EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
10th Edition
ISBN: 9780134183848
Author: HEIZER
Publisher: PEARSON CO
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 3, Problem 5P
Draw the activity-on-node (AON) project network associated with the following activities for Carl Betterton’s construction project. How long should it take Carl and his team to complete this project? What are the critical path activities?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A farm owner is going to erect a maintenance building with connecting electrical gen-
erator and water tank. The activities, activity descriptions and estimated durations are
given in the following table. Construct the AOA network for this project, identify the
critical path and construct a Gantt chart for the project.
Description
Excavate
Erect building
Install generator
Install tank
Activity
A
Predecessor Duration
2
B
A
6
A
4
D
A
E
Install maintenance equipment
В
4
F
Connect generator and tank building
B,C,D
5
G
Paint finish
В
3
H
Check out facility
E,F
2
Please help me experts to solve this problem.
Thank you.
Construct an AON project network for the following set of activities. Analyze the project network,
answer the following questions.
Activity Activity Predecessor
I
3
4
S
6
7
8
9
1
2
3
3
4.5.6
2
S
Which of the following is a critical path?
O2->5->8
1->4->8
Time (months)
4
7
8
3
9
O 1->3->7
O 1->3->6->8
2
Chapter 3 Solutions
EP PRIN.OF OPERATIONS MGMT.-MYOMLAB
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - The Rover 6 is a new custom-designed sports car....Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 1CSCh. 3 - Prob. 2CSCh. 3 - Prob. 3CSCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Critical path and project durationarrow_forwardUsing the information given in Chapter 19 Computational Exercise Questions 19.2-36 on page 596 in the paper textbook, and your responses to the questions in the Online Discussion this week, develop the following for Mary's wedding project: A risk management plan that includes at least one major risk, one medium risk and one acceptable risk, complete with mitigation plans. An expense budget for the activity elements included in the plan. Show details of Labor, Material and facilities rental.arrow_forwardConstruct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path:arrow_forward
- You may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 42- week completion date requested by the owner. The Mueller project manager prepared the following project network. Start Activity A B с D E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. TI G H Optimistic Most Probable 4 6 6 weeks 3 6 5 10 A 5 8 7 12 5 9 8 B 15 6 Pessimistic 12 8 18 7 18 17 20 (b) What is the expected project completion time (in weeks)? 52 13 F E (a) Find the critical path. (Enter your answers as a comma-separated list.) A,C,E,G,H G H Finish (c) Based only on the critical path, what is the estimated probability the project can be completed in 42 weeks as requested by the owner? (Round your answer to four decimal places.) X (d) Based only on the…arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) A BCDEFG с This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = d) Slack time for each of the activities is: days. Activity A B C ס ח ד 0 F B A, D C E, F G Slack Time Time (days) 4 6 1 103510arrow_forwardA project has seven (7) main activities labelled A through G as shown in the below table which also shows their estimated duration times ( in weeks) and immediate predecessors. Activity a b Immediate Remarks predeccessor A 1 2 3 a = optimistic time 2 3 4 m = most likely time C 4 A b = pessimistic time 8 9 10 E 2 5 8 C,D 4 6. G 1 2 3 E (a) Develop a project network for this problem.arrow_forward
- Below is information about a project to implement a new manufacturing cell to assemble personal digital assistance devices Calculate the expected time for all tasks and maintain one decimal place. Complete a critical path analysis. Complete forward and backward passes. What is the critical path? What is the project duration? What is the latest start for Activity 4 "Secure patent?"?arrow_forwardThe manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are presented in Table 3. Draw a project network. Develop an activity schedule. What are the critical activities, and what is the expected project completion time? What is the probability that the swimming program will be ready in 13 weeks?arrow_forwardAnalyze projects using network-planning models?arrow_forward
- Roger Ginde is developing a program in supplychain management certification for managers. Ginde haslisted a number of activities that must be completed beforea training program of this nature could be conducted. Theactivities, immediate predecessors, and times appear in theaccompanying table: a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors,and times appear in the accompanying table: a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?arrow_forward(please try to do math in handwritten) Use the following project data for problem 1 through 5 Activity name Predecessor Activity Activity Duration N 3 M 2 P M,N 4 3 P,Q R,S 2. 1. Prepare an AON Network Diagram 2. Identify all possible paths. Provide that information in a table. The heading of your table should as follow: Path Duration 3. Perform a forward pass and a backward pass. Display your result in an AON diagram.Usethe follow legend for your node(s) Activity ES EF Duration LS LF 4. Prepare a table summarizing the results of your Activity Schedule. The heading of your table should as follows: Activity name ES Slack EF LS LF 5. Identify the critical path. What is the project duration? 2. 4.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY