Jamarcus Bradshaw, plant manager of Georgia Paper Company’s papermaking mill, was looking over the cost of production reports for July and August for the Papermaking Department. The reports revealed the following:
Jamarcus was concerned about the increased cost per ton from the output of the department. As a result, he asked the plant controller to perform a study to help explain these results. The controller, Leann Brunswick, began the analysis by performing some interviews of key plant personnel in order to understand what the problem might be. Excerpts from an interview with Len Tyson, a paper machine operator, follow:
Len: We have two papermaking machines in the department. I have no data, but I think paper machine No. 1 is applying too much pulp and, thus, is wasting both conversion and materials resources. We haven't had repairs on paper machine No. 1 in a while. Maybe this is the problem.
Leann: How does too much pulp result in wasted resources?
Len: Well, you see, if too much pulp is applied, then we will waste pulp material. The customer will not pay for the extra product; we just use more material to make the product. Also, when there is too much pulp, the machine must be slowed down in order to complete the drying process. This results in additional conversion costs.
Leann: Do you have any other suspicions?
Len: Well, as you know, we have two products—green paper and yellow paper. They are identical except for the color. The color is added to the papermaking process in the paper machine. I think that during August these two color papers have been behaving very differently. I don't have any data, but it just seems as though the amount of waste associated with the green paper has increased.
Leann: Why is this?
Len: I understand that there has been a change in specifications for the green paper, starting near the beginning of August. This change could be causing the machines to run poorly when making green paper. If this is the case, the cost per ton would increase for green paper.
Leann also asked for a database printout providing greater detail on August’s operating results. September 9 Requested by: Leann Brunswick Papermaking Department—August detail
Prior to preparing a report, Leann resigned from Georgia Paper Company to start her own business. You have been asked to take the data that Leann collected, and write a memo to Jamarcus Bradshaw with a recommendation to management. Your memo should include analysis of the August data to determine whether the paper machine or the paper color explains the increase in the unit cost from July. Include any supporting schedules that are appropriate. Round any calculations to the nearest cent.
Trending nowThis is a popular solution!
Chapter 3 Solutions
Managerial Accounting
- Ethics in Action In August, Lannister Company introduced a new performance measurement system in manufacturing operations. One of the new performance measures is lead time, which is determined by tagging a random sample of items with a log sheet throughout the month. The log sheets recorded the time that the sample items started production and the time that they ended production, as well as all steps in between. At the end of the month, the controller collected the log sheets and computed the average lead time of the tagged products. This number was reported to central management and was used to evaluate the performance of the plant manager. Because of the poor lead time results reported for August, the plant was under extreme pressure to reduce lead time in September. The following memo was intercepted by the controller. Date: September 3 To: Hourly Employees From: Plant Manager During last month, you may have noticed that some of the products were tagged with a log sheet. This sheet records the time that a product enters production and the time that it leaves production. The difference between these two times is termed the lead time. Our plant is evaluated on improving lead time. From now on, I ask all of you to keep an eye out for the tagged items. When you see a tagged item, it is to receive special attention. Work on that item first, and then immediately move it to the next operation. Under no circumstances should tagged items wait on any other work that you have. Naturally, report accurate information. I insist that you record the correct times on the log sheet as the product goes through your operations. How should the controller respond to this discovery?arrow_forwardThe following is a list of costs incurred by several manufacturing companies: a. Annual picnic for plant employees and their families b. Cost of fabric used by clothing manufacturer c. Cost of plastic for a toy manufacturer d. Cost of sewing machine needles used by a shirt manufacturer e. Cost of television commercials f. Depreciation of copying machines used by the Marketing Department g. Depreciation of microcomputers used in the factory to coordinate and monitor the production schedules h. Depreciation of office building i. Depreciation of robotic equipment used to assemble a product j. Electricity used to operate factory machinery k. Factory janitorial supplies I. Fees charged by collection agency on past-due customer accounts m. Fees paid to lawn service for office grounds n. Maintenance costs for factory equipment o. Oil lubricants for factory plant and equipment p. Pens, paper, and other supplies used by the Accounting Department q. Repair costs for factory equipment r. Rent for a warehouse used to store work in process and finished products s. Salary of a physical therapist who treats plant employees t. Salary of the manager of a manufacturing plant u. Telephone charges by corporate office v. Travel costs of marketing executives to annual sales meeting w. Wages of a machine operator on the production line x. Wages of production quality control personnel Instructions Classify each of the preceding costs as a product cost or period cost. Indicate whether each product cost is a direct materials cost, a direct labor cost, or a factory overhead cost. Indicate whether each period cost is a selling expense or an administrative expense. Use the following tabular headings for preparing your answer, placing an X in the appropriate column:arrow_forwardBello, a general manager of a highly automated coffee production plant in Laguna, has provided the following information for transactions that occurred during October. The production plant uses a JIT costing system.arrow_forward
- Bob Randall, cost accounting manager for Hemple Products, was asked to determine the costs of the activities performed within the company’s Manufacturing Engineering Department. The department has the following activities: creating bills of materials (BOMs), studying manufacturing capabilities, improving manufacturing process, training, employees, and designing tools. The general ledger accounts reveal the following expenditures for Manufacturing Engineering: Salaries $ 500,000 Equipment 100,000 Supplies 30,000 Total $630,000 The equipment is used for two activities: improving process and designing tools. The equipment’s time is divided by two activities: 40 percent for improving process and 60 percent for designing tools. The salaries are for nine…arrow_forwardAs an assistant cost accountant for Firewall Industries, you have been assigned to review the activity base for the predetermined factory overhead rate. The president, JoJo Gunn, is concerned about the wide fluctuation in the amount of over- or underapplied overhead in recent years. An analysis of the company's operations and use of the current overhead rate (direct labor cost) has narrowed the possible alternative overhead bases to direct labor cost and machine hours. For the past five years, the following data have been gathered: ww mwwwww M M w Year 5 Year 4 Year 3 Year 2 Year 1 Actual overhead $ 790,000 $ 870,000 $ 935,000 $ 845,000 $ 760,000 Applied overhead 777,000 882,000 924,000 840,000 777,000 (Over-) underapplied overhead $ 13,000 $ (12,000) %24 $ 11,000 5,000 $ (17,000) Direct labor cost $3,885,000 $4,410,000 $4,620,000 $4,200,000 $3,885,000 Machine hours 93,000 104,000 111,000 100,400 91,600 8,49 840,000 1. Calculate a predetermined factory overhead rate for each…arrow_forwardProvide a brief conclusion of the case study.arrow_forward
- please do not provide hand written answer.arrow_forwardEthics and the Manager Terri Ronsin had recently been transferred to the Home Security Systems Division of National Home Products. Shortly after taking over her new position as divisional controller, she was asked to develop the division’s predetermined overhead rate for the upcoming year. The accuracy of the rate is important because it is used throughout the year and any underapplied or overapplied overhead is closed out to Cost of Goods Sold at the end of the year. National Home Products uses direct labor-hours in all of its divisions as the allocation base for manufacturing overhead. To compute the predetermined overhead rate, Terri divided her estimate of the total manufacturing overhead for the coming year by the production manager’s estimate of the total direct labor-hours for the coming year. She took her computations to the division’s general manager for approval but was quite surprised when he suggested a modification in the allocation base. Her conversation with the general…arrow_forwardJohn Patrick has recently been hired as controller of Valdosta Vinyl Company (VVC), a manufacturer of vinyl siding used in residential construction. VVC has been in the vinyl siding business form any year sand is currently investigating ways to modernize its manufacturing process. At the first staff meeting Patrick attended, Jack Kielshesky , chief engineer, presented a proposal for automating the Molding Department. Kielshesky recommended that the company purchase two robots that would have the capability of replacing the eight direct-labor employees in the department. The cost savings outlined in the proposal include the elimination of direct-labor cost in the Molding Department plus a reduction of manufacturing overhead cost in the department to zero, because VVC charges manufacturing overhead on the basis of direct-labor dollars using a plant wide rate. The president of VVC was puzzled by Kielshesky's explanation: “This just doesn't make any sense. How can a department’s overhead…arrow_forward
- Cain Components manufactures and distributes various plumbing products used in homes and other buildings. Over time, the production staff has noticed that products they considered easy to make were difficult to sell at margins considered reasonable, while products that seemed to take a lot of staff time were selling well despite recent price increases. A summer intern has suggested that the cost system might be providing misleading information. The controller decided that a good summer project for the intern would be to develop, in one self-contained area of the plant, an alternative cost system with which to compare the current system. The intern identified the following cost pools and, after discussion with some plant personnel, appropriate cost drivers for each pool. There were: Cost Pools Costs Activity Drivers Receiving $ 600,000 Direct material cost Manufacturing 5,500,000 Machine-hours Machine setup 900,000 Production runs Shipping 1,000,000 Units shipped…arrow_forwardCain Components manufactures and distributes various plumbing products used in homes and other buildings. Over time, the production staff has noticed that products they considered easy to make were difficult to sell at margins considered reasonable, while products that seemed to take a lot of staff time were selling well despite recent price increases. A summer intern has suggested that the cost system might be providing misleading information. The controller decided that a good summer project for the intern would be to develop, in one self-contained area of the plant, an alternative cost system with which to compare the current system. The intern identified the following cost pools and, after discussion with some plant personnel, appropriate cost drivers for each pool. There were: Cost Pools Costs Activity Drivers Receiving $ 600,000 Direct material cost Manufacturing 5,500,000 Machine-hours Machine setup 900,000 Production runs Shipping 1,000,000 Units shipped…arrow_forwardCain Components manufactures and distributes various plumbing products used in homes and other buildings. Over time, the production staff has noticed that products they considered easy to make were difficult to sell at margins considered reasonable, while products that seemed to take a lot of staff time were selling well despite recent price increases. A summer intern has suggested that the cost system might be providing misleading information. The controller decided that a good summer project for the intern would be to develop, in one self-contained area of the plant, an alternative cost system with which to compare the current system. The intern identified the following cost pools and, after discussion with some plant personnel, appropriate cost drivers for each pool. There were: Cost Pools Costs Activity Drivers Receiving $ 600,000 Direct material cost Manufacturing 5,500,000 Machine-hours Machine setup 900,000 Production runs Shipping 1,000,000 Units shipped…arrow_forward
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning