EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175859
Author: Munson
Publisher: VST
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 3, Problem 13P
a)
Summary Introduction
To draw: A network for the given situation.
b)
Summary Introduction
To determine: The activities on the critical path.
c)
Summary Introduction
To determine: The length of the critical path.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Roger Ginde is developing a program in supplychain management certification for managers. Ginde haslisted a number of activities that must be completed beforea training program of this nature could be conducted. Theactivities, immediate predecessors, and times appear in theaccompanying table:
a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?
(a) The critical path for the network activities shown below is?
(b) What is the completion time in weeks?
Refer attached image
Activity
Preceding
Time
A
-
8
B
-
10
C
A , B
5
D
B
8
E
C , D
6
Below is information about a project to implement a new manufacturing cell to assemble personal digital assistance devices
Calculate the expected time for all tasks and maintain one decimal place. Complete a critical path analysis. Complete forward and backward passes.
What is the critical path?
What is the project duration?
What is the latest start for Activity 4 "Secure patent?"?
Chapter 3 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The following represent activities in Marc Massoud's Construction Company project 3) Choose the correct network to represent this situation. OA SERTT D The critical path is b) Which activities are on the critical path? H c) What is the length of the critical path? The length of the critical path is weeks. (Enter your response as a whole number) ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (WEEKS) ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (WEEKS) 4 2 2 OB ABCD Q+0 Start B F В H 6 шиот F F. G OC. Startarrow_forwardA project network is shown below, with three time estimates (Optimistic Time-Most Likely Time-Pessimistic Time (in days)) for each activity in the network. a. Compute the expected time for each activity in the project network. b. Identify and list all possible paths in the project network. Compute the expected duration for each path in the project network. c. Identify the critical path(s) in the project network. What is the expected project completion time? d. Compute the variance of each activity on the critical path(s). e. Determine the project variance and project standard deviation. Use the PERT analysis results in 2(c) and 2(e) to answer questions (f), (g), (h), and (i) below:f. What is the probability that the project can be completed within 22 days of its start? g. What is the probability that the project can be completed within 16 days of its start? h. Determine the project deadline that gives this project a 78% chance of on-time completion. i. Determine the project deadline…arrow_forwardThe following represent activities in a major construction project. Draw the network to represent this project. Activity Immediate Predecessor A - B - C A D B E B F C, E G D H F, Garrow_forward
- A project has seven (7) main activities labelled A through G as shown in the below table which also shows their estimated duration times ( in weeks) and immediate predecessors. Activity a b Immediate Remarks predeccessor A 1 2 3 a = optimistic time 2 3 4 m = most likely time C 4 A b = pessimistic time 8 9 10 E 2 5 8 C,D 4 6. G 1 2 3 E (a) Develop a project network for this problem.arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors,and times appear in the accompanying table: a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?arrow_forward(please try to do math in handwritten) Use the following project data for problem 1 through 5 Activity name Predecessor Activity Activity Duration N 3 M 2 P M,N 4 3 P,Q R,S 2. 1. Prepare an AON Network Diagram 2. Identify all possible paths. Provide that information in a table. The heading of your table should as follow: Path Duration 3. Perform a forward pass and a backward pass. Display your result in an AON diagram.Usethe follow legend for your node(s) Activity ES EF Duration LS LF 4. Prepare a table summarizing the results of your Activity Schedule. The heading of your table should as follows: Activity name ES Slack EF LS LF 5. Identify the critical path. What is the project duration? 2. 4.arrow_forward
- A farm owner is going to erect a maintenance building with connecting electrical gen- erator and water tank. The activities, activity descriptions and estimated durations are given in the following table. Construct the AOA network for this project, identify the critical path and construct a Gantt chart for the project. Description Excavate Erect building Install generator Install tank Activity A Predecessor Duration 2 B A 6 A 4 D A E Install maintenance equipment В 4 F Connect generator and tank building B,C,D 5 G Paint finish В 3 H Check out facility E,F 2arrow_forwardConstruct the network for the following project and determine the following i) Critical Path ii) ES,EF,LS,LF iii) TF,FFarrow_forwardPlease help me experts to solve this problem. Thank you.arrow_forward
- You may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 42- week completion date requested by the owner. The Mueller project manager prepared the following project network. Start Activity A B с D E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. TI G H Optimistic Most Probable 4 6 6 weeks 3 6 5 10 A 5 8 7 12 5 9 8 B 15 6 Pessimistic 12 8 18 7 18 17 20 (b) What is the expected project completion time (in weeks)? 52 13 F E (a) Find the critical path. (Enter your answers as a comma-separated list.) A,C,E,G,H G H Finish (c) Based only on the critical path, what is the estimated probability the project can be completed in 42 weeks as requested by the owner? (Round your answer to four decimal places.) X (d) Based only on the…arrow_forwardEX6-6 (Algo) From the following information, develop... From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? ID A Survey site B Description C Excavate site Install power lines. D Install drainage E Pour foundation The project will take The critical path is The late start on Activity C is The slack on Activity C is The slack on Activity D is The early start on Activity E is Predecessor None A B B C, D. Time 4 5 4 3 days. days. days. days, days.arrow_forwardConsider a project for which the following activities and time estimates in weeks apply activity To tm tp 1-2 3 5 8 1-3 2 3 5 1-5 2 3 4 2-3 1 2 5 2-6 7 8 9 3-4 1 3 6 3-5 2 4 6 4-5 1 2 4 5-6 1 2 3 Draw the project network Compute the expected time and variance for each activity iii. Compute slack for each event and find the critical path Find the length of the critical path and the project duration Approximate the probability that activity 3 – 4 will have positive slack. What is the managerial implication of that probability?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY