complete each activity. The activities involved in the job are listed below: Activity Description of Activity Preceding Activity Estimated Time Required (in weeks) A B C D E F G H I J K Planning Meeting Obtain Permit Inspect Damage Begin Repair Work Order Additional Materials Apply for Waiver Obtain Waiver Complete Electrical Work Build Interior Partitions Onsite Testing Meet With Client -- A B A D E C, F D H G, I J 5 2 5 4 2 4 2 5 5 2 2 REQUIRED: Prepare a Gantt Chart from the facts in this time budget.arrow_forwardWork Breakdown Structure (WBS) for A millionares mansion with four to five (4-5) high level tasks and an average of four to five (4-5) sub-tasks for each high level task. Under these 4 phases Planning - Interior Design - Landscape/Outdoor Entertainment - Project Closeoutarrow_forward
- a. Work Breakdown Structure (WBS): Develop a detailed work breakdown structure thatlists all the tasks required to launch the product or service. Organise the tasks into logicalphases and sub-phases.arrow_forwardCan we identify a specific area of difficulty being tackled by the workflow management tool?arrow_forward(Note: Task N is a dummy task. It must be included in the relationships, but its duration is 0. Be sure its duration is set to 0) Please see attached charts and diagram. Assign the following resources to the tasks. All resources will be full time. (Set the leveling to manual first). Task Resource Cost / Day A R1 200 B R2 300 C R3 300 D R4 300 E R2 300 F R4 300 G R1 200 H R5 200 I R6 400 J R5 200 K R1 200 L R3 300 M R2 300 N - - 1. Check for over-allocation. Which resources are over allocated? 2. Level if necessary. Then determine the new critical path and duration. 3. What is the total cost of the project (Fixed + Resource cost)? How much does the project need in the first, second, and third weeks?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY