Chapter 3, Problem 19P

Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table:

Chapter 3, Problem 19P, Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned

a) Determine the expected completion time and variance for each activity.

b) Determine the total project completion time and the critical path for the project.

c) Determine ES, EF, LS, LF, and slack for each activity.

d) What is the probability that Kelle Carpet and Trim will finish the project in 40 days or less?

a)

Expert Solution
Check Mark
Summary Introduction

To determine:The expected completion time and variance of the various activities.

Introduction:

The activity times of various tasks in a PERT project network are assumed to follow a probability distribution. For calculating the expected times and standard deviation, the parameters required are the following:

  • Optimistic time: This is the time denoted by “a”, which is the best possible or in other words, the quickest time in which an activity can be completed, assuming that everything goes as per plan.
  • Pessimistic time: This is the worst case scenario, where all the conditions are adverse or unfavorable. The maximum time which may be taken in such a situation is the pessimistic time denoted by “b”.
  • Most likely time: The most realistic estimate of the time, denoted by “m” in normal conditions, is another parameter which is important in the computation of expected times and variances.

Answer to Problem 19P

The expected times and standard deviations for the following six activities are shown in Table 1.

Explanation of Solution

Given information:

Activity a m b t Immediate predecessor
A 3 6 8 8
B 2 4 4 4
C 1 2 3 3
D 6 7 8 8 C
E 2 4 6 6 B,D
F 6 10 14 14 A,E
G 1 2 4 4 A,E
H 3 6 9 9 F
I 10 11 12 12 G
J 14 16 20 20 C
K 2 8 10 10 H,I

Formula:

The expected time “t” would be calculated by the formula shown below.

t=(a+4m+b)6

where “a” is the optimistic time, “b” is the pessimistic time and “m” is the most realistic time.

The variance denoted by σ2 is calculated by using the formula shown below.

Variance=(b-a6)2

Calculation of expected completion time and variance of the various activities:

Use the above formulas to obtain the expected completion time and the variance for the various activities, as shown below.

Unit=number of days

Activity a m b t Immediate predecessor t SD Variance
A 3 6 8 8 5.83 0.83 0.69
B 2 4 4 4 3.67 0.33 0.11
C 1 2 3 3 2.00 0.33 0.11
D 6 7 8 8 C 7.00 0.33 0.11
E 2 4 6 6 B,D 4.00 0.67 0.44
F 6 10 14 14 A,E 10.00 1.33 1.78
G 1 2 4 4 A,E 2.17 0.50 0.25
H 3 6 9 9 F 6.00 1.00 1.00
I 10 11 12 12 G 11.00 0.33 0.11
J 14 16 20 20 C 16.33 1.00 1.00
K 2 8 10 10 H,I 7.33 0.00

Table 1

Excel worksheet:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 3, Problem 19P , additional homework tip  1

Hence, the expected times and standard deviations for the following six activities are shown in Table 1

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The critical path and the project completion time.

Answer to Problem 19P

The longest path is CàDàEàFàHàK which is the critical path and the project completion time is 36.33 days.

Explanation of Solution

Given information:

Activity a m b t Immediate predecessor
A 3 6 8 8
B 2 4 4 4
C 1 2 3 3
D 6 7 8 8 C
E 2 4 6 6 B,D
F 6 10 14 14 A,E
G 1 2 4 4 A,E
H 3 6 9 9 F
I 10 11 12 12 G
J 14 16 20 20 C
K 2 8 10 10 H,I

Calculation of critical path and the project completion time:

The AON project network diagram with the precedence relationships of various activities is shown below,

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 3, Problem 19P , additional homework tip  2

The various project paths from the above diagram and the path durations are in Table 1.

  • AàFàHàK, path accounting for a duration of 5.83+10+6+7.33=29.16days
  • Path AàGàIàK accounting for a duration of 5.83+2.17+11+7.33=26.33days
  • Project path BàEàFàHàK accounting for a duration of 3.67+4+10+6+7.33=31days
  • Project path BàEàGàIàK accounting for a duration of 3.67+4+2.17+11+7.33=28.17days .
  • Project path CàDàEàGàIàK accounting for a duration of 2+7+4+2.17+11+7.33=33.50days
  • Project path CàDàEàFàHàK accounting for a duration of 2+7+4+2.17+10+6+7.33=36.33days .
  • Project path CàJ accounting for a duration of 2+16.33=18.33days

The longest path is CàDàEàFàHàK and is the critical path. Therefore, the project completion time is 36.33days.

Hence, The critical path is CàDàEàFàHàK and the project completion time is 36.33 days.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: Early start, Early finish, Late start, Late finish and slack for each activity.

Answer to Problem 19P

The Early start, Early finish, Late start, Late finish and slack for each activity is shown in Table 2.

Explanation of Solution

Given information:

Activity a m b t Immediate predecessor
A 3 6 8 8
B 2 4 4 4
C 1 2 3 3
D 6 7 8 8 C
E 2 4 6 6 B,D
F 6 10 14 14 A,E
G 1 2 4 4 A,E
H 3 6 9 9 F
I 10 11 12 12 G
J 14 16 20 20 C
K 2 8 10 10 H,I

Calculation of Early start, Early finish, Late start, Late finish and slack for each activity:

The AON diagram along with the time duration for each project activity is shown below.

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 3, Problem 19P , additional homework tip  3

Slack activity can be calculated by finding the difference LS-ES or LF-EF. ES, EF, LS and LF for the project as shown in the table below.

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 3, Problem 19P , additional homework tip  4

Table 2

The slack for each activity is shown in the above table

CàDàEàFàHàK is the critical path and therefore activities C, D, E, F, H and K have no slack.

The slack in activity A is 7.17 days, the slack in activity B is 5.33 days, the slack in activity G is 2.83 days, the slack in activity I is 2.83 days and the slack in activity J is 18 days.

Hence, the Early start, Early finish, Late start, Late finish and slack for each activity is shown in Table 2.

d)

Expert Solution
Check Mark
Summary Introduction

To calculate:The probability that the project will be completed in 40 days or less.

Answer to Problem 19P

The probability that the project will be completed in 40 days or less is 94.63%.

Explanation of Solution

Given information:

Activity a m b t Immediate predecessor
A 3 6 8 8
B 2 4 4 4
C 1 2 3 3
D 6 7 8 8 C
E 2 4 6 6 B,D
F 6 10 14 14 A,E
G 1 2 4 4 A,E
H 3 6 9 9 F
I 10 11 12 12 G
J 14 16 20 20 C
K 2 8 10 10 H,I

Calculation of probability that the project will be completed in 40 days or less:

Consider the expected project completion time of 36.33 days as the mean and the variance of the distribution σ2, is the sum of the variances of individual activities on the critical path which are C, D, E, F, H, and K (refer table 1)

Consequently,

σ2=0.11+0.11+0.44+1.78+1.00+1.78=5.22

Therefore the standard deviation is the square root of 5.22, which works out to 2.28

Calculate the z value as shown below

z=4036.332.28=1.61

From thez-factor table1.61 corresponds to 0.9463. The probability that the project will be completed in 40 days is 94.63%.

Hence, the probability that the project will be completed in 40 days or less is 94.63%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
What is Bitcoin? How important is it to businesses and individuals? How does it cause environmental damage and is that damage worth continued uses of Bitcoin? Read the following articles to help answer these questions: United Nations University. (2023, October 24). UN study reveals the hidden environmental impacts of bitcoin: Carbon is not the only harmful by-product. https://unu.edu/press-release/un-study-reveals-hidden-environmental-impacts-bitcoin-carbon-not-only-harmful-product#:~:text=Bitcoin%2C%20the%20most%20popular%20cryptocurrency,the%20worldwide%20Bitcoin%20mining%20network. Salam, E. (2023, April 26). Bitcoin is terrible for the environment – can it ever go green? The Guardian. https://www.theguardian.com/technology/2023/apr/26/bitcoin-mining-climate-crisis-environmental-impact
419 X .com/courses/1546/assignments/49499?module_item_id=111573 Unlimited Attempts Allowed ✓ Details Directions: Record a video of yourself giving a business presentation. Imagine you are tasked with researching a professional development topic on business communication for 40 coworkers. You are then expected to give a 4 - 5 minute presentation on the topic. Choose any topic related to business communication, such as intercultural communication, effective leadership, professional writing, etc. Research the topic and prepare a 4 - 5 minute presentation that could be given over video conference call (such as Zoom). You may use visual aids if you choose. Upload a video file of your presentation. Provide all needed citations. Requirements: 4-5 minutes long Contains visual and audio Create your own work; do not plagiarize Cite your sources using APA citations Choose a submission type T
acts Container chips (s 150 cussion: Conflict X + e.com/courses/1546/discussion_topics/15722?module_item_id=111559 24 Winter > Discussions > Week 8 Discussion: Conflict 时☆ 26 Replies, 26 Unread Week 8 Discussion: Conflict Write a 200 - 300 word discussion post based on the prompt below. Reply to at least one other student in 50 - 100 words. Can you think of a time when a conflict led to a new opportunity, better understanding, or other positive result? If not, think of a past conflict and imagine a positive outcome. Discuss the impact of this conflict on your workplace relationships, productivity, and innovation. Source: Business Communication for Success. (2015). University of Minnesota Libraries Publishing. Attribution-NonCommerical-ShareAlike. Edit View Insert Format Tools Table 12ptv Paragraph BIUA T2

Chapter 3 Solutions

EBK PRINCIPLES OF OPERATIONS MANAGEMENT

Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY