EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175859
Author: Munson
Publisher: VST
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 3, Problem 15P
Dave Fletcher (sec Problem 3.12) was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, BF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
Activity
Time (weeks)
Immediate Predecessor(s)
Activity
Time (weeks)
Immediate Predecessor(s)
A
7
−
E
5
B
B
8
−
F
6
B
C
4
A
G
11
C, E
D
3
A
H
7
D , F
Part 2
Dave's earliest start (ES) and earliest finish (EF) are:
Part 3
Part 4
Part 5
Part 6
Part 7
Part 8
Part 9
Part 10
Dave's latest start (LS) and latest finish (LF) are:…
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
Activity
Time (weeks)
Immediate Predecessor(s)
Activity
Time (weeks)
Immediate Predecessor(s)
A
7
−
E
4
B
B
6
−
F
5
B
C
4
A
G
10
C, E
D
2
A
H
8
D , F
Part 2
Dave's earliest start (ES) and earliest finish (EF) are:
Part 3
Part 4
Part 5
Part 6
Part 7
Part 8
Part 9
Part 10
Dave's latest start (LS) and latest finish (LF) are:…
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS,
LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
Activity
A
B
C
D
Time
(weeks)
7
6
2
2
Dave's earliest start (ES) and earliest finish (EF) are:
Time
Immediate
Predecessor(s) Activity (weeks)
E
4
6
10
6
A
A
Activity
A
B
ES
0
0
F G H
EF
7
Immediate
Predecessor(s)
B
B
C, E
D, F
Chapter 3 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A E B F с G D H Dave's earliest start (ES) and earliest finish (EF) are: 6 7 3 2 A A Activity A ES EF 6 4 6 10 7 B B C, E D, Farrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: O Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) E F A B C D Dave's earliest start (ES) and earliest finish (EF) are: 5 8 00 2 2 Activity HOT G ES Н EF 5 5 5 10 7 B B C, E D.Farrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 7 - E 4 BB 8 - F 7 BC 4 A G 11 C, ED 1 A H 6 D , F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A 0 7 B 0 8 C 7 11 D 7 88 E 8 12 Part 7 F ? ? G ? ? H ? ?arrow_forward
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 6 - E 5 BB 8 - F 6 BC 2 A G 9 C, ED 3 A H 7 D , F Dave's earilest start (ES) and earliest finish (EF) are: Activity ES EF A 0 6 B 0 ? C D E F G Harrow_forwardCharlie Cook was able to determine the activity times for constructing his chemical contaminant tracking machine. Cook would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Q Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A B C D 7 8 2 1 Charlie's earliest start (ES) and earliest finish (EF) are: A A Activity A EFGH ES EF 7 5 7 11 8 B B C, E D, Farrow_forwardDave Fletcher was able to determine the activity times for constructing hi ser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity A B C D Time (weeks) 5622 Immediate Predecessor(s) A A Dave's earliest start (ES) and earliest finish (EF) are: Activity A B O ס ח ד 0 I Dave's latest start (LS) and latest finish (LF) are: F G H Activity Activity ES 0 0 5 5 EFGH 6 6 11 12 LS Time (weeks) 5 6 9 7 EF 156 7 7 11 12 20 19 LF Immediate Predecessor(s) B B C, E D, Farrow_forward
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Activity (weeks) 6 7 ABCO 3 2 Immediate Predecessor(s) A A D Dave's earliest start (ES) and earliest finish (EF) are: Time Activity (weeks) 4 EFGHI 6 10 7 Immediate Predecessor(s) B B C, E D,Farrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Dave's earliest start (ES) and earliest finish (EF) are: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A B C D 7 2 A Activity A F G H ES | FF 5 6 9 7 B B C. E D, Farrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Activity (weeks) A 6 B 8 с 2 D 1 Immediate Time Predecessor(s) Activity (weeks) E 3 F 7 A A Dave's earliest start (ES) and earliest finish (EF) are: G H 9 8 Immediate Predecessor(s) B B C, E D.Farrow_forward
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Dave's earliest start (ES) and earliest finish (EF) are: Dave's latest start (LS) and latest finish (LF) are: Activity A B C D Time (weeks) 7 6 2 2 Immediate Predecessor(s) A A Activity A C D F G H Activity H Time Activity (weeks) E 4 F 6 G 10 H 6 ES 0 0 7 7 6 6 10 12 LS 14 EF 7 9 1228 10 20 LF Immediate Predecessor(s) B B C, E D, F 27arrow_forwardThe Farmer's American Bank of Leesburg is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates, as shown in the following table. Use POM- QM to analyze this project. According to the result of POM-QM, the expected project completion time is (type number only, no text) Activity a b C d C f 8 k Activity Description Position recruiting System development System training Equipment training Manual system test Preliminary system changeover Computer-personnel interface Equipment modification Equipment testing System debugging and installation Equipment changeover Activity Predecessor a a b, c b, c d, e d, e h f.g a 5 3 4 5 I 1 3 Time Estimates (weeks) 1 1 2 5 m 8 12 7 8 I 4 6 2.5 1. 2 8 b 17 15 10 23 1 13 9 7 1 2 11arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Activity (weeks) Dave's earliest start (ES) and earliest finish (EF) are: Dave's latest start (LS) and latest finish (LF) are: The slack times are: The activities on the critical path are The total project completion time for Dave = weeks. ▼ Time Immediate Activity (weeks) Predecessor(s) A 6 8 3 3 B C D A A Activity A B C D E F G H Activity H G F E D C B A Activity A B C D E F G H | E F 6 G ES □ 0 H 8 T П LS 15 14 8 9 12 11 0 5 Slack || EF 6 13 22 23 5 7 9 8 LF | | L | | Immediate Predecessor(s) B B C, E D,Farrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY